0(Tr 5 1981

/

/

Docket Hos.: 50-460/S13 r

itElloitAhDUll Fb't: Elinor G. Adensan, Acting Branch Chief

// /' )

f Licensing Branch #4, DL

/

/./

gl

'/

,e FR0ri:

Ronald W. liernan, Project itanager Licensing Branch #4, DL j

, p.

u /

SUtiJEC1:

NOTICE OF MtETING AND TutSt BY CASELOAD F0dECAST PMLL TO ASSESS CONSTRUCTION CQiFLETION SCHEDULES - WASl!INGTON NUCLEAR PROJECT - UNIT 1 4

/

DATE & TliiE:

WPPSS Presentations (per attached agenda)

WNP-1 g'

1:00 - 5:00 Pit October 21, 1981 8:30 - 11:00 PH October 22, 1981

/

Site tour - WNP-1

/

12:30 - 5:00 Pit October 22, IW1 Discussion period WNP-1 8:30 - 10:00 #1 October 23, 1981 Exit meeting WuP-1 Plant Site 11:00 #1 October 23, 1961 PURPOSE:

To assess construction progress and schedules on an independent basis in preparation for establishing a licensing review scheaule for WkP-1.

1/

PNITICIPANTS:--

tRC Washington Public Power Supply Systen:

W. Lovelace

b. Sorensen
x. doot R. iternan G. Bouchey
11. Carrigan D. ;iazur it. Johnson Bechetel Power Corp.

United Engineers ano Constructors F. Waterhouse W. Taylor E. Edwards Ronald ti. liernan, Project Hanager Licensing Branch #4, DL cc: See next page

,1f fleetings between IRC Technical staff and applicants for licenses are open for interested r: embers of the public, petitioners, intervenors, or other Dartien LU a b bclIO ob OD5erVers pursuant to "Open llecting and Statement fIC

- " " " " ~ " " " -

- *Q

[/

"'cr>....... P.ol icy.",. 43. federal.aMister-24058., 6/.28/78c- ~

( _ _ " _ g_"_

cu m " b

. N. nan;q _,

............. ~. ~. ~

~ ~. ~ ~.. - ~. ~ ~

'9110190152 811005

  • 1PDR ADOCK 05000460 g

10/.J.... /81.~10/J~~/81

..g.................

~

~~.

~

~ ~ ~ -

knc rohu ais no.somcu ono OFFICIAL R$ CORD COPY

p no uq[o, UNITED STATES g

8 NUCLEAR REGULATORY COMMISSION n

(

WASHINGTON, D. C. 20555 j#

October 5, 1981 Docket Nos.:

50-460/513 MEMORANDUM FOR:

Elinor G. Adensam, Acting Branch Chief Licensing Branch #4, DL FROM:

Ronald W. Hernan, Project Manager Licensing Branch #4, DL

SUBJECT:

NOTICE OF MEETING AND TOUR BY CASELOAD FORECAST PANEL TO ASSESS CONSTRUCTION COMPLETION SCHEDULES - WASHINGTON NUCLEAR PROJECT - UNIT 1 DATE & TIME:

WPPSS Presentations (per attached agenda)

WNP-1 1:00 - 5:00 PH October 21, 1981 8:30 - 11:00 PN October 22, 1981 Site tour - WNP-1 12:30 - 5:00 PM October 22, 1981 Discussion period - WNP-1 8:30 - 10:00 AH October 23, 1981 Exit meeting WNP-1 Plant Site 11:00 AM October 23, 1981 PURPOSE:

To assess construction progress and schedules on an independent basis in preparation for establishing a licensing review schedule for WNP-1.

1/

PARTICIPANTS:-

NRC Washington Public Power Supply System W. Lovelace

6. Sorensen R. Root R. Hernan G. Bouchey M. Carrigan D. Mazur R. Johnson Bech tel Power Corp.

United Engineers and Constructors F. Waterhouse W. Taylor E. Edwards Ronald W. Hernan, Project Manager Licensing Branch #4, DL cc:

See next page 1/ Meetings between NRC Technical staff and applicants for licenses are open for interested members of the public, petitioners, intervenors, or other parties l

to attend as observers pursuant to "Open Meeting and Statement of NRC Staff Policy", 43 Federal Register 28058, 6/28/78.

l l

l

WNP Mr. R. L. Ferguson llanaging Director Uashington Public Power Supply System P.O. Box 968 3000 George Washington Way Richland, Washington 99352 cc: Mr. V. Mani United Engineers & Constructors, Inc.

30 South 17th Street Philadelphia, Pennsylvania 19101 Nicholas S. Reynolds, Esq.

DeBevoise & Liberman 1200 Seventeenth Street, N.W.

Washington, D. C.

20036 Mr. E. G. Ward Senior Project Manager Babcock & Wilcox Company P.O. Box 1260 Lynchburg, Virginia 23505 Resident Inspector /WPPSS NPS c/o U.S. Nuclear Regulatory Commission P.0. Box 69 Richland, Washington 99352

WASHINGTON NUCLEAR PRujECT, UNIT 1 CASELOAD FORECAST PANEL VISIT MLETING AGENDA FOR WPPSS PRESENTATION October 21-23, 1981 1.

Overview of project construction schedule including organizational structures, progress and major milestones completed since February 1980, current problems and any ant; ipated problem areas that may impact the current projected fuel load date.

2.

Detailed review and current status of design and engineering effort (by major discipline) including any potential problems that may arise from necessary rework.

3.

Detailed review and current status of procurement activities including valves, pipe, instruments, cable, major components, etc.

4.

Actual and proposed craf t work force (by major craft), craf t availability, productivity, potential labor negotiations and problems.

5.

Detailed review and current status of all large and small bore pipe hangers, restraints. snubbers, etc., including design, rework, procurement, fabrica-tion, delivery and installation.

6.

Detailed review of project schedule identifying present percent completion, critical path items, near critical items, amount of float for various activi-ties, tne current critical path to fuel loading, methods of implementation of corrective action for any activities with negative float, and provisions for contingencies.

7.

Detailed review and current status of bulk quantities including current estimated quantities, quantities installed to date, quantities scheduled to date, current percent complete for each, actual versus forecast installation rates, and basis for these figures for the following:

(a) Concrete (CY = Cubic Yards)

(b) Process Pipe (LF - Linear Feet)

- Large Bore Pipe (2 1/2" and larger)

- Small Bore Pipe (2" and smaller)

(c) Yard Pipe (LF)

(d) Large Bore Pipe Hangers, Restraints, Snubbers (each)

(e) Small Bore Pipe Hangers, Restraints (each)

(f) Cable Tray (LF)

(g) Total Conduit (LF)

so D

2-(h) Total Exposed Metal Conduit (LF)

(i) Cable

- Power

- Control

- Securi ty

- Instrumentation

- Plant Lighting (j ) Terminations (each)

- Power

- Control

- Security

- Instrumentation

- Plant Lighting (k) Electrical Circuits (each)

- Power

- Control

- Securi ty (1)

Instrumentation (each) 8.

Detailed review and current status of preparation of preop and acceptance test procedures, integration of preop and acceptance test activities with construction schedule (if applicable), system turnover schedule, preop and acceptance tests schedule, current and proposed preop and acceptance tests program manpower as follows:

(a) Total number of preoperational and acceptance test procedures required for fuel load.

(b) humber of draf t procedures not started.

(c) Number of draf t proceoures being written.

(d) Number of procedures approved.

(e) Number of procedures in review.

(f) humber of preop and acceptance tests completed.

(g) Number of preop and acceptance tests currently in progress.

(n) Number of systems trurned over to WPPSS.

9.

Detailed discussion of potential construction influence due to changes attributed to NUREG-0737 gnd other recent licensing requirements.

10. Discussion of schedular impact, if any, regarding patential deficiencies reported in accordance with 10 CFR 50.SS(e).

MEETINGNdTICEDISTRIBUTION Docket File #

'/6 0 J. Kramer fiRC PDR J. Stolz Local PDR S. Ilanauer TIC P. Collins NSIC D. Vassallo LB #4 r/f D. Ziemann WT 5 issi N. Hughes T. Murley E. Case.

F. Schroeder O. Eisenhut K. Kniel R. Purple D. Skovholt T. Novak G. Knighton S. Varga M: Ernst T. Ippolito R. Baer R. A. Clark E. Adensam A. Thadani R. Tedesco ACRS (10.:

J. Youngblood Attorney, OELD A. Schwencer OIE (3)

M OSD (7) 7 M'@.

F. Miraglia Project Manager RHernan l

J. R. Miller G. Lainas b

Gi Licensing Assistant unnncan I

S [ \\\\\\

Receptionist

~

D. Crutchfield i'

W. Russell

'9'I ge

'J TERA J. LeDoux, I&E J. Olshinki R. Vollmer ON I2 V. Moore R. Bosnak 9

I&E Headquarters Ds.w 9

/

I&E Region I

f. Schauer 4%p[gd I&E Region II R. E. Jackson W

I&E Region III G. Lear V. Noonan I&E Region IV S. Pawlicki I&E Region V V. Benaroya Z. Rosztoczy NRC

Participants:

W. Lovelace W. Haass R. Hernan D. Muller R. Ballard W. Regan R. Mattson P. Check Chief, Power Systems Branch

0. Parr F. Rosa bec:

Applicant & Service List W. Butler W. Kroger R. W. Houston Chief, Radiological Assessment Branch W. Gammill L. Rubenstein T. Speis W. Johnston B. Grimes S. Schwartz F. Pagano S. Ramos

_ _ _ _ _ _ _ _ _ _ _ _