Commonw cith Edison C
One First National Plaza. CNcago. tilinois C ~'
Address Reply to: Post OUse Box 767
~
N Chicago, Illinois 60690 January 13, 1983 Director of Nuclear Reactor Regulation Attention:
Mr. A. Schwencer, Chief Licensing Branch #2 Division of Licensing U.
S. Nuclear Regulatory Commission Washington, DC 20555
Subject:
LaSalle County Station Unit 2 Expected Fuel Load Date NRC Docket No. 50-374 Reference (a):
D. G. Eisenhut letter to L. O.
De1 George dated May 3,
- 1982,
" Extension of Construction Completion Date - LaSalle County Station, Unit 2."
Dear Sir:
The purpose of this letter is to provice you uitn information on tne expected fuel load data for LaSalle Caunty Station Unit 2.
The applicant has determined that fuel load for LaSalle County Station Unit 2 is no longer expected to occur in April, 1983.
The status of Unit 2 is currently being re-evaluated at the highest levels of corporate managen.ent arid cor.siJeratio7 is being given to issuance of a new projected fuel load date within the next several weeks.
Reference (a) granted an extension of Construction Permit CPPR-100 for the latest completion cate for LaSalle County Station Unit 2 to September 30, 1983.
The applicant currently expects that fuel load will be achieved without need for further extension of the Construction Permit.
Enclosed for your use are one (1) signed original and thirty-nine (39) copies of this letter.
Very truly yours,
, //3 C
C.
W.
Schroeder Nuclear Licensing Administrator 1m cc:
Mr. J. G. Keppler - Region III NRC Resident Inspector - LSCS llf 8301210114 830113 PDR ADOCK 05000374 A