a PHILADELPHIA ELECTRIC COMPANY 23O1 M ARKET STREET P.O. BOX 8699 1881 -1981 PHILADELPHIA. PA.19101 SHIELDS L. D ALTROFF ELacTn c PR c ton October 14, 1981 Docket Nos. 50-277 50-278 Mr. Darrell G.
Eisenhut, Director Division of Licensing US Nuclear Regulatory Commission Washington, DC 20555
SUBJECT:
Implementation of Appendix R Fire Protection Requirements for Peach Bottom Atomic Power Station
Dear Mr. Eisenhut:
This letter requests exceptions to the implementation schedule identified in 10CFR 50.48 for the Peach Bottom Atomic Power Station and thereby modifies the commitments made in a letter dated March 20, 1981 (S. L. Daltroff, Philadelphia Electric Company to D.
G.
Eisenhut, NRC).
Additionally, we are proposing a revision to a commitment in the referenced letter that is consistent with the provisions of 10CFR 50, appendix R.
The schedule adjustments requested involve some of the modifications required by 10CFR 50.48, as well as the commitments l
in the March 20, 1981 letter referenced above, to be implemented by November 19, 1981.
Completion of the modifications are contingent on many factors, including the timely delivery of eculpment and material utilized in the installation.
We propose a revised completion date of January 19, 1982 for the subject-
~
modifications, provided the necess'iry equipment is delivered by November 2, 1981.
We will advise the Commission of any slippage l
in this proposed schedule resulting from procurement delays beyond November 2, 1981.
The revised schedule would apply to the following modifications:
8110300 @
- -