ML20031G641

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-313/81-25 & 50-368/81-24 on 810722-0821. Noncompliance Noted:Failure to Submit Ler,Inoperable Penetration Fire Barrier & Inoperable Control Room Ventilation Intake Duct Monitor
ML20031G641
Person / Time
Site: Arkansas Nuclear  
Issue date: 09/30/1981
From: Callan L, Hunnicutt D, Johnson W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20031G639 List:
References
50-313-81-25, 50-368-81-24, NUDOCS 8110230414
Download: ML20031G641 (10)


See also: IR 05000313/1981025

Text

. . .

.

.

.

.

I

APPENDIX B

U. S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMEllT

'

REGION IV

i

Dockets:

50-313/81-25

License:

DPR-51

50-368/81-24

NPF-6

i

Licensee:

Arkansas Power and Light Company

Post Office Box 551

Little Rock, Arkansas 72203

Facility Name:

Arkansas Nuclear One (AN0), Units-1 and 2

Inspection at:

AND Site, Russellville, Arkansas

,

Inspection Conducted: July 22-August 21, 1981

,

Inspectors:

7'[ [)

CA

[h

9-Fo-3 i

W. D. Johns'on, Senior Resident Reactor Inspector

Date

?~ i? b

h

4-30-31

L. J. Caihn, Resident Reactor Inspector.

Date

l

Approved:

7- !.

b

9 9 0-Bl

D. M. Hunnicutt, Chief, Reactor Projects Section 2

Date

Inspection Sunaary

,

Inspection conducted during period of July 22-August 21, 1981

j

(Report 50-313/81-25)

Areas Inspected:

Routine, announced inspection including operational safety

verification, surveillance, maintenance, follow-up on previously identified

items, and follow-up on IE Circulars.

The inspection involved 124 inspector hours on site by two NRC inspectors.

Results:

Within the five areas inspected, no violations or deviations

were identified.

.

4

8110230414 811006

PDR ADOCK 05000

0

_ . . . _ . . _ , _ _ . _ . . - . _ _ _ . . . . _ . . . _ _ _ , , _ , _ _ _ . _ . . _ . _ _ . _ , _ . _ . , , _ . _ . _ . _ . . _ _ . _ _ . _ . _ . . _ _ _ - _ _ _ , _

2

i

Inspection conducted during period of July 22-August 21, 1981

Report 50-368/81-24)

Areas Inspected:

Routine, announced inspection including operational safety

verification, surveillance, maintenance, follow-up on previously identified

items, and follow-up on IE Circulars.

The inspection involved 120 inspector hours on site by two NRC inspectors.

Rasults: Within the five areas inspected, three apparent violations were

Identified in two areas (Failure to submit Licensee Event Report, paragraph 2;

inoperable penetration fire barrier, paragraph 3; and inoperable control

room ventilation intake duct monitor, paragraph 3).

l

1

.

.

3

DETAILS SECTION

1.

Persons Contacted

J. P. O'Hanlon, ANO General Manager

G. H. Miller, Engineering & Technical Support Manager

B. A. Baker, Operations Manager

T. N. Cogburn, Plant Analysis Superintendent

E. C. Ewing, Plant Engineering Superintendent

L. Sanders, Maintenance Manager

J. McWilliams, Unit 1 Operations Superintendent

J. Albers, Planning and Scheduling Supervisor

D. D. Snellings, Technical Analysis Superintendent

M. J. Bolanis, Health Physics Superintendent

L. J. Dugger, Special Projects Manager

L. Taylor, Operations Technical Engineer

R. Tucker, Electrical Maintenance Superintendent

L. Humphrey, Administration Manager

J. Lamb, Safety and Fire Protection Coordinator

J. C. Garrett, Materials Management Supervisor

B. Hampton, Stores Supervisor

L. Schempp, Manager of Nuclear Quality Control

B. Beckham, QC Inspector

B. West, I&C Supervisor

C. Cole, Planning and Scheduling Coordinator

The inspectors also contacted other plant personnel, including operators,

technicians and administrative personnel.

2.

Follow-up on Previously Identified Items (Units 1 & 2)

(Closed) Unresolved Item 368/8120-01:

The effect of missed surveillance

on system operability.

The licensee continues to take the position that the failure to perform

a surveillance requirement within the specified time interval does not

affect the OPERABILITY requirements for a Limiting Condition for

Operation (LCO).

As a result of this position, the licensee did not

submit to the Director of NRC Region IV within thirty days a written

report describing the conditions discovered on June 26, 1981, that

led to operation in a degraded mode permitted by LCO 3.8.2.5, Con-

tainment Penetration Conductor Overcurrent Protective Devices.

Specifically, on June 26, 1981, the licensee determined that

Surveillance Requirement 4.8.2.5a had not been performed since

September 12, 1978, and, therefore, had not been performed in

the specified time interval (every 18 months).

In accordance with

'

Technical Specification 4.0.3, which states, in part, that "Per-

formance of a Surveillance Requirement within the specified time

interval shall constitute compliance with OPERABILITY require-

ments for a Limiting Condition for Operation . . .

the affected

"

,

containment penetration conductor overcurrent protective devices

then became technically inoperable until Surveillance Requirement 4.8.2.5a was successfully completed on June 27, 1981.

The licensee's

.

4Tt-*-#

a

hg'-M--yrym.e

-ywq.yy

p My =-rya w99 T m y-p-e,Ww 9 wy

ysww+ * svr-w g emy'W 9wy9-giry*g-+-qwy

ow-e*we'a-

r---'*4

  • g-

w-

<-g-g-

erw't-'--FM

+-ee-m-

-

r*E"T

MP

FT T

4*f-"'-"F~~W-"'T*'"CD'

'

.

4

failure to submit, as required by Technical Specification 6.9.1.9b, a

written report within thirty days to the Director of NRC Region IV

describing this event constitutes an apparent violation (368/8124-02).

(0 pen) Open Item 313/8111-02; 368/8110-04:

Updating plant drawings

following design changes.

In March 1981, the inspector expressed concern to ANO management that

plant operation could be adversely affected if important plant

drawings are not maintained current to show actual system status.

Due

to the delay in updating plant drawings following design changes,

Operations Department personnel have found it necessary to append

informal sketches reflecting the as-built systems to plant drawings.

Although copies of DCP's are protided to the Control Room, it is a

time consuming research task to review the necessary DCP's and

integrate the information contained in several DCP's into a form

useful for plant operation.

The licensee was encouraged to develop

a system which would ensure that plant drawings are updated in a

timely manner following design changes.

This condition still exists.

Many of the design changes which wire

completed on Unit 1 during the first quarter of 1981 are not yet

closed out and reflected in plant drawings.

The licensee's response

to violation 313/8111-01 included a commitment to place the drawing

revision process under the control of Plant Engineering instead of

the Corporate Office with a goal of improving the timeliness and

control of the drawing revision process.

The estimated completion

date for this change was given as December 31, 1981.

Section 5.5.2 of the Arkansas Power & Light Quality Assurance Manual

for Operations states, " Applicable instructions, procedures and

drawings shall be reviewed and revised, as necessary, following any

modifications to the plant." The NRC inspector's position is that

updated drawings shall be issued and available to operations

personnel at the time that a modified safety related system is

turned over to the Operations Department following installation of

a design change.

The licensee has underway a project to close old Design Change Packages

with the assistance of a contractor.

The licensee is urged to complete

this project in a timely manner and to develop a system to implement

the above position.

This item remains open and has been reclassified

as an unresolved item pending appropriate licensee action.

3.

Operational Safety Verification (Units 1 and 2)

The NRC inspectors observed control room operations, reviewed applica-

ble logs and conducted discussions with control room operators.

The

inspectors verified the operability of selected emergency systems,

re/iewed tagout records and verified proper return to service of

-

..

.

-- - ,.

-

-. -

l

i

.

.

l

l

5

i

l

l

affected components.

Tours of accessible areas of the units were

conducted to observe plant equipment conditions, including potential

fire hazards, fluid leaks, and excessive vibrations and to verify that

maintenance requests had been initiated for equipment in need of

maintenance.

The inspectors, by observation and direct interview,

verified that the physical s:curity plan was being implemented in

accordance with the security plan.

The inspectors observed plant housekeeping / cleanliness conditions and

verified implementation of radiation protection controls.

The

!

inspector walked down the accessible portions of the " RED" Engineered

l

Safeguards Electrical Distribution System for Unit 2, the Unit 1

"A" High Pressure Injection, and the Unit 2 "A" diesel generator

fuel oil and air start s.vstems to verify operability.

The inspector

also witnessed portions of the radioactive waste system controls

associated with radwaste shipments and barreling.

These reviews and observations were conducted to verify that facility

operations were in conformance with the requirements estaclished

under Technical Specifications, 10 CFR, and administrative procedures.

!

Penetration Fire Barrier

During a tour of the Unit 2 Auxiliary Building, the NRC inspector noted

l

that the removal of a ventilation exhaust fan from above the southwest

corner of the ceiling for the North Engineered Safeguards Switchgear

Room (which contains Engineered Safeguards electrical bus 2A3) exposed

an approximate 2 ft. x 2 ft. hole through the ceiling.

The inspector

further noted that paper trash and other debris had been discarded

into the opening from above so that a significant amount of flammable

trash had collected in the various safety-related cable trays below

the opening.

Since the ceiling to the North Engineered Safeguards

Switchgear Room comprises part of the penetration fire barrier for

that safety-related area, the licensee ;s required by Unit 2

Technical Sepcification 3.7.11 to station a continuous fire watch

cn at least one side of the nonfunctional penetration within an

i

hour.

Contrary to the above, although the hole in the southwest

corner of the ceiling of the North Engineered Safeguards Switchgear

Room had existed for at least one day, the NRC inspector found

that no fire watch was stationed at 1400 on August 11, 1981.

This

is an apparent violation (368/8124-01).

Constant Air Monitors

The NRC inspector noted during various tours of the Unit 1 and 2

Auxiliary Buildings that the costant air montiors (CAMS) were not

being adequately maintained.

One of the CAMS (NMC 009 located on

the 335' level in the Unit 2 Auxiliary Building) was found to be

,,_ _ ,_. _-_... _ . . _ . _ _ . _ . .

, _ . _ _. _ _ _ .__,,__ . _ __.-

,-.,,.._ _ , _ - _ _ .-

_

-

.

6

inoperable on July 31, 1981, and appeared to have been almost

continuously inoperable since about the end of May 1981.

Problems

relating to inadequate care and maintenance of CAMS were identified

in paragraph 4.5.6 of a NRC Health Physics appraisal conducted during

the period October 27 - November 7, 1980 (Docket Nos. 50-313/80-20 and

50-368/80-20), and since then the licensee has developed and imple-

mented Procedure 1602.22, " Operation of NMC Continuous Air Monitor."

However, it appears that the CAM maintenance program requires additional

improvement in order to attain adequate reliability and operability

,

of these units.

This item will remain open pending the inspector's

determination that the CAMS are being adequately maintained (313/8125-01;

368/8124-03).

Fire Detection Systems

The in pector is concerned about the present status of the Unit 1 and

Unit 2 Fire Detection Systems, specifically with respect to the system's

ability to meet the operability requirements of Technical Specification 3.5.5 for Unit 1 and 3.3.3.8 for Unit 2.

In the case of the Unit 1

Fire Detection System, the inspector's concern stems from the chronic

electrical problems the system has experienced during the past few

months. Although it appears to the inspector that the actual heat

and smoke detectors associated with the system are indeed operable

and will alarm in the control room as required, the concern is

that these electrical problems have resulted in a large number

(almost continuous) of spurious system " trouble" indications

on the control room indicating panel that have the potential to

mask an actual " trouble" condition and could thereby prevent

an operator from diagnosing a true inoperability condition.

In

the case of the Unit 2 Fire Detection System, the inspector's

concern is that due to the fact that a new, more complex system

is in the final stages of installation while the previous system

was recently phased out, the majority of the licensed operators

in the control room are unsure of the new system's status, are

not adequately trained on the operating characteristics of the

new system, and, in the inspector's opinion, would have difficulty

assessing an incoming alarm.

This matter regarding the operability

of the Unit 1 and Unit 2 Fire Detection Systems will remain un-

resolved pending further inspector review (313/8125-02; 368/8124-04).

Control Room Ventilation Intake Duct Monitor

i

Unit 2 Technical Soecification Table 3.3-6 requires that the control

room ventilation intake duct monitor (2RITS-8750-1) be operable during

all operating modes. The applicable action statement states, "With

the number of channels OPERABLE less than required by the Minimum

Channels OPERABLE requirement, within one hour initiate and maintain

operation of the control room emergency ventilation system in the

4

'

recirculation mode of operation."

. - - - _ - _ - - _ _ - _ _ _ -

,

.

. _ .

.

.

_

___

.

-

- _ _

.

_.

.

.

t

i

7

On July 27, 1981, at 0750 hours0.00868 days <br />0.208 hours <br />0.00124 weeks <br />2.85375e-4 months <br />, the NRC inspector found 2RITS-8750-1

inoperable (in the test mode with indication failed low) and the control

,

room emergency ventilation system was not in the recirculation mode

of operation.

The operators on duty were not aware of the status of

this instrument until it was pointed out by the inspector.

Upon

.being informed, the plant operator placed the instrument in service.

It was not known when the instrument had been taken out of service.

'

This is an apparent violation of Technical Specification requirements

,

(368/8124-05).

i

Heat Tracing Channel Alarms

,'

!

The NRC inspector observed that numerous channels of system heat

!

tracing were in alarm and could not be cleared by the operators.

The

Operations Superintendent stated that he would submit a Plant-

Engineering Analysis Request in an attempt to identify and correct the

problems contributing to this condition.

This is an open item

(313/8125-04; 368/8124-07).

4.

Monthly Surveillance Observation (Units 1 and 2)

i

The NRC inspectors observed the Technical Specification required monthly

surveillance testing on the Unit 2 "A"

Diesel Generator (2104.36 Supple-

i

ment I) and verified that testing was performed in accordance with adequate

procedures, that test instrumertation was calibrated, that Limiting Condi-

tions for Operation were met, that removal and restoration of ti.e affected

components were accomplished, that test results conformed with Technical

Specifications and procedure requirements and were reviewed by personnel

other than the individual directing the test, and that any deficiencies

identified during the testing were properly reviewed and resolved by

j

appropriate management personnel.

-

The NRC inspector also witnessed portions of the following test activities:

Calibration of Unit 2 Hydrogen Analyzers (2304.029).

.

Monthly surveillance on Unit 1 Reactor Protective System Channel "B"

.

(1304.38).

a

l

Unit 1 Reactor Building Hydrogen Purge Standby System Station monthly

.

j

surveillance (1104.33 Supplement II).

4

The NRC inspector reviewed surveillance te.it records for tests performed in

accordance with the requirements of Unit 2 lechnical Specifications 4.6.4.1

t

and 4.6.4.2.

The test procedures included:

!

!

2104.44, Supplement 1

2104.44, Supplement 2

l

i

4

I

C_.__.,._______-.___.__.._.__,_..._,_____,_

.

.

,

8

2104.44, Supplement 3

2104.44, Supplement 4

2304.62

2304.31

2304.29

These are surveillance tests performed on the electric hydrogen recombiners

and on the hydrogen analyzers.

Technical Specification 4.6.4.1 requires

that the two hydrogen analyzers be calibrated once per 92 days on a STAGGERED

TEST BASIS.

The NRC inspector found that up until March 1981, the calibra-

tion had been performed once per six months on a STAGGERED TEST BASIS.

In

March 1981, the test program was altered to perform this calibration at

the required interval.

The licensee had identified this apparent Techni-

cal Specification violation during the first refueling outage and Report

of Abnormal Condition (RAC) No. 81071 was prepared by the licensee.

Since the licensee identified and corrected this apparent Technical

Specification violation, it will not be cited by the NRC.

The NRC

inspector noted that Technical Specification 4.6.4.lb requires tha use

of a 4% hydrogen sample gas in the calibration of the hydrogen analyzers.

The licensee should propose a change to this specification to account

for the increased range (0 - 10%) of the new hydrogen analyzers which were

installed earlier this year.

This is an open item (368/8024-06).

No

other violations or deviations were identified.

5.

Monthly Maintenance Observation (Units 1 and 2)

Station maintenance activities of safety-related systems and components

listed below were observed / reviewed to ascertain that they were conducted

in accordance with approved procedures, regulatory guides and industry

codes or standards and in conformance with technical specification.

The following items were considered during this review:

The Limiting

Conditions for Operation were met while components or systems were

removed from service; approvals were obtained prior to initiating the

work; activities were accomplished using approved procedures and were

inspected as applicable; functional testing and/or calibrations were

performed prior to returning components or systems to service; quality

control records were maintained; activities were accomplished by qualified

personnel; parts and materials used were properly certified; radiologi-

cal controls were implemented; and fire prevention controls were imple-

mented.

Work requests were reviewed to determine status of outstanding jobs

and to assure that priority is assigned to safety-related equipment

maintenance which may affect system performance.

..-

- - . . - -

. , - . , - _ -

. , - - - - . . - - - . . . . , -

_.

.

.

9

The following maintenance activities were observed / reviewed:

Repair of lower primary manway on "A" OSTG (J0-1191)

.

Repair and replace lower manway on "A" 0TSG (J0-06266)

.

Repair 2P36C (J0-15160 on July 22, 1981, and J0 1635 August 7,

.

1981)

Machine standpipe from B Reactor Coolant Pump Seal (J0-6255)

.

Repack 2P36A (J0-15172)

.

Following completion of maintenance on the Unit 2 "A" charging pump,

the NRC inspector verified that this system had been returned to

service properly.

In conjunction with the Unit 1 OTSG manway replacement job, the NRC

inspector inspected the licensee's stock of spare primary and secondary

manway gaskets.

The following table lists the gaskets found in stock:

Purchase Order

AP&L Stock No.

No. in Stock

No. Rings

27084

580064

6

14

16437

580064

1

22

27084

580066

2

19

16437

580066

8

21

07960

580066

10

24

AP&L Stock No. 580064 is for primary manway gaskets and 580066 is for

secondary manway gaskets.

The gaskets in stock are identified by

paper tags attached to the gaskets or inside the plastic bag con-

taining the gasket.

The licensee's procedure fer replacement of a

primary manway cover 1402.30, points out the difficulty in differentiat-

ing between primary and secondary manway gaskets and states that primary

gaskets may be identified by counting the rings (should be 20-24).

Babcock and Wilcox drawing 135040E states that primary manway gaskets

and the gaskets in stock do not have metal identification tags. The

NRC inspector discussed the problem of identification of primary manway

gaskets and the apparent discrepancy in the identification of the gas-

kets now in stock with the Material Management Supervisor and the Stores

Supervisor.

The Stores Supervisor agreed to seek resolution through

submission of a Plant Engineering Analysis Request and a Nonconforman;e

Report.

This is an open item (313/8125-03).

No violations or deviations were identified.

,

,

-

.

--

-

-

-.

-

-

.

10

6.

IE Circular Followup (Units 1 and 2)

For the IE Circulars listed below the NRC inspector verified that the

Circular was received by the licensee management, that a review for

applicability was performed, and that if the circular were applicable

to the facility, appropriate corrective actions were taken or were

i

scheduled to be taken.

,

.

80-18

10 CFR 50.59 Safety Evaluations for Changes to Radioactive

Waste Treatment Systems

80-21

Regulation of Refueling Crews

80-23

Potential Defects in Beloit Power Systems Emergency Generators

.

81-04

Role of Shift Technical Advisors and Importance of Reporting

Operational Events

81-06

Potential Deficiency Affecting Certain Foxboro 10 to 50

Milliampere Transmitters

81-08

Foundation Materials

No violations or deviations were identified.

7.

Unresolved Items (Units 1 and 2)

Unresolved items are matters about which more information is required in

order to ascertain whether they are acceptable items, items of noncom-

pliance, or deviations.

Unresolved items disclosed during the inspec-

tion are discussed in paragraphs 2 and 3.

8.

Exit Interview

The NRC inspectors met with Mr. J. P. O'Hanlon (Plant General Manager)

l

and other members of the AP&L staff at the end of various segments of

l

this inspection.

At these meetings, the inspectors summarized the

.

scope of the inspection and the findings.

l

!

!

!

4

i

+

1

.

!

1

l

1

f

1

l

l

- .

. _. . . ~ , , . _ . . . _ , . _ _ _ . _ , _ _ _ _ . _ . . - . . _ . - , _ ~ _ . _ . _ _ _ _ _ _ , _ _ . _ . _ - , ~ - . _