....s O
TNCIDSimE Northern States Power Company Monticello Docket No. 50-263 l
Certain activities under your license appear to be in noncompliance with AEC license requirements as indicated below A.
Section 4.8, paragraph D, of the facility Technical Specifications states, "A sample from each of the Wasto Sample, Floor Drain, Condensate Storage, and Waste Surgo Tanks shall be taken, analyzed and recorded every 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. If no additions to one of the above tanks has occurred since the last sample, that tank need not be sampled until the next addition."
Contrary to the above requirement, no sampics were taken of the following tanks, as indicated, even though records show additions had been made to the tanks during the period.
Waste Sample Tank "B" September 14-20, 1971 September 29 - October 5, 1971 November 2-5, 1971 l
Waste Sample Tank "A" September 16-20, 1971 i
(
Deccaber 8-12, 1971 Floor Drain Sample Tank November 25 - December 15, 1971 Waste Surge Tank September 2 - December 15, 1971 B.
Section 4.8, paragraph C.2.d of the facility Technical Specifications states, " Grab sampics vill be taken from the discharge canal monthly and analyzed for tritium and significant isotopes."
Contrary to the above requirement, no analyses of canal samples for tritium were made for the months of August and September 1971.
/
4
(
9104300419 720209 PDR ADOCK 05000263 O
- - -