Responds to NRC 820826 & 1124 Ltrs Re Violations Noted in IE Insp Rept 50-320/82-10.Corrective Actions:Completion of Reorganization Process Requires Tech Spec Change.Change Request Submitted on 821129 Pending NRC Approval
ML20028D053
Person / Time
Site: Crane 
Issue date: 12/29/1982
From: Kanga B
GENERAL PUBLIC UTILITIES CORP.
To: Haynes R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML20028D051 List:
References
4410-82-L-0078, 4410-82-L-78, NUDOCS 8301140449
Download: ML20028D053 (2)


Text

7..

I' GPU Nuclear Corporation Nuclear l;:=getb 48o s

Middletown, Pennsylvania 17057 717 944-7621 TELEX 84 2386 Writer"s Direct Dial Number:

December 29, 1982 4410-82-L-0078 Office of Inspection and Enforement Attn: Mr. Ronald C. Haynes, Director Region I US Nuclear Regulatory Camission 631 Park Avenue King of Prussia, PA 19406

Dear Sir:

Wrce Mile Island Nuclear Station, Unit 2 ('IMI-2)

Operating License No. DPR-73 Docket No. 50-320 Inspection Report 50-320/82-10 Status Update 1.

Capletion of' reorganization by December 31, 1982 As stated in the response to Inspection Report 82-10, completion of the reorganization process at 'IMI-2 requires a Technical Specification Change due to the nodification of the safety review process. Wis change request was subnitted on Novenber 29, 1982, and is pending NRC approval. Additionally, impimentation of the nodified safety review process requires training of personnel involved in this process. h is training is presently underway. Based on training constraints, completion of the reorganization will be delayed beyond Decenber 31, 1982. Training of essential personnel will be cmpleted by January 14, 1982, with training of additional personnel continuing thereafter, and inplementation of the new organization will be empleted shortly after NRC approval of the Technical Specification Change Request.

l 2.

Issuance of 80% of presently drafted procedures by December 31, 1982 Cmpletion of this cmmitment, as clarified by an NRC Ictter from R. W. Starostecki to B. K. h'anga dated November 24, 1982, has been postponed to January 3,1983, In order to inplement the new procedure process at the start of the new year. Wis change in inplenentation date is a minor nodification of GPU's previous cmmitment and is provided for your information.

3.

Finish Review of empleted work requests by January 31, 1983 GPU letter 4410-82-L-0040 dated Novmber 2,1982, provided a description o'. the extent of GPU's review of empleted work. Wis review is currently in progress and should be cmpleted by January 31, 1983.

8301140449 8305l'E

'I'on is a subsidiary of the General Pubhc Utihties Corporation

~

PDR ADOCK 05000320 Q

PDR

e

.b.RohaldC.Haynes

~ 4410-82-L-0078 4

4.

Modification of Contracts to require doctnent distribution by Dec mber 31, 1982 This has aircady been accomplished for the contract / contractor that performs GPU's ventilation testing. Changes to the remaining.

contracts will be modified when the contracts are renewed effective January 1, 1983.

If you have any questions concerning any of the above items, please contact Mr. J. J. Byrne of my staff.

S cere C f

]

f.

ga

' ector, Dil-2 BKK/SDC/jep CC: Mr. L. H. Barrett, Deputy Program Director - TMI Program Office Dr. B. J. Snyder, Program Director - 31I Program Office l