Requests That 820401 Deadline for Integrated Exercise Demonstrating Emergency Preparedness Be Extended to 820630 W/Actual Exercise Conducted About mid-June
ML20030B928
Person / Time
Site: Peach Bottom  
Issue date: 08/19/1981
From: Daltroff S
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To: Harold Denton
Office of Nuclear Reactor Regulation
References
NUDOCS 8108250199
Download: ML20030B928 (2)


Text

i j

w

3.,g -r',

PHILADELPHIA ELECTRIC COMPANY 2301 MARKET STREET

,, Q

' (;

P.O. BOX 8699 j

1881 1981

!& 2 4 % w 9 PHILADELPHI A. PA.19101 (215) 841 Sool lieb IDabs asourag,.

smf LDS L D ALTR,OFF M50'4 euce.eene ies=

, 3)J vic j

.c ooucno.

T August 19, 1981 Re: Docket Nos. 50-277 50-278 Mr. Harold R. Denton, Director Of fice of Nuclear Reactor Regulation US Nuclear kegulatory Contnission Washington, DC 20555

Dear Mr. Denton:

i This letter is a request for an extension beyond the prescribed l

date of April 1, 1982 to demonstrate emergency preparedness via an inte-

)

grated exercise for the Peach Bottom Atomic Power Station.

PEMA has formally advised us that Peach Bottom is currently scheduled for the integrated exercise on April 29, 1982.

Furthermore, PEMA has stated that their limited resources would prevent advancing the Peach Bottom exercise.

We maintain liaison with state and county emergency management personnel. Through this liaison, we are kept aware of the status of state and county emergency plans.

The county plans relative to Peach Bottom will not be formally submitted to the Regional Advisory Council before April 1, 1982.

PEMA is opposed to conducting an exercise before submittal of county plans for formal RAC review.

We have discussed with PEMA the merits of moving this date eith-er forward or backward.

Our Unit 2 outage for refueling and major plant nudifications will span the period from February 20 to May 31,1982.

To move the exercise forward would conflict with PEMA's position.

PEMA is quite firm in their position even though their involvement in the Peach Bottom exercise will be limited.

PEMA has no objections to an exercise later than April 29, 1982.

We have serious reservations about conducting such an important and complex operation during a Unit outage.

Because of the burden on state and county resources and because of the scheduled Unit 2 r efuel outage, we request an extension beyond i

8108250199 810819 b

PDR ADOCK 05000277 F

PDR m

Mr. Harold R. Denton, Director Page Two.

August 19, 1981 April 1, 1982 for the Pea-h Bottom integrated exercise. We request that the extension be granted to June 30, 1982 with the actual exercise con-ducted about mid-June.

Very truly yours, s

/.