Revised Operating Data Rept Page to Monthly Operating Rept for June 1983
ML20024F012
Person / Time
Site: Millstone Dominion icon.png
Issue date: 08/15/1983
From: Gibson J
NORTHEAST NUCLEAR ENERGY CO.
To:
Shared Package
ML20024F006 List:
References
NUDOCS 8309080115
Download: ML20024F012 (1)


Text

..

o OPERATING DATA REPORT (JUNE REVISION)

DOCKET NO.

50-336 DATE COMPLETED BY J. Gibson TELEPHONE (203) 447-1791 Ext. 4431 OPERATING STATUS 1.

Unit Name:

Millstone 2 Notes: Items 21 and 22 cumulative 2.

Reporting Period:

June 1983 (Revision) are weighted ave, unit 3.

Licensed Thermal Power (MWt):

2700 operated at 2560 MW 4.

Nameplate Rating (Gross MWe):

909 thermal prior to its 5.

Design Electrical Rating (Net MWe):

870 uprating to its current 6.

Maximum Dependable Capacity (Gross MWe):

895*

2700 MW thermal power 7.

Maximum Dependable Capacity (Net MWe): 864*

1evel.

8.

If Changes Occur in Capacity Ratings (Items Number 3 Through 7)

Since Last Report, Give Reasons:

N/A 9.

Power Level To Which Restricted, If Any (Net MWe):

N/A 10.

Reasons For Restrictions, If Any:

N/A This Month Yr.-to-Date Cumulative 11.

Hours In Reporting Period 720 4343 65855 12.

Number Of Hours Reactor Was Critical 0

3130.5 48365.3 13.

Reactor Reserve Shutdown Hours 0

0 2205.5 14.

Hours Generator On-Line 0

2994.9 46182.2 15.

Unit Rererve Shutdown Hours 0

0 468.2 16.

Gross Thermal Energy Generated (MWH) 0 7877464 13171669 17.

Gross Elec. Energy Generated (MWH) 0 2575530 37806378 18.

Net Electrical Energy Generated (MWH) (-3011)**

2471358.3**

36233171**

19.

Unit Service Factor 0

69.0 70.1 20.

Unit Availability Factor 0

69.0 70.8 21.

Unit Capacity Factor (Using MDC Net) 0 65.9*

65.9*

22.

Unit Capacity Factor (Using DER Net) 0 65.4 65.0*

23.

Unit Forced Outage Rate 0

13.7 19.1 24.

Shutdgwns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

Continuation of Refuel / Maintenance Outage 25.

If Shut Down At End Of Report Period, Estimated Date of Startup:

26.

Units In Test Status (Prior to Commercial Operation):

Forecast Achieved INITIAL CRITICALITY N/A N/A INITIAL ELECTRICITY N/A N/A COMMERCIAL OPERATION N/A N/A

  • Incorrect MDC gross and MDC net values were used.
    • Corrects math error in original June report.