ML20028F156
| ML20028F156 | |
| Person / Time | |
|---|---|
| Site: | Waterford |
| Issue date: | 01/24/1983 |
| From: | Maurin L LOUISIANA POWER & LIGHT CO. |
| To: | Jay Collins NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| References | |
| 1-CFR-50.55E, 10CFR-050.55E, 10CFR-50.55E, 42, 48, W3I83-0017, W3I83-17, NUDOCS 8301310193 | |
| Download: ML20028F156 (1) | |
Text
r =
P O W E R & L I G H T! P O BOX 6008
- NEW ORLEANS. LOUISIANA 70174 142 DELARONDE STREET
- (504) 366 2345 MrODt f SOUTH U riu rit S S fSTEM L. V. MAURIN January 24, 1983 vice President 3$h[l!'
'l; Il T.
Nuclear Opcodons I
l W3I83-0017 JAN 261983 Q-3-A35.07.42 i
\\
Q-3-A35.07.48
/
N 1
=rr;q q,
Mr. John T. Collins, Regional Adminisi mm., :e m I'l U. S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76012
SUBJECT:
Reopening of Significant Construction Deficiencies 42 and 48
Dear Mr. Collins,
As a result of a NRC site review of SCD files for which final reports have been submitted by LP&L, it has been determined that the final reports sub-mitted for SCD's 42 and 48 do not adequately describe the scope of the corrective action performed. The Nonconformance Reports (%CR's) used to identify the problem and track the corrective action have been reopened.
Upon disposition of these NCR's, LP&L will resubmit final reports for SCD's 42 and 48.
It is anticipated that final reports on these SCD's will be transmitted to the NRC by February 14, 1983.
If you have any questions, please advise.
u l/
/
27Nuan L. V. Maurin LVM/ MAL:keh cc:
- 1) Director 3)
E. L. Blake Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.
20555
- 2) Director 4)
W. M. Stevenson Office of Management Information and Program Control U. S. Nuclear Regulatory Commission Washington, D. C.
20555 0
/
8301310193 830124 PDR ADOCK 05000382 s
PDH l