YANKEE ATOMIC NUCLEAR P0h'ER STATION ~

MONTHLY STATISTICAL REPORT 75-9 FOR THE MONTH OF SEPTEMBER,-1975=

W e

8110060591 751007 PDR ADOCK 05000029 8

R PDR

Al'I'ENDIX 1)

=

DOCKET NO.

50-29 UNIT YANKEE RONE i

DATE 7,51007 COMPLETED BY E. C. TARNUZZER TELEP110NS (617) 366-9011 X2585 AVERAGE DAILY UNIT PONER LEVEL

' MONT11 September, 1975 DAY AVERAGE DAILY MWe-net DAY AV$ RAGE DAILY MWo-1 158 16 147 2

157 17 146 3

156 18 145 l

I 4

156 19 145 5

155 20 144 6

154 21 143 153 22 142 7

i 142 152 23 i

8 l

l 141

[

g 152 24 i

141 10 150 25 142 149 26 11 142 149 27 12

^

141 I49 28 13 139 148 29 14 138 148 30 15 31 l

Tr l

.5 i

OPEIMYllmh UNIT NAME YANKEE RONE COMPLETED BY E. C. TARMUZZER TFLEP110NE (617) 366-9011 X2585 ELE R AllN E SI AIU S 720 1.

REPdRTINGPERIOD: September, 1975 GROSS Il0URS IN REPORTING PERIOD 175 600 MAX. DEPEND, CAP. (MWe-NET) 2.

CURRENTLY AUT110RIZED POWER LEVEL MWt.

DESIGN ELECiRICAL RATING (MNe'-NET) 175 NONE 3.

PONER LEVEL TO WiiICH RESTRICTED (IF ANY):

4.

REASONS FOR RESTRICTIONS (IF ANY):

N/A CUMULATIVE THIS YR-TO-DATE TO DATE MONTH 720 6,500 108,507 5.

HOURS REACTOR WAS CRI,TICAL 0

0 0

6.

REACTOR RESERVE SHUTDOWN HOURS 720 6,479 104,718 7.

HOURS GENERATOR ON-LINE I

0 0

0 8.

UNIT RESERVE SHUTDOWN HOURS 9.

GROSS THERMAL POWER GENERATED (MWH) 367,878 3,702,729 55,331,396

10. GROSS ELECTRICAL POWER GENERATED (MWH) 113,762 1,172,626 16,967,073 I
11. NET ELECTRICAL POWER GENERATED (MWH) 106,234 1,102,217 15,878,959 12.

REACTOR YERVICE FACTOR 100.0 99.2 82.0 100'.0 99.2 82.0 l

13.

REACTOR AVAILABILITY FACTOR 100.0 98.9 80.3

14. UNIT SERVICE FACTOR 100.0 98.9 80.3 IS.

UNIT AVAILABILITY FACTOR 84.3 96.1 72.7 16.

UNIT CAPACITY FACTOR (USING MDC) 84.3 96.1 72.7 17.

UNIT CAPACITY FACTOR (USING DESIGN MWe) 0.0 0.2 1.0

18. UNIT FORCED OUTAGE RATE SHUTDOWNS. SCHEDULED TO BEGIN IN NEXT 6 MONTHS (STATE TYPE, DATE AND DURAT 19.

Six week refueling outade commencing Cetober 18, 1975.

OF EACll):

N/A IF SIIUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

20.

Rev. 10/75

DATE 751007 COMPLETED BY E. C. TARNUZZER APPENDIX D TELEPHONE (617) 366-9011 X251 i

' UNIT SHUTDOWNS AND POWER REDUCTIONS l

REPORT MOKnl September, 1975 TYPE METHOD OF.

F-FORCED DURATION SHUTTING DOWN NO.

DATE S-SCHEDULED (HOURS)

REASON (1)

THE REACTOR, (2)

CORRECTIVE ACTIONS / COMMENTS 4

i l

I 1

SUMMARY

The Plant continued in "coastdown" operation toward an October 18 ref,ueling~ outage.

s Rev. 10/75 0

..