Forwards List of Implementation Dates for Generic Ltr 90-03 Re Relaxation of NRC Position in Generic Ltr 83-28,Item 2.2, Part 2.Implementation of Util Key Vendor Contact Program Delayed from 901231 to 910114
ML20028H672
Person / Time
Site: Waterford Entergy icon.png
Issue date: 01/23/1991
From: Burski R
ENTERGY OPERATIONS, INC.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GL-83-28, GL-88-14, GL-90-03, GL-90-3, W3F1-91-0001, W3F1-91-1, NUDOCS 9101250061
Download: ML20028H672 (2)


Text

{{#Wiki_filter:f .

       +                                                                                                            1 Entergy opsrations,inc.
         * -{"-~~ Entergy:

(: Ope, rations - 3 " s>- s' Ww Orav lA 70112

                                                                                        *
  • sus 1 '

TN 504 J39-077a Raymond F. Burski vs a;e> 5 3 8. #tCAdlWg Ai os W3F1-91-0001 A4.05 QA January 23,J1991; U.S. Nuclear Regulatory Commission i ATTN: Document - Control Desk

   'F              . Washington, . D.C. : 20555 0               . 

Subject:

         'Waterford .3 SES Docket No. 50-382 License No. NPF-38 '

Licensee implementation Dates Gentlemen:

                   . As: requested :by a. representative of the NRC Staff, please find attached a brief summary; which serves to confirm. the Licensee Implementation Dates for -
                   - the three items listed.

Please- note _that the completion date for "Waterford GL' 90-03, Relaxation of  ! Staff Position in --GL 83-28, Item 2.2 Part '2" has been changed. We informed youx(W3P90-1492 L dated October 1, _1990) that 'the.'Waterford 3 Key _ Vendor ~

Contact:

Program was in place and functioning,cand full implementation would o_ccur'upon final _ procedure issuance by December 31,.1990.- Due to

                   - administrative constraints signature , approval (was delayed and procedure                     ,

issuance -occurred on January 14,1991. . Should yo,u -have any questions or need additional information, please contact-L.W.- Laughlin at (504) 739-6331. lI Very 'truly yours, lbuub'

                   . RFH /PLC/ssf-
               . ' Attachment ec: . Messrs. R.D. Martin, NRC Region IV
                             .D.L. Wigginton, .-NRC-NRR-E.~L. Blake .

R.B. McGohee NRC Resident ~ Inspectors Office 9 0\

                                                                                /

l 9101250061 910123 PDR ADOCK:0500g2 , P  ; \ - .-.. N

v% Attachment to . . W3F1-91-0001 . Page 1 of 1 \ U.S. NRC Implementation Task I.D. Title Date Remarks M71737 "Waterford Instrument Air Following Refuel 4 Two valve air accumulators are to be modified (Generic Letter 88-14)" 5/31/91 to assure margin is restored. (See Inspection Report Violation 50-382/8911-01 and Licensee submittal W3P89-3048 dated 6/9/89.) M75571 "Waterford 3 Surveillance 4/2/90 Amendment 62 to OL NPF-38 issued 4/2/90. Times (106)" Modified T.S. 4.0.2, Surveillance Requirements. The new provision is not used repeatedly but performed on a case by case basis. (See GL 89-14) Ri76311 "Waterford GL 90-03, Relaxation 1/14/91 Final procedure issuance. of Staff Position in GL 83-28, Item 2.2 Part 2"

                                                                                                                                                   ,}}