ML20024E663
| ML20024E663 | |
| Person / Time | |
|---|---|
| Issue date: | 07/29/1983 |
| From: | Potapovs U NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | Depowell A E.D. GIBERSON & CO., INC. |
| Shared Package | |
| ML20024E664 | List: |
| References | |
| REF-QA-99900834 NUDOCS 8308160344 | |
| Download: ML20024E663 (2) | |
Text
..
JUL 2 91983 Docket No. 99900834/83-01 E. D. Giberson & Company, Inc.
ATTN:
Mr. A. T. DePowell Vice President and General Manager 1330 Livingston Avenue North Brunswick, New Jersey 08902 Gentlemen:
This refers to the inspection conducted by Mr. L. E. Ellershaw of this office on June 14, 1983, of your facility at North Brunswick, New Jersey, associated with the supply of nuclear pipe, tubing and fittings and to the discussions of our findings with you and members of your staff at the conclusion of the inspection.
This inspection was made as a result of the NRC's initiation of inspections of material manufacturers and material suppliers in order to determine compliance with NRC and ASME Code requirements pertaining to procurement-activities.
Areas examined and our findings are discussed in the enclosed report. Within these areas, the inspection consisted of an examination of procedures and representative records, interviews with personnel, and obsewvations by the inspector.
The enclosed Notice of Violation is sent to you pursuant to the provisions of Section 206 of the Energy Reorganization Act of 1974.
You are required to submit to this office within 30 days from the date of this letter, a written statement containing: (1) a description of steps that have been or will be taken to correct these items; (2) a description of steps that have been or will be taken to prevent recurrence; and (3) the dates your corrective actions and preventive measures were or will be completed.
Consideration may be given to extending your response time for good cause shown.
The response requested by this letter is not subject to the clearance procedures of the Office of Management and Budget as required by the Paperwork Reduction Act of 1980, PL 96-511.
In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC's Public Document Room.
If this report contains any information that you believe to be exempt from disclosure under 10 CFR 9.5(a)(4), it is necessary that you (a) notify this office by telephone within 10 days from the date of this letter of your intention to file a request for withholding; and.(b) submit within
'RIV Np R&CPSI SC:R& CPS BC:VPB D:
h LEEllershaw/ mas IBarnes UPotapovs RL n art 7 /I /83 1 /22/83 1/$/87 01/[/83 g\\/,
t 8308160344 830729 k
PDR GA999 ENV*****
/
99900834 PDR 1
L
, ~,
r E. D. Giberson & Company, Inc. 25 days from the date of this letter a written application to this office to withhold such information.
If your receipt of this letter has been delayed such that less than 7 days are available for your review, please notify this office promptly so that a new due date may be established.
Consistent with Section 2.790(b)(1), any such application must be accompanied by an affidavit executed by the owner of the information which identifies the document or part sought to be withheld, and which contains a full statement of the reasons on the basis which it is claimed that the information should be withheld from public disclosure. This section further requires the statement to address with specificity the considerations listed in 10 CFR 2.790(b)(4).
The information sought to be withheld shall be incorporated as far as possible into a separate part of the affidavit.
If we do not hear from you in this regard within the specified periods noted above, the report will be placed in the Public Document Room.
Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
Sincerely, Of'Iffnal Signee g,g Uldis PotaPova i
Uldis Potapovs, Chief i
Vendor Program Branch
Enclosures:
1.
Appendix A - Notice of Violation 3.
Appendix B - Inspection Report No. 99900834/83-01 4.
Appendix C - Inspection Data Sheets (3 pages) l bec:
JTCollins, RIV RLBangart, RIV JEGagliardo, RIV EHJohnson, RIV MIS Section (J. Perry) l VPB Branch Chief VPB Section Chiefs i
VPB Inspector i
DMB-IE: 09 ASME l
NBB&PVI l
i
.I
)
i i
i l
~.
-