Confirms 820913 Discussions Re HVAC Independent Review.Util Will Comply W/License Condition 2.C (33).(b) & Submit Review from CF Braun by 821008.Interim Rept Expected by 820920
ML20027B377
Person / Time
Site: LaSalle Constellation icon.png
Issue date: 09/13/1982
From: Schroeder C
COMMONWEALTH EDISON CO.
To: Novak T
Office of Nuclear Reactor Regulation
References
5005N, NUDOCS 8209200382
Download: ML20027B377 (2)


Text

,.

h Commonwealth Edison

[T ) one First N tionti Plaza. Chictgo. Ilknots

\\ C '7 Addr:ss R ply to: Post Office Box 767

\\

/ Chicago, Illinois 6Mi90 1

September 13, 1982 Mr. T. M.

Novak Assistant Director Division o f Licensing U.S. Nuclear Regulatory Commission Washington, D.C.

20555

Subject:

LaSalle County Station Unit 1 HVAC Independent Review NRC Do cket No. 50-373 Re ferences (a):

Cordell Reed letter to H. Denton Augus t 4, 1982.

(b):

License NPF-ll, Condition 2.C(33). (b).

Dear Mr. Novak :

Af ter discussions with the NRC staf f, Commonwealth Edison Company submitted Reference (a).

Following the NRC Commissioners' meeting on August 5, 1982, the NRC staff issued Reference (b).

The purpose of this letter is to confirm discussions today between C. W.

Schroeder o f Commonwealth Edison and Dr.

A.

Bournia of your staf f regarding the submittal date o f a report of the subject independent review o f HVAC at LaSalle.

Commonwealth Edison Company will comply with Reference (b) by submitting the results of an independent review of the HVAC l

system prior to exceeding 50% power operation.

It is currently l

expected that the C. F. Braun independent review will be completed l

by approximately October 8, 1982.

Because this date has slipped l

from the original target of September 15, 1982, Commonwealth Edison does not intend to submit a report on September 15, 1982.

C.

F. Braun has determined, however, that certain portions o f their final report are essentially complete at this time.

This includes a statement of independence, scope, work plan, experience of key personnel, etc.

In addition, they are summarizing their current status and outlook / projections.

poDI l

5005N 8209200 3$1p

T. M.

Novak September 13, 1982 Therefore, Commonwealth Edison expects that an interim report will be submitted for your review by September 20, 1982.

Because this information is currently available, you may be able to expedite your review of the final report by reviewing the interim report when submitted.

If there are any questions in this matter, please contact this office.

One (1) signed original and thirty-nine (39) copies of this letter are provided for your use.

Very truly yours, 9fl3)S7 C. W. Schroeder Nuclear Licensing Administrator 1m cc:

J.

G. Keppler NRC Resident Inspector 5005N l

O