Text
-
.
.
'
.
,
MAY 051994
Docket Nos. 50-338, 50-339
,
Virginia Electric and Power Company
ATTN: Mr. W. L. Stewart
Senior Vice President - Nuclear
5000 Dominion Boulevard
Glen Allen, VA 23060
Gentlemen:
,
,
SUBJECT: NRC INSPECTION REPORT N05. 50-338/94-07 AND 50-339/94-07
This refers to the inspection conducted by Mr. R. McWhorter of this office on
March 20 through April 16, 1994. The inspection included a review of
activities authorized for your North Anna facility. At the conclusion of the
inspection, the findings were discussed with those members of your staff
i
identified in the enclosed report.
Areas examined during the inspection are identified in the report. Within
these areas, the inspection consisted of selective examinations of procedures
and representative records, interviews with personnel, and observation of
activities in progress.
Within the scope of the inspection, violations or deviations were not
i
identified.
The inspection identified a condition where an abnormal procedure called for
tripping the main turbine, but the turbine was not tripped due to personnel
safety considerations. We agree with your concern about personnel safety
considerations and this justified waiting to trip the turbine.
However, we
are concerned about the operators' command and control during the evolution,
,
and identify this concern as a weakness.
Consequently, this weakness is being
highlighted for your attention and resolution.
Pursuant to 10 CFR 2.790 of the NRC's " Rules of Practice", a copy of this
letter and its enclosure will be placed in the NRC Public Document Room.
Should you have any questions concerning this letter, please contact us.
Sincerely,
()b aa< &)4
&c/10. b% Chb
Davi
M.
errelli,
hief
Reactor Projects Branch 2
Division of Reactor Projects
Enclosure: NRC Inspection Report
cc w/ encl:
(See page 2)
170CT3
s (\\.
9405100059 940505
- DR
ADDCK 0500
8
gg
.-. . .
. . .
. -
.
.
,
-
t
t
Virginia Electric and
2
MY 0 51994
Power Company
cc w/ encl:
M. L. Bowling, Jr., Manager
Nuclear Licensing
Virginia Electric & Power Company
5000 Dominion Boulevard
-
j
Glen Allen, VA 23060
G. E. Kane, Station Manager
North Anna Power Station
P. O. Box 402
Mineral, VA 23117
j
Executive Vice President
Old Dominion Electric Cooperative
4201 Dominion Boulevard
Glen Allen, VA 23060
Dr. W. T. Lough
Virginia Corporation Commission
'
Division of Energy Regulation
P. O. Box 1197
Richmond, VA 23209
William C. Porter, Jr.
County Administrator
1
'
Louisa County
P. O. Box 160
Louisa, VA 23093
Michael W. Maupin, Esq.
Hunton and Williams
Riverfront Plaza, East Tower
951 E. Byrd Street
Richmond, VA 23219
Attorney General
Supreme Court Building
101 North-8th Street
Richmond, VA 23219
Robert B. Strobe, M.D., M.P.H.
State Health Commissioner
Office of the Commissioner
,
P. O. Box 2448
i
Richmond, VA 23218
bec w/ enc 1: (See page 3)
-1
,
,
MAY 051994
Virginia Electric and
3
Power Company
bec w/ enc 1:
G. Belisle, RII
,
L. Garner, RII
L. Engle, NRR
.
'
Document Control Desk
NRC Resident Inspector
i
U.S. Nuclear Regulatory Commission
Route 2, Box 78-A
Mineral, VA 23117
NRC Resident Inspector
U.S. Nuclear Regulatory Commission
Surry Nuclear Power Station
5850 Hog Island Road
Surry, VA 23883
)
RII:DRP
RII:D
U u G.
fi
-
LGarner
GBe1% e
5/f/94