Provides Daily Highlight for 830825.Torrey Pines Technology Independent Review of Plant Project Mgt Rept Received on 830823.Rept Recommends Particular Mgt Organization to Verify Quality of Completed Design & Const & to Perform Testing
ML20024F032
Person / Time
Site: Zimmer
Issue date: 08/25/1983
From: Kintner L
Office of Nuclear Reactor Regulation
To: Carter J, Case E, Harold Denton
Office of Nuclear Reactor Regulation
References
NUDOCS 8309080137
Download: ML20024F032 (1)


Text

n AUG 2 5 1983, ___ _.

Docketl(50-358)N

^

PDR LPDR MEMORANDUM FOR:

H. R. Denton, NRR NSIC E. G. Case, NRR PRC Systen)

J. Carter, NRR D. Eisenhut, DL LB#1 Rdg H. Thompson, DHFS MRushbrook R. Vollmer, DE

-LKintner R. Mattson, DSI J. Sniezek, IE T. Spe's, DST J.-Stone, IE J. Sniezek, I&E T. Ippolito, ORAB T. Novak, DL G. Lainas, DL F. Miraglia, DL ~

THRU:

B. J. Youngblood, Chief, Lice.nsing Branch No. 1, DL FROM:

L. Kintner, Project Manager, Licensing Branch No.1, DL

SUBJECT:

DAILY HIGHLIGHT Zimmer Unit 1 A report describing the independent review of Zimmer Project Management by Torrey Pines Technology was issued to Cincinnati Gas & Electric Company on August 19, 1983 and a copy was received by NRR on August 23, 1983.

The review was made as the initial step in CG&E'S response to the Commission's November 12, 1982 Order suspending safety related construction at Zimmer.

Volume 1, the summary, recommends a particular management organization out of 16 alternatives considered, to verify quality of completed design and construction, complete construction, perform preoperational testing, licensing, and startup testing of the plant.

The recommended organization would retain most of the present CG&E Managers, including the P.esident and Senior Vice President, and hire an experienced external organization to manage construction and the quality verification program. Audits would be performed at the CG&E Board of Directors level and at the Senior Vice President level. The manager of quality assurance would have the same status as the managers of engineering, construction, and operations.

CG&E will evaluate the Torrey Pines Review and then submit a recommended course of action to Region III for approval. CG&E must then submit a plan to verify construction quality, complete the approved verification program, and then submit a plan for completion of construction before the Commission's Order suspending construction is lifted.

Original Signed bi Lester L. Kintner L. Kintner, Project Manager Licensing Branch No. 1 Division of Licensing DL:LB#1 DL:LB#1 LKintner:es BJYoungblood 8/25/83 8A5/83 8309080137 830825 PDR ADOCK 05000358 A