Application for Amend to Licenses DPR-77 & DPR-79,revising Visual Insp Schedule Per Generic Ltr 90-09, Alternative Requirements for Snubber Visual Insp Intervals & Corrective Actions
ML20024H276
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 05/24/1991
From: Wallace E
TENNESSEE VALLEY AUTHORITY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20024H277 List:
References
GL-90-09, GL-90-9, NUDOCS 9105310104
Download: ML20024H276 (2)


Text

A kemn u e. o

, en e n, y w~ n,.

.T hat 0( 241991 TVA-SQN-TS-91-06 10 CFR 50.9A U.S. Nuclear Regulatory Commission ATTN:

Document Control Desk k'ashington, D.C.

20555 Gentlemen:

In the Matter of

)

Docket Nos 50-327 Tennessee Valley Authority

)

50-328 SEQUOYAH NUCLEAR PLANT (SQN) - TECHNICAL SPECIFICATION (TS) CHANGE 91-06, SNUBBER VISUAL INSPECTION FREQUENCY In accordance with 10 CFR 50.90, we are enclosing a requested amendment to Licenses DPR-77 and DPR-79 to change the TSs of SQN Units 1 and 2.

The proposed changes to the snubber-related sections will revise the visual inspection schedule in accordance with Generic Letter 90-09, " Alternative Requirements for Snubber Visual Inspection Intervals and Corrective Actions";

delete the 50 percent drag force increase from the acceptance criteria for functional tests; and delete the Plant Operations Review Committee concurrence for snubbers that are added or deleted to the accessible or inaccessible listing.

The proposed TS change is identified in Enclosure 1.

The justification for the proposed TS change is provided in Enclosure 2.

A proposed determination of no significant hazards consideration performed pursuant to 10 CFR 50.92 is provided in Enclosure 3.

The Unit 1 Cycle 5 refueling outage is currently scheduled to begin October 4, 1991. TVA plans to utilize the relaxed visual inspection frequency during the upcoming Unit 1 outage.

Accordingly, we request your approval by September 1,1991, to allow adequate time to incorporate this change into our procedures and integrate it into the outage schedule.

We are requesting an implementation period of 30 days from the receipt date of the TS change to allow for procedural changes.

/9 0 9105310104 910524

/_.

PDR ADOCK 05000327

.I P

PDR

MAY 241991 2

U.S. Nuclear Regulatory Commissien Please direct questions concerning this issue to W. C. Ludwig at (615) 843-7460.

Very truly yours, TENNESSEE VALLEY AUTHORITY

,g?

l C#

/

-J h+

E. C. Wallace, Manager Nuclear Licensing and Regulatory Affairs Sworn to (no cubscribed before me this p?'/L day of DA 1991 Mw Notary Public

/

My Commission Expires /// Y i[2 Enclocures cc (Enclosures):

American Nuclear Insurere NRC Resident Inspector Attention:

Librarian Sequoyah Nuclear Plant The Exchange, Suite 245 2600 Igou Ferry Road 270 Farmington Avenue Soddy Daisy, Tennessee 37379 Farmington, Connecticut 06032 Me. S. C. Black, Deputy Director Mr. B. A. Wilson, Project Chief Project Directorate 11-4 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Region II One White Flint, North 101 Marietta Street, NW, Suite 2900 11555 Rockville Pike Atlanta, Georgia 30323 Rockville, Maryland 20852 Mr. D. E. LaBarge, Project Manal;er U.S. Nuclear Regulatory Commission One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852 Mr. Michael H. Mobley, Director (w/o Enclosures)

Division of Radiological Health T.E.R.R.A. Building 150 9th Avenue, N Nashvil'e, Tennessee 37203 l

1 i

-