IE Insp Rept 50-346/81-16 During Sept 1981.Noncompliance Noted:Failure to Sign Maint Work Orders on Completed Maint Activities
ML20032C821
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 10/15/1981
From: Mcgregor L, Reyes L, Rogers W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20032C815 List:
References
50-346-81-16, IEB-81-02, IEB-81-2, NUDOCS 8111110763
Download: ML20032C821 (6)


See also: IR 05000346/1981016

Text

_ _ _ _ _

. _ _ _ - _ _ - _ - _ _ _ _ _

,

.

U.S. NUCLEAR REGULATORY COMMISSION

l

OFFICE OF INSPECTION AND ENFORCEMENT

l

l

REGION III

l

Report No. 50-346/81-16

Docket ho. 50-346

License No. NPF-3

Licensee: b ledo Edison Company

Edison Plaza, 300 Madison Avenue

Toledo, OH 43652

Facility Name: Davis-Besse Nuclear Power Station, Unit 1

Inspection At:

Oak Harbor, OH

Inspectio1 Conducted: September 1-4, 8-11, 14-15, 21-25, and 28-30, 1981

/wJL e Tv:

y

Inspectors:

L. A. Reyes

/8 //5 /8/

fO:>Nf ,f

W. G. Rogers

/C //f[8/

_

'l )$ 4:Yti e-

Approved By:

L. G. McGrego , Acting Chief

/8

D/8[

-

Reactor Projects Section 2B

Inspection Summary

Inspection on September 1-4, 8-11, 14-15, 21-25, and 28-30, 1981 (Report

No. 50-346/81-16)

Areas Is.;pected: Routine, unannounced inspection of followup of previous

inspection items, Operational Safety Verification, maintenance activities,

Monthly Surveillance Observations, followup on Licensee Event Reports, IE

Bulletin followup and Plant Trip on September 3, 1981. The inspection in-

volved a total of 202 inspector-hours onsite by two NRC inspectors incl.uding

59 inspector-hours onsite during offrhifts.

Results: Of the seven areas inspect 2d, no items of noncompliance or

deviations were identified in six areas, one apparent item of noncompliance

was identified in another area (failure to sign Maintenance Work Orders on

completed maintenance activities).

8111110763 811028

PDR ADOCK 05000346

0

PDR

_

.

.

.

DETAILS

1.

Persons Contacted

  • T. D. Murray, Station Superintendent

B. Beyer, Assistant Station Superintendent

  • S. Quennoz, Assistant Station Superintendent

P. Carr, Maintenance Engineer

  • J.

Werner, Administrative Coordinator

D. Miller, Operations Engineer

D. Briden, Chemist and Health Physicist

J. Hickey, Training Supervisor

L. Simon, Operations Supervisor

G. Daft, Operations QA Manager

  • J. Greer, QC Supervisor
  • Denotes those attending the exit interview on September 22, 1981.

The inspectors also interviewed other licensee employees, including

members of the technical, operations, maintenance, I&C, training and

health physics staff.

2.

Followup On Previous Inspection Items

50-346/80-12-01 (Closed) Open Item: Loss of gaitronics during the

April 19, 1980 event.

Procedure SP 1107.09, Instrument AC System

Procedure, was revised to allow the inverters to be supplied from

the DC Bus when the normal feed for the regulated rectifiers from

motor control centers E12A or F12A are to be de-ernegized. The

licensee has upgraded the internal communication system of portable

radios by installing a passive antenna to improve communication at

the frequencies used at the station. The use of fifteen (15) two

channel portable walkie-talkie radios is covered under administrative

memorandum No. 14.

Management review of the April 19, 1980 event

resulted in increased review of abnormal electrical lineup during

outages.

50-346/81-03-06 (Closed) Deviation: Failure to review and alprove

Procedure AD 1805.00 by QA Revision 16.

The procedure was reviewed

and approved 'ay QA on September 4, 1981.

i

50-346/81-03-03 (0 pen) Noncompliance: Example, Failure to Update

Control Room Procedures File. During a review of the procedure file

at the auxiliary shutdown panel the inspector found that Procedures

SP 1106.16 and AD 1839.02 were not the latest revision.

3.

Operational Safety Verification

The inspector observed control room operations, reviewed applicable

logs and conducted discussions with control room operators during

the month of September. The inspector verified the operability of

selected emergency systems, reviewed tagout records and verified

-2-

-

-

. - -

.

-

-

- - -

--

- _ - - _ _ _ _ _ _

. _ _ _ _ - - - - _ - - - . - - - - - - - - - - - - - - - _ - - - - - - - . - _ _

-

.

.

proper return to service of affected components. Tours of the

auxiliary building and turbine builling were conducted to observe

plant equipment conditions, including potential fire hazards, fluid

leaks, and excessive vibrations and to verify that maintenance

requests had been initiated for equipment in need of maintenance.

The inspector by observation and direct interview verified that

the physical security plan was being implemented in accordance with

the station security plar.

The inspector observed plant housekeeping / cleanliness conditions and

verified implementation of radiation protection controls.

During the

month of September, the inspectar walked down the accessible portions

of the Emergency Diesel Generator No. 2 systems to verify operability.

The inspector also witnessed portions of the radioactise waste system

controls associated with radwaste shipments and barreling.

During a review of the locked valve log the inspector noticed that both

ECCS room coolers for No. 2 ECCS room were valve out of service.

Cooler

No. 1-1 was isolated on January 25, 1981 and cooler No. 1-2 was isolated

on September 12, 1981. On September 15, 1981 the inspector notified the

licensee that FSAR Section 6.3.6 list the ECCS room coolera as essential

auxiliary equipment to support the ECCS operation during a LOCA. Upon

notification the licensee returned No. 1-1 cooler to service.

The licensee has initiated Deviation Report 81-140 and is working with

the Architect Engineer to determine when in the ECCS actuation mode (in-

jection or recirculation) are the ECCS room coolers required. Repairs

(

are underway to return the ccolers to operable status. This item is

'

unresolved pending the licerisee submittal of the above mentioned

-

information.

(50-346/81-16-02)

,

On September 25, 1981 while conducting a plant tour the inspector found

several cracks in the auxiliary building floor drain piping. All cracks

found were adjacent to welds in the piping. The licensee is removing a

section of the pipe for analysis and will conduct repairs once the failure

mechanism is identified. The inspectors will followup the licensee's

corrective action.

(50-346/81-16-03)

4.

Maintenance Activities

Duric. .ne review of the licensee maintenance activities of safety

related systems and components the inspector determined that a serious

breakdown exists in the administrative controls used to implement the

maintenance program. The Maintenance Work Order ($43) system estab-

lished to control the conduct of maintenance is not enforced as per the

requirements of Administrative Procedure AD 1844.00, " maintenance."

This procedure requires that upon completion of maintenance, the

responsible foreman reviews and approves the MWO and forwards it to

the Shif t Supervisor for any testing required.

Once the testing is

completed the shif t supervisor should sign the MWO and forward it to

the maintenance engineer.

-3-

..

.

__

.

.

-

-

.

-

.

.

.

'

'

q

Contrary to this requirement the licensee'is using a verbal notification

'

fron. the maintenance foreman to notify the Shift Supervisor of the com-

pletion of maintenance. Subsequent to this verbal notification the Shift

Supervisor is testing the equipment and declaring it operable.

The above mentioned practice has resulted in numerous W0s implemented

during the 1979 and 1980 outages to be shown outstanding when indeed.the

work was completed.

In addition, since the FN0 and work performed is not

routed to Quality Control for review and approval there is no assurance

that the work conducted and the parts used were of the required quality.

This has resulted in the operation of the unit with outstanding Noncon-

formance Reports issued in the parts used or the work conducted.

The below listed tN0s are examplec of systems and components and

the equipment declared operable without the completion of an MWO.

a.

Emergency Diesel Generators

WO 80-275

Change out turbocharger drive gear

,

MWO 81-2602

Obtain backlash readings

b.

Auxiliary Feedwater System

WO 79-317

Suction strainers for auxiliary feedwater pump

MWO IC-572-81 Static "0"

ring pressure switch

i

c.

Core Flood System

4

!

.

MWO 77-2024

Work in valves CFLA and CF1B

!

MWO 80-3400

Repair valve CF-30

d.

Makeup and Purification System

MWO 79-1985

Repair Makeup Pump 1-1

l

e.

Reactor Protection System

1

.

MWO IC-523-80 Ground between RPS Ch. 3 and VLPM cabinet

I

f.

Reactor Coolant Pumps

3

WO 80-4163

Replacement of RCP Seal 1-2-1

g.

Containment Ventilation System

'

MWO C-78-390

Cooling duct for REs 2004 through 2007

Another example of breakdown in the Administrative Controls of the

maintenance program is the implementation of tNO 77-424. This INO

was signed as completed on September 13, 1978. The work covered by

this FNO included the installation of grouted seismic supports on

i

the Steam Feedwater Rupture Control System Instrument lines. On

1

September 4, 1981 the inspector found that these supports were not

painted or grouted.

!

.

- 4-

. . - . . . - , _ , _ . ~ _ . _ . . . _ _ . . _ _ _ _ - _ . _ _ .,_

_ - - . _ _ , , _ , . _ - . _ _ . _ . . _ - . . ,

. _ _ - _

7

-

.

.

.

On October 30, 1981 Maintenance Technicians working under FNO 81-3496

-removed the Reactor Coolant Drain Tank Rupture disk. No tagging was

performed on the isolable lines that discharge into the drain tank.

Water from the isolable line was spilled on the floor resulting in

an unplanned release of less than two curies of noble gasses. The

Administrative Controls for the conduct of maintenance require that

tagging be conducted prior to the performance of maintenance.

Failure to comply with the requirements of Administrative Procedure

A0 1844.00 " Maintenance" is considered an item of noncompliance.

No additional items of noncompliance or deviations were identified.

5.

Monthly Surveillance Observation

The inspector observed technical specifications required surveillance

testing on the Reactor Protection System Chann+1 No. 3 (ST 5030.02)

and verified that testing was performed in accordance with adequate

procedures, that test instrumentation was calibrated, that limiting

conditions for operation were met, that removal and restoration of the

affected components were accomplished, that test results conformed with

technical rcecifications and procedure requirements and were reviewed by

personnel other than the individual directing the test, and that any

ceficiencies identified during the testing were properly reviewed and

rnsolved by appropriate management pe sannel.

The inspector also witnessed portions of the following test activities:

RCS Water Balance (ST 5042.02)

AFW No. 2 Morthly Test (ST 5071.01)

No items of noncompliance or deviations were identified.

6.

Licensee Event Reports Followup

Through direct observations, discussions with licensee personnel, and

review of records, the following event reports were reviewed to deter-

mine that reportability requirements were fulfilled, immediate corrective

action was accomplished, and corrective action to prevent recurrence had

been accomplished in accordance with technical specifications.

80-33

Hydraulic Snubber deficiencies

81-39

Cantainment Personnel Airlock Surveillance Exceeded 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />

81-42

U.:gative pressure door 302 broken latching mechanism

81-46

Unsealed Penetration in safety related firewall

'

81-47

Quadrant Power tilt exceeded

81-48

RCS Flow not recorded during deboration

i

81-49

RPS channel Intermediate Range Failed High

81-51

BWST Channel 3 level Failed High

No items of noncompliance or deviations were identified.

l

-5-

,

- . -

. ,- - --

.. .- -.-.- .--,

. ~ . . - - .


- - - - . - - -

..

.

7.

IE Bulletin Followup

For the IE Bulletins listed below the inspector verified that the

written response was within the time period stated in the bulletin,

that the written response included the information required to be

reported, that the written response included adequate corrective

action commitments based on information presentation in the bulletin

and the licensee's response, that licensee management forwarded copies

of the written response to the appropriate onsite management representa-

Lives, that information discussed in the licensee's written response

was accurate, and that corrective action taken by the licensee was as

described in the written response.

81-02

Supplement 1 failure of gate valves to close against

differential pressure.

No items of noncompliance or deviation were identified.

8.

Plant Trips

Following the plant trips on September 2, 1981, the inspector

ascertained the status of the reactor and safety systems by observation

of control room indicators and discussions with licensee personnel con-

cerning plant parameters, emergency system status and reactor coolant

chemistry. The inspector verified the establishment of proper com-

munications and reviewed the corrective actions taken by the licensee.

All systems responded as expected, and the plant was returned to

operation on September 3, 1981.

No items t! noncompliance or deviations were identified.

9.

Unresolved Items

Unresolved items are matters about which more information is required

in order to ascertain whether they are acceptable items, items of non-

compliance, or deviations. The unresolved items disclosed during the

inspection are discussed in Paragraph 3.

10.

Exit Interview

The inspector met with licensee representatives (denoted in Paragraph 1)

throughout the month of September.

-6-