Submits Addl Info on Completion of Actions Contained in CAL RIII-94-05 Re Thermocouple Funnels
ML20029D955
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 05/09/1994
From: Kofron K
COMMONWEALTH EDISON CO.
To: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
BW-94-0084, BW-94-84, CAL-RIII-94-05, CAL-RIII-94-5, NUDOCS 9405130108
Download: ML20029D955 (2)


Text

W Conunonwsalth Edison

  • 3

' Braidwood Nuclear Power Station 1 i Route #1, Box 84 l Braceville, Illinois 60407 g Telephone 815/458-2801 May 9, 1994 BW/94-0084 .

1 Mr. John B. Martin Regional Administrator U.S. Nuclear Regulatory Consission Region III 801 Warrenville Road Lisle, Illinois 60532-4351

References:

(1) Confirmatory Action Letter RIII-94-005 for Braidwood Unit 2 (2) Braidwood letter BW/94-0075, K. L. Kofron to Mr. J. B. Martin, May 6, 1994

Dear Mr. Martin:

Subject:

Additional information on completion of actions contained in Confirmatory Action Letter (CAL)

RIII-94-005 for Braidwood Unit 2 Reference 1 required that Braidwood Station inform the NRC, )

in writing, when the actions contained in the CAL were complete.

Reference 2 contained Commonwealth Edison's response to Reference 1 and stated that all thermocouple funnels on Braidwood Unit 2 had been inspected, and their pins were found to be installed correctly. 1 A more detailed review of the inspection data and additional visual inspections showed that another thermocouple funnel was also missing l a pin. The missing pin was located on top of the upper internals j and retrieved. j i

Commonwealth Edison will be conducting corrective / preventive i repairs on the Unit 2 thermocouple funnels. l This information was communicated to Mr. Edward G. Greenman of your staff by Mr. Karl Kaup, Braidwood Station Site Vice President, in a telephone conversation at 0805 on May 9, 1994.

Mr. David J. Miller, Braidwood Station Technical Services Super-intendent, informed Mr. Rolf A. Westberg, Augmented Inspection Te,.m Leader, via telephone on Saturday, May 7, 1994, and updated this information at approximately 1000 on May 9, 1994.

9405130100 940509 PDR ADOCK 05000457 P PDR mRL 5 $0

E .'

. .a Mr. John B. Martin 2 May 9, 1994 ,

If you have any questions, contact Mr. David J. Miller at Braidwood Station, (815) 458-2801, extension 2114.

Sincerely, s ,) I

' ) , C. - r* Na

-K. L. Koftbn-Station Manager Braidwood Station KLK/DH/dla ,