Requests Exemption from Requirements of 10CFR50.48 Re Status of Certain Fire Protection Mods.Delay Necessitated by Problems in Procuring Hardware.New Implementation Date Is Scheduled for 820119
ML20032E673
Person / Time
Site: Peach Bottom  
Issue date: 11/13/1981
From: Daltroff S
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
NUDOCS 8111200797
Download: ML20032E673 (2)


Text

. 'm o

PHILAD ELPHIA ELECTRIC COM PANY 23O1 MARKET STREET A

P.O. BOX 8699 3

(f A

g 1881 -1981 PHILADELPHIA. PA.19101 1.

y,

SHIELDS L. DALTROFF ulE*lic"/E'b 5. U b '*2u8,'"y"**

?.

, p/

:g$

November 13, 1981 Re: Docket Nos. 50-277 50-278 Mr. Darrell G.

Eisenhut, Director Division of Licensing U.S. Nuclear Regulatory Commission Washington, DC 20553

SUBJECT:

Request for Exemption from 10 CFR 50.48 for Peach Bottom Atomic Power Station

Dear Mr. Eisenhut:

This letter supplements our letter of October 14, 1981 (J.

W.

Gallagher to D.

G.

Eisenhut) relating to the status of certain fire protection modifications, and requests, pursuant to Section 50.12 of the Commission's regulations, exemptions to the implementation schedules identified in 10 CFR 50.48, subsections (c)(2) and (d)(2).

Relief from the schedule is necessitated by l

unforeseen delays in the procurement of some of the hardware for the modifications described in the October 14, 1981 letter, as l

well as the following additional modifications: electrical l

supervision of fire doors as approved in the staff's Supplement l

No. 1 to the Safety Evaluation of the Peach Bottom Atomic Power j

Station Fire Protection Program, item 3.2.6 (R.

W.

Reid to E.

G.

l Bauer, dated August 14, 1980).

The delivery schedule of the hardware and our request for an extension of the completion date from November 17, 1981, to January 19, 1982, were discussed in a

(

telephone conversation with the staff's Peach Bottom Project Manager on November 6, 1981.

l 1

0 p

Rv?

Ao i

8111200797 811213 DR ADOCK 05000277 PDR

f.

<a

/

Mr. Darrell G.

Eisenhut Page 2 Pursuant to 10 CFR 170.22, Philadelphia Electric proposes that this exemption be considered as Class II for Unit 2, and Class I for Unit 3.

A check payable to the U.S.

Nuclear Regulatory Commission in the amount of $1600 is enclosed.

Very truly yours,

)