l%R 2 0199)
,
.
Docket No. 50-382/91-04
License No. NPF-38
Entergy Operations, Inc.
ATTN:
Ross P. Barkhurst, Vice h esident
Operations, Waterford
P.O. Box B
Killona, Louisiana 70066
Gentlemen:
SUBJECT: NOTICE OF VIOLATION (NRC INSPECTION REPORT NO. 50-382/91-04)
This refers to the inspection conducted by Ms. Linda McLean of this office
during the period February 5-8, 1991. The inspection included a review of
activities authorized for your Waterford-3 f acility. At the conclusion of the
inspection, the findings were discussed with those members of your staff
identified in the enclosed report.
The area examined during the inspection was the implementation of your
fitness-for-duty (FFD) program. Within this area, the inspection consisted of
selective examination of procedures and representative records, interviews with
personnel, and observation of activities in progress.
Based upon the results of this inspection, certain of your activities appeared
to be in violation of NRC requirements, as specified in the enclosed Notice of
Violation (Notice).
One violation related to Waterford-3's policy which allows contractor
supervisors 90 days to complete the required supervisory training.
10 CFR 26.22 requires that all supervisory personnel, including contractors, be
trained in supervisory aspects of the program prior to assignment of duties.
In accordance with Section V.G.I. of the NRC's Enforcement Policy, no citation
is being issued for the second violation described in Section 6 of the enclosed
inspection report.
You are required to respond to this letter and should follow the instructions
specified in the enclosed Notice when preparing your response.
In your
response, you should document the specific actions taken and any additional
actions you plan to prevent recurrence.
After reviewing your response to this
Notice, including your proposed corrective actions and the results of future
inspections, NRC will determine whether further NRC enforcement action is
necessary to ensure compliance with NRC regulatory requirements,
n
- RIV: NMSIS
- C:NMSIS
D: )R
MLMcLean:st
CLCain
AE
h
SJ:ollin
'/ /91
/ /91
3 /l9/91
y'51
- Previously concurred
?!R
%88ER 8!8S88am
3')
}
4
-
Q
!
280004
\\
v
t
.
- _--
- - _ _ - _ - . _
,
I
n'
}
' '
1%K 4 01991
- Dc:ket No. 50-382/91-04
License No. NPF-38
j
!
,
Entergy Operations, Inc.
ATTN:' Operations, Waterford
Ross P. Barkhurst, Vice President
<
'
.P.O.. Box B
}
K111ona, Louisiana- 70066
1
i
Gentlemen:
SUBJECT: NOTICE OF VIOLATION (NRC INSPECTION REPORT N0' 50-382/91-04)
.
LThis refers to the; inspection conducted by Ms. Linda McLean of this office
.
'
- during the period February 5-8, 1991.
The inspection included a review of
activities authorized for your. Waterford-3 facility. At the-conclusion of the
'
'
' inspection -the findings were discussed with those members of your staff
1
. identified in the enclosed report.
=The area examined during the_ inspection was the implementation of your
fitness-for-duty -(FFD) program. Within this area, the inspection consisted'of
i
selective examination 1 of procedures and representative records,. interviews with
personnel, and observation of activities in progress,
i
Based upon the results of thisiinspection, certain of your activities appeared
-
_to beiin violation of NRC-requirements, as specified in the enclosed Notice of
.
LViolation_'(Notice).,
'"
. .
One violation related to Waterford-3's policy which allows contractor
supervisors 90 days;to complete the . required supervisory training..
E101CFR 26;22' requires.that all tupervisory personnel, including contractors, be-
g
trained in'_: supervisory aspects of'the program prior to assignment of duties.
.
- ..
~In accordance with Section V.Gil, of._the NRC's Enforcement Policy, no citation
"
is being; issued _for the second violation-described in'Section 6 of the enclosed
+
'
' inspection report.
You are required to respond to this-letter and should follow the instructions
'specified in1the enclosed Notice when preparing your response. -In your'
<
response,Jyou should document the specific actions 'taken and any-additional .
'
.c
actions you plan to preventL recurrence. l Af ter _ reviewing you response to_ this
,
W
. Notice,iincluding your' proposed correctiveiactions and the results of future-
inspections, NRC will: determine whether further NRC enforcement action is
-;
,
6
'necessary .to' ensure ::ompliance with NRC regulatory requirements'.
RIV:NMSIS
C:NMSISO.O
0:DRSS-
0:0RP
MLMcLean:
CLCain
- V ABBeach
SJCollins
L.1 / 6/91-
3/H/91+
/ /91
/ /91
V
,' -
j
.
im-
-~.u..
-
. . .
. .
_ - _ , _
.- .
.
__,
_ _ _ . _
__
_ _ _ _ _ _ _ _ - _
_ _ _ _ _ _ - _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ - _ _ _ _ _ ,
t
VM 2 U l99)
'
Docket No. 50-382/91-04
License No NPF-38
Entergy Operations Inc.
ATTN:
Ross P. Barkhurst, Vice President
Operations, Waterford
P.O. Box B
K111ona, Louisiana 70066
Gentlemon:
SUBJECT:
NOTICE OF VIOLATION (NRC INSPECTION REPORT NO. 50-382/91-04)
.This refers to the inspection conducted by Ms. Linda McLean of this office
during the period February 5-8, 1991. The inspection included a review of
activities authorized for your Waterford-3 facility. At the conclusion of the
inspection, the findings were discussed with those members of your staff
identified in the enclosed report.
The area examined during the inspection was the implementation of your
fitness-for-duty (FFO) program. Within this area, the inspection consisted of
selective examination of procedures and representative records, interviews with
personnel, and observation of activities in progress.
Based upon the results of this inspection, certain of your activities appeared
.
to be in violation of NRC requirements, as specified in the enclosed Notice of
Violation (Notice).
.One violation related to Waterford-3's policy which allows contractor
supervisors 90 days to complete the required supervisory training.
10 CFR 26.22 rq uires that all supervisory personnel, including contractors, be
trained in supervisory aspects of the program.
In accordance with Section V.G.I. of the NRC's Enforcement Policy, no citation
is being . issued for the second violation described in Section 6 of the enclosed
inspection report.
You are required to respond to this letter and should follow the instructions
specified in the enclosed Notice when preparing your response.
In your
response, you should document the specific actions-taken and any additional
. actions you plan to prevent recurrence. After reviewing you response to this
Notice, including your proposed corrective actions and the results of future
inspections, NRC will determine whether further NRC enforcement action is
necessary to ensure compliance with NRC regulatory requirements.
RIV:NMSIS
C:NMSIS
0:DRS$
D:DRP
MLMcLean: p CLCain
ABBeach
SJCollins
st
J ////91
/ /91
/ /91
/ /91
-
_
_.
.
.
Entergy Operations, Inc.
-2-
In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a cocy of
tt.is letter and its enclosures will be placed in the NRC Public Document Room.
The response directed by this letter and the enclosed Notice are not subject to
the clearance procedures of the Office of Management and Budget as required by
the Paperwork Reduction Act of 1980, Pub. L. No. 96.511.
Sincerely,
OP.!GfNE si n g g
Samuel J. Collins, Director
Division of Reactor Projects
Enclosures:
1.
Appendix A - Notice of Violation
2.
Appendix B - NRC Inspection Report
50-382/91-04
cc w/ enclosures:
Entergy Operations, Inc.
ATTN:
Donald C. Hintz, Executive Vice
President & Chief Operating Officer
P.O. Box 319il5
Jackson, Mississippi
39286
Entergy Operations, Inc.
ATTN: Gerald W. Muench, Vice President
Operations Support
P.O. Box 31995
Jackson, Mississippi
39286
Wise, Carter, Child & Caraway
ATTN:
Robert B. McGehee, Esq.
P.O. Box 651
Jackson, Mississippi
39205
Entergy Operations, Inc.
CTN:
J. R. McGaha, Jr. , General
Manager Plant Operations
P.O. Box B
K111ona, Louisiana 70066
Entergy Operations, Inc.
ATTN:
J. G. Dewease, Senior Vice
President, Planning & Assurance
P.O. Box 31995
Jackson, Mississippi
39286-1995
-
-
- - . - , -
. - - .
.
__.
. - - . -
- - - - - - - - . -
- - -
.
-_
_ _ _ - _ - _ _ _ _
_ - _ _ _ _ _ _ - - . _ _ - _ _ _ _
.
.
Entergy Operations, Inc.
-3-
Entergy Operations, Inc.
ATTN:
L. W. Laughlin, Site
Licensing Support Supervisor
P.O. Box B
K111ona, Louisiana 70066
Shaw, Pittman, Potts & Trowbridge
ATTN: Mr. E. Blake
2300 N Street, NW
Washington, D.C.
20037
Chairman
Louisiana Public Service Commission
One American Place, Suite 1630
Baton Rouge, Louisiana 70825-1697
Entergy Operations, Inc.
ATTN:
R. F. Burski, Director
Nuclear Safety
317 Baronne Street
New Orleans, Louisiana 70112
Department of Environmental Quality
ATTN: Glenn Miller, Administrator
Radiation Protection Division
P.O. Box 14690
Baton Rouge, Louisiana 70898
President, Parish Council
St. Charles Parish
Hahnville, Louisiana 70057
Mr. William A. Cross
Bethesda Licensing Office
3 Metro Center
Suite 610
Bethesda, Maryland 20314
bec to DMB (IE01)
bec distrib. by RIV:
- R. D. Martin
- Resident Inspector
- Section Chief (DRP/A)
- DRP
- DRSS-RPEPS
- MIS System
- Project Engineer (DRP/A)
- RSTS Operator
"RIV File
- DRS
- D Wigginton, NRR Project Manager (MS:
13-D-18)
Lisa Shea, RM/ALF
- ABBeach
- LAYandell
- MLMc Lean
- Security File
- w/766
_ _ _ _ - _ _ _ - _ _