Memorandum & Order (Telcon ).* Applicants Will File Answers to Questions,Nrc Will File Response & Intervenor Will File Supplemental Info by 910322.W/ Certificate of Svc.Served on 910123
ML20029A022
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 01/22/1991
From: Bechhoefer C
Atomic Safety and Licensing Board Panel
To: Bailey J, Carroll G, Hoffarth D
GEORGIA POWER CO., GEORGIANS AGAINST NUCLEAR ENERGY
References
CON-#191-11326 90-617-03-OLA, 90-617-3-OLA, OLA, NUDOCS 9102010064
Download: ML20029A022 (5)


Text

$

/l>3 $9

Lt.! M

' :,Ne L UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION

'91 JM 23 A10:30 ATOMIC SAFETY AND LICENSING BOARD s

., r ' r t ca

it-i

,,mt Defore Administrative Judges:

Charles Bochhoefer, Chairman Dr. James H. Carpenter SERVED JAN 2 3 991 Dr. Emmoth A.

Luebke Docket Nos. 50-424-OLA In the Matter of 50-425-OLA GEORGIA POWER CO.,

et al.

ASLBP No. 90-617-03-OLA (Vogtle Electric Generating Plant, Units 1 and 2) i Facility Operating Licenses NPF-68 and NPF-81 January 22, 1991 MEMORANDUM AND OPDER (Telenhone Conference Call. 1/22/91)

On January 22, 1991, the Licensing Board conducted a telephone conference call, for the primary purpose of posing i

certain clarifying questions, derived from the Supplemental Statement submitted by the Applicants and the responses I

thereto submitted by GANE and the Staff.

Participating in l

l the call were all members of the Licensing Board;

Messrs, i

Arthur H.

Domby and Ernest L.

Blake (joined by Mr. James Bailey), for the Applicants; Ms. Glenn Carroll and Mr.

Dennis Hoffarth, for GANE; and Mr. Charles A.

Barth (joined by Messrs. Darl Hood, Ralph E. Architzel and Patrick M.

Madden), for the NRC Staff.

At the outset, the Board reminded Ms. Carroll that it had contacted her the preceding week about a possible 4/

9102010064 910122

)b PDR ADOCK 05000424 O

PDR

, typographical error in GANE's response to the Applicants' Supplemental Statement, and that she had agreed there was such an error and that she would notify the Board and i

parties.

Because Ms. Carroll had not yet done so, the Board l

agreed that it would set forth the correction in this Order.

Specifically, the reference by GANE, in paragraph 4, p. 1 of its December 10, 1990 response, to "FSAR, Sec. 2.2.6" should instead have been a reference to VEGP 13145-1, rev. 25, S 2.2.6 (at p. 4 of 46).

The other questions posed by the Board were:

1.

Is the obligation to dispatch an operator to the diesel in the event of an automatic diesel start mandatory or permi"sive?

In other words, instead of the permissive word "o

-ald," did the Applicants intend to use a mandatory term such as "Will" or "must," at DCP-90-V1NO138-0-1, page 1

(

l of 2, and DCP-90-V2N0166-0-1, page 1 of 2 (both included in Exhibit 1 of Applicants' Supplementary Statement)?

2.

What has been the observed failure rate in the industry of the three-way valve that bypasses the NSCW/ jacket water heat exchanger?

l 3.

Provide the calculations used to ascertain the l

10*/ minute temperature rise estimated by the Applicants and relied upon by the Staff at Architzel Aff., T6 (p. 7) and Correia Aff., 14 (p. 9).

As elaborated during the conference call, have there been any start-up observations of diesel generator temperature rise?

1 1

- 4

. 4.

How is the calibration of the Calgon sensors locked into place?

Why does the calibration drift?

5.

How is the capab..ity for testing the status and operability of the bypass circuits maintained, as required by Reg. Guide 1.9, Position 7?

6.

Inasmuch as Reg. Guide 1.9, Position 7, conditions the grant of bypass authority on the alarming in the control room of " abnormal values of all bypaso parameters," how can the Staff justify granting the Applicants an exemption from this requirement (as applicable to the HJWT trip alarm) until after May, 1991 (see Applicants' letter, dated January 10, 1991; Architzel Aff., 15:

Chopra Aff., 17).

Informing operators that the alarm does not work does not appear to meet the Reg. Guide requirement satisfactorily.

What action, if any, is the Staff proposing to take as a result of the apparent lack of the trip alarm from May 25, 1990 to December, 1990, when this deficiency was first uncovered by the Staff?

7.

Which, if any, of the 11 power plants referenced by Mr. Alfred E.

Chaffee at page 5 cf his affidavit (line 20) have sought a license amendment to permit (or have licenses permitting) bypassing the Calcon sensors in emergency conditions?

What was the Staff action on each request?

8 (suggested by GANE).

What are the normal shift-manning requirements for operators at the facility?

c..-

)

. )

3 As agreed upon during the telephone conference call, j

the Applicants shall file their response (to all except questions 6 and 7) by Friday, March 22, 1991.

The Staff.

shall file its response to questions 6 and 7 by the same date.

Further, GANE shall file its supplemental information concerning the asserted 25*/ minute temperature. rise (and relevant to-the subject of question 3) as soon as.possible but in no event later than March 22, 1991.

All of the above responses or material are to be filed by express mail (or by I

means designed to rt h the recipients no later than the delivery time for er tss mail, if filed on the latest date' available, see 10 C.F.R. S 2.710).

Comments by the various-participants on the foregoing' filings shall be submitted (by 4

regular mail) no later than Monday, April 22,;1991.

Following receipt of all this material, the Board will determine whether further activities in this proceeding are-warranted.

l IT IS SO ORDERED.

FOR THE ATOMIC SAFETY AND LICENSING DOARD ha

>J Charles Bechlioefer, Ch/irman ADMINISTRATIVE JUDGE Bethesda, Maryland January.22, 1991 1

-_....._........u._;__

UNITED S?ATES OF AMERICA NUCLiAR REGULATORY COMMISB!ON In the Matter of 1

GEORGIA POWER COMPANY. ET AL.

I Docket No.(s) 50-424/425-OLA I

(Vogtle Electric Genert. tina Plant.

I Units 1 and 2)

I 1

CERTIFICATE OF BERVICE I hereby certify that copies of the foregoino LB M60 (TELE. CONF. CALL 1/22)

I have been served upon the following persons by U.S. sail, first class, except as otherwise noted and in accordance with the requirements of 10 CFR 6ec. 2.712.

Atomic Safety and Licensing Appeal Administrative Judge Board Charles Bechhoefer, Chairman U.S. Nuclear Reculatory Cosaission Atente Safety and Licensing Board Washington, DC 20555 U.S. Nuclear Regulatory Consission Washington, DC 20555 Administrative Judge Administrative Judge James H. Carpenter Eameth A. Luebke Atomic Safety and Licensing Board 5500 Friendship Boulevard, Act. 1923N U.S. Nuclear Regulatory Consission Chevy Chase, MD 20815 Washincton, DC 20555 Charles A. Barth. Escuire Arthur H. Domby Office of the General Counsel Troutaan, Sanders, Lockerman & Ashmore i

U.S. Nuclear Regulatory Cosatssion Candler Buildino, Suite 1400 Washington DC 20555 127 Peachtreet Street, NE.

Atlanta, GA 30303 Ernest L. Blake, Jr., P.C.

Glenn Carroll Bhan. Pittman, Potts and Trowbridge Georgians Against Nuclear Energy 2300 N Street. NW.

P.O. Box 8574 Washinoton, DC.

20037 Atlanta, GA 30306 l

l Dated at Rockville. Md. this 23 day of January 1991

.......b. %..............

Office of the Secretary of the Consission

.