ML20030C356

From kanterella
Jump to navigation Jump to search
Interim Deficiency Rept Re Bostrom Bergen Metal Products Welded Assemblies,Initially Reported on 801208.Testing Has Been Completed.Final Engineering Rept Will Not Be Available Until End of Jul 1981.Final Rept by 810814
ML20030C356
Person / Time
Site: Washington Public Power Supply System
Issue date: 07/17/1981
From: Mazur D
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Faulkenberry R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
10CFR-050.55E, 10CFR-50.55E, GO1-81-209, NUDOCS 8108260015
Download: ML20030C356 (2)


Text

gg -

50.55(e) Report Docket Nos. 50-460/513 Washington Public Power Supply System P.O. Box 968 3000 GeorgeWashington Way Richland, Washington 99352 (509)372-5000 July 17, 1981 G0-1-81-209

,g7Q, fY, fr$.%-$

s Q JUL o,:T!l d

e. % ! C; j'
  • v Nuclear Regulatory Commisrion g

I8 Region V Suite 202 Walnut Creek Plaza

'>)

1990 'l. California Boulevard

/,/

Walnut Creek, California 94596 9

m n

~

i

,g@y,r Attention:

Mr. R. H. Faulkenberry

, c,

Chief, Reactor Construction gy 11 Projects Branch gj i

r kV,.

o.5-

"/

'x 5

Subject:

PROJECTS 1 AND 4

N/jj.. \\ \\

DOCKET NOS. 50-460 AND 50-513 j

POTENTIALLY REPORTABLE CONDITION 10CFR50.55(e)

BOSTR0M BERGEN METAL PRODUCTS WELDED ASSEMBLIES

Reference:

1)

Telecon TJ Houchins, Supply System to DF Kirsch, Region V Nuclear Regulatory Commission dated December 8, 1980 2)

G3-1-81-03, dated January 7, 1981, DW Mazur to RF Engelken, Director 3)

G0-1-81-167, dated June 9, 1981, DW Mazur to RH Faulkenberry, Chief, Reactor Construction reportable Jeficiency under 10CFR50.55(e) and references 2) potentially In reference 1) the Supply System informed your office of a and 3) were interim reports on the subject condition.

Our letter of June 9,1981 (reference 3 above) indicated that the test-ing program described in Attachment "A" of our January 7,1901 (reference 2 above) interim report, would be completed by mid June 1981, with a final report following by July 17, 1981. The testing has been completed by the testing laboratory and the test results have been transmitted to UE&C Engineering, Philadelphia for evaluati<.n; however, since the test-ing took longer than previously anticipated, a final engineering report will not be available until the end of July 1981. Therefore, this is an interim report with a final report to follow by August 14, 1981.

TO

s 1/0 S!ASPo88PoS$8$8 S

$l-kl

Mr. R. H. Faulkenberry GO.1-81-209 Bostrom Bergen Metal Products Page 2 If you have any question or desire further information, please advise.

Very truly yours,

. W.

Program Director WNP-1/4 DWM:MER:lm cc:

CR Bryant, Bonneville Power Administration /399 EW Edwards, Bechtel Power Corporation V Stello, Director of Inspection and Enforcement, NRC 1