ILLINDIS POWER 00MPANY

/g lg (91_,4)6 500 SOUTH 27TH STREET. DECATUR, ILUNOIS 62525 January 24, 1983 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.

20555

Dear Mr. Denton:

Reference:

IP Letter 10/11/82 (U-0561), L. J. Koch to H. R.

Denton, NRC Clinton Power Station Unit 1 Docket No. 50-461 The referenced letter provided a quarterly update report on the Clinton Unit 1 construction schedule.

This is another quarterly updating and our current schedule for Clinton Unit 1 remains unchanged from the last report to you, i.e.,

construction completion and fuel loading in January, 1984 and commercial operation projected for August, 1984.

We will comply with your request to provide your office with quarterly updates.

Our next schedule report will be sent in May, 1983.

Sincerely,

/N &

1

,d L

J. Koch Vice President GEW/jmm cc:

Dr. H. Abelson, NRC Clinton Project Manager Mr. H. H. Livermore, NRC Resident Inspector j

Illinois Dept. of Nuclear Safety QD J 0301200057 830124 PDR ADOCK 05000461 A

ppg