ML20024J341

From kanterella
Jump to navigation Jump to search
Forwards Rev 1 of Westinghouse Rept SG-94-08-006, Farley-1 Cycle 12 IPC Assessment.... Info Requested in NRC SER Re TS Amend 106 to License NPF-2,dtd 940405 for Application of IPC for Cycle 13 Included in Rept
ML20024J341
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 10/04/1994
From: Woodard J
SOUTHERN NUCLEAR OPERATING CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20024J342 List:
References
NUDOCS 9410140072
Download: ML20024J341 (1)


Text

Southem Nuclear Operating Company Post Office Box 1295 Birmin0 ham. Alabama 35201 Telephone (205) 868-5086 m

Southern Nudear Operating Company J. D. Woodard Executive Vice President October 4, 1994 l

Docket No.: 50-348 l

U. S. Nuclear Regulatorv Commission ATTN: Document Control Desk Washington, DC 20555

)

Joseph M. Farley Nuclear Plant - Unit 1 Assessment ofIPC Methodolog Gentlemen:

/

This report provides the Cycle 12 interim plugging criteria (IPC) assessment and projected end-of-cy cle 13 steam line break leakage for the J. M. Farley Unit-1 steam generators. Included in this t

report is infbrmation requested in the NRC Safety Evaluation report related to Technical Specifications Amendment No.106 to Facility Operating License No. NPF-2, dated April 5,1994, for application of the IPC for Cycle 13.

If there are any questions, please advise.

Respectfully submitted, j

acEW odard EFB/ cit:asmtipc doe Enclosure cc: Mr. S. D. Ebneter Mr. B. L Siegel Mr. T. M. Ross 1200.0 9410140072 941004 I

DR ADOCK 05000348 PDR q