Responds to V Gilinsky & PA Bradford Requests Made During Licensee Presentation to Commission on 811014. Gpu Accident Review Task Force Final Summary Rept Encl
ML20032B091
Person / Time
Site: Crane  
Issue date: 11/02/1981
From: Blake E
SHAW, PITTMAN, POTTS & TROWBRIDGE
To: Palladino N
NRC COMMISSION (OCM)
Shared Package
ML20032B092 List:
References
ISSUANCES-SP, NUDOCS 8111040409
Download: ML20032B091 (3)


Text

.

e41 SHAW, PITTMAN, PoTTs & TROWBRIDGE 1800 M STRE CT. N. W.

WASHINGTON, O. C. 20036 cs.MSay D.potrS MARM AUGENSLICK oAvto M. RVSENSrctN MOWAmo H. SMAFFERM AN PC#Rle'kTEWt" ooc E"Lr'o';'.1""l,;ES

' ^

' " ~

"^Jr'3'.i"^E' *L *

E!o*?r"'"

  • E"'t*JJ 4

!Z'."1"C J "",

'"a";'^.tr!R

'f,*2"c,SM"

    • l" * "': M ' ?fR1, A

HMtLLap o. SOSrWICM SMCLDON J. WEISCL 1ELcCOP4ER RAND L. ALLEN DELISSA A. RIDOWAY EL SAScrH M CrON DAY D WRcNC M LLcR E Ge M

. JR.

rR CM ICKE 2'.t C hit NocR l'3"l'lJo"'*S tfA'i.'Rr' OYA,v^ "^lu'^lS,.cocL

^"E!c'l',,E"^"l'N!

  • ^

lie *E * **CY"of"JA. sR.

E*2JEiv"t M"

003%!"' ice, ie.

!!" 2 " "^R"2"'

E^!fOls""It'o.LL

'?ifdt.",.urrtE R

  • 7 ["S,^*"*[*~ '

Oll0" "r*^c",to

"7ff f. 0't"c*le",~.N m

r:R:.=SS.,r,

=:=":-~

=~."::::a-

==:==.

  • ffli'RISO'l~~ '"

"'."Jo'i*en'!.".

"iE"'."ff"!!",.

C.'Olo"20%'",,,

WRivcwS o RcCr o.*L Nu-en R EcNLY WE.BS. rem RoscR18 pQ/asaNS BONNIc S. GOrTLIES

.r 4.NicL. Reco. sR.

SrcvCN uauC^*

822-1084 Novembe

'*Q, W

/\\

The Honorable Nunzio Palladino DOLMETEi!

Chairman J

USHRC United States Nuclear Regulatory

,(.

NOVO 31981 )

Commission 4-2/.1 m -2 PS:09 vis, %

=8 5mussa Washington, D.C.

20555 M

OFFICE OF SECRETARY In the Matter oi

?

00CKETjigERVICE Metropolitan Edison Company (Three Mile Island Nuclear Station, Unit No. 1)

Docket No. 50-289 SP (Restart)

Dear Mr. C.. airman:

The purpose of this letter is to respond to requests made by Commissioner Gilinsky and Commissioner Bradford during Licensee's presentation to the Commission on TMI-l Restart held on October 14, 1981.

In response to Commissioner Gilinsky's request (Tr. 89),

enclosed is a copy of the GPU Accident Review Task Force Final Summary Report.

In response to requests of Commissioner Bradford, we agreed to recap the testimony of Mr. Charles Mell given to the Senate investi-gating committee (Hart Investigation) concerning conversations j

between TMI Unit II and the system load dispatcher prior to the accident.

Tr. 149.

DS ]

We have reviewed Mr. Mell's testimony and discussed with Mr.

3 Mell the substance of his testimony.

Mr. Mell, who was a CRO trainee during the period ha recalls a telephone call being made,

/

teatified that the shift supervisc' made the telephone cal) to the h!O404$9 of000289 p

ADOC 1102 PDR

f-SHAW, PITTMAN, POTTS & TROT / BRIDGE Chairman Nunzio Palladino November 2, 1981 Page Two system load dispatcher office.

The Reading system load dispatcher would have been the dispatcher contacted by the shift supervisor.

Mr. Mell recalls the person having a telephone conversation with the dispater.er as being Mr. Joseph Chwastyk.

Mr. Chwastyk does not recall the instance Mr. Mell recollects, but stated that he makes many calls to the dispatcher and the telephone call Mr. Mell recollects could have been a call during which he had a general discussion on scheduling of a plant shutdown.

Mr. Chwastyk pointed out that if there had been an immediate safety issue, he would have taken the plant off the line.

We have attempted to secure a copy of the tape or written tran-script of the telephone conversation between Tic. Chwastyk and the dispatcher.

The procedure for retention of the tapes of telephone conversations with the system load dispatcher pre >:1udes our being able to retrieve the contents of that particular telephone conver-sation.

Tapes of telephone conversations with the system load dis-patcher are retained for a thirty-day period after which the tapes are cleared and reused.

An exception occurs if a timely request has been made to retain a tape or reduce it to written form.

This procedure creates a thirty-day rollover for tapes of telephone con-versations between a plant and the system load dispatcher.

There-fore, there are no tapes and we know of no transcripts having been made of the telephone call Mr. Mell recollects.

Respectfully submitted, M.94 A Ernest L.

Blake, Jr.

Counsel for Licensee ELB/tjc Encl.

cc:

(w/ enclosure)

Commissioner Victor Gilinsky Commissioner Thomas Roberts Commissioner John Ahearne Commissioner Peter Bradford Samuel J. Chilk, Secretary Administrative Judge John H. Buck Administrative Judge Christine N.

Kohl Administrative Judge Ivan W. Smith Administrative Judge Walter H.

Jordan Administrative Judge Linda W.

Little Administrative Judge Gary L. Milhollin (continued next page)

F SHAW, PITTMAN, POTTS & TROWBRIDGE Chairman Nunzio Palladino November 2, 1981 Page Three cc:

(continued)

James R. Tourtellotte, Esquire Mr. Robert Q. Fcllard Robert Adler, Esquire Thomas J. Germine, Esquire John A. Levin, Esquire John E. Minnich, Chairman, nauphin County Board of Commissioners Walter W. Cohen, Esquire Jordan D. Cunningham, Esquire Ms. Louise Bradford, TMI ALERT Ellyn R. Weiss, Esquire Mr. Steven C. Sholly Ms. Gail Phelps, ANGRY William S. Jordan, III, Esquire Ms. Judith H. Johnsrud Mr. Marvin I. Lewis Mr. Norman Aamodt Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Appeal Board Panel Docketing and Service Section, NRC i

l t

I l

t

..