Forwards Tabular Listings, Common Encl Identification Rept Equipment, Per 821105 Request for Justification of Compliance W/App R Fire Protection
ML20028B930
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 12/02/1982
From: Hukill H
GENERAL PUBLIC UTILITIES CORP.
To: Eisenhut D
Office of Nuclear Reactor Regulation
Shared Package
ML20028B931 List:
References
5211-82-281, NUDOCS 8212070251
Download: ML20028B930 (2)


Text

-. _- -

GPU Nuclear Corporation U Guclear

==8 B x80 Middletown. Pennsylvania 17057 717 944-7621 TELEX 84-2386 Writer"s Direct Dial Number:

Decanber 2,1982 5211-82-281 Officr. of Nuclear Reactor Regulation Attn: D. G. Eisenhut, Director Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C. 20555

Dear Sir:

Three Mile Island Nuclear Station, Unit 1 (TMI-1)

Operating License No. DPR-50 Docket No. 50-289 Fire Protection - Appendix R This letter transmits the following documents which were requested at the uPU Nuclear and NRC Staff Meeting on TMI-l compliance with 10 CFR 50 Appendix R on November 5, 1982.

Attachment 1 A tabular listing of associated circuits of the common enclosure type. The safe shutdown circuit and its function is identified on the first page of each primary circuit listing. The listing for each safe shutdown (primary) circuit identifies those circuits which are routed through the relay and

(

control rooms and share a common enclosure with a primary circuit elsewhere in the plant.

Ob Nineteen existing primary circuits which may be used for safe shutdown have been identified. Additional circuits required for safe shutdown of the L s, * ',

plant may be identified during detailed design of remate shutdown capability. s More associated circuits may be identified if any additional safe shutdown 9***

circuits are routed in existing enclosures.

Attachment 2 A tabular listing of both times required and times available to operate safe shutdown valves for fires in the various fire area / zones of the plant.

Attachment 3 An updated schedule and further justification for our already stated (July 1, 1982 letter) need for schedular relief for the completion of 10 CFR 50 Appendix F212070251 821202 PDR ADOCK 05000289 F PDR UPU Nuclear Lorporation is a subsidiary of the General Public Utilities Corporation

Mr. D. G. Eisenhut 5211-82-281 R modifications. Specifically, our request asked that those modifications which do not require plant shutdown or prior NRC approval be granted schedular exemption to be compieted no later t han the end of Cycle 6 refueling outage.

Schedules shawn are contingent upon equipment vendor ability to meet estimated delivery. We trust that the abcve stated information will assist your review of our technical and schedular exemption requests.

Sincerely, 06

' 0. kill Director, TM1-1 HDH:CJS:vj f cc: J. Van Vliet R. C. Haynes, w/o attachments R. Conte, w/o attachments e