U'0299 lLL/NOIS POWER COMPANY ff?
L03-81(10-02)-6 500 SOUTH 27TH STREET, DECATUR, ILLINOIS 62525 October 2, 1981 to p
th,
\\
Mr. James R. Miller, Chief 2
Standardization & Special Projects Branch E:
OCT 9 Esta-ts7/
Division of Licensing m.m Office of: Nuclear Reactor Regulation g
,ggj U.
S. Nuclear Regulatory Commission Washington, D.
C.
20555
-0$
s
- G
Dear Mr. Miller:
Reference:
Letter J. R. Miller, NRC to G. Wuller, IP,
Subject:
Review Questions on the Clinton Power Station Clinton Power Station Unit 1 Docket No. 50-461 This is in reply to the referenced letter, which we received on September 28, wherein you requested our schedule for responding to the FSAR review questions.
Illinois Power plans to respond to the questions provided in the enclosures to the referenced letter as follows: - Financial Information - Application revision (general information) Amendment in October 1981. - Materials Engineering Branch (Materials) -
via FSAR amendment in October 1931. - Materials Engineering Branch (Components) -
via FSAR amendment in October 1981. - Hydrologic & Geotechnical Engineering Branch -
via FSAR amendment in October 1981 Sincerely,
~
G. E. Wuller Supervisor - Licensing Nuclear Station Engineering GEW/em cc:
Mr. J. H. Williams, NRC Clinton Proj ect Manager Mr. H. H. Livermore, NRC Resident Inspector f
'8110130180 811002 j[fp PDR ADOCK 05000461 f
A PDR