Third Interim Deficiency Rept Re Standby Gas Treatment Design Defect,Initially Reported 801212.Alternatives Are Being Reviewed to Correct Drainage Problems.Results Will Be Submitted by 820212.Also Reportable Per Part 21
ML20031B977
Person / Time
Site: Hartsville, Phipps Bend  
Issue date: 10/01/1981
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
REF-PT21-80 10CFR-050.55E, 10CFR-50.55E, NUDOCS 8110060342
Download: ML20031B977 (1)


Text

-.,

TENNErscE VALLEY AUTHORITY O 4 ATTANCOGA. TENNESSEE 37401 i

400 Chestnut Street Tower II

- o October 1, 1981 t

4 HTRD-50-518, -519, -520, -521/81-03 O

pr<

s y

PBRD-50-553, -554/81-03 fg 4

OC'T G 19815 Mr. James P. O'Reilly, Director

{~

v3

\\'. ' ~ NsIcY" Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission

'\\ /

f 4,

Region II - Suite 3100 f,/ Si(h 101 Marietta Street Atlanta, Georgia 30303

Dear Mr. O'Reilly:

HARTSVILLE AND PHIPTS BEND NUCLEAR PLANTS - SGTS DESIGN DEFICIENCY -

HTRD-50-518, -519, -520, -521/61 PBRD-50-553, -554/81-03 The subject deficiency was initially reported to NRC-OIE, Region II Inspector, McKenzie Thomas on December 12, 1980, as NCR's HTNANEB 8004 and PBNNEB 8004. The first and second interim reports were submitted on January 9, and May 26, 1981, respectively. In compliance with paragraph 50.55(e) of 10 CFR Part 50, this letter constitutes the third interim report on the subject deficiency.

TVA is continuing to review the alternatives to correct the SGTS water drainage problem. The alternatives are to enlarEe the size of the drains or put a timer on the spray system to limit the amount of water sprayed on the charcoal and carried to the drainage system. We anticipate a decision and the results forwarded to you in the form of a final report by February 12, 1982. We consider 10 CFR Part 21 applicable to thic nonconformance. If you have any questions, please call Jim Domer at FTS 857-2014.

Very truly yours, l

TENNESSEE VALLEY AUTHORITY gj j-s

~

l-. ]i ;. (l,

L. M. Mills, Manager Nuclear Regulation and Safety cc:

Mr. Victor Stello, Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, DC 20555 se t s