Notification of 830824-26 Meetings W/Util in Joliet,Il to Discuss Status of Const & Completion Schedules.Agenda Encl
ML20024D447
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 07/28/1983
From: Stevens J
Office of Nuclear Reactor Regulation
To: Youngblood B
Office of Nuclear Reactor Regulation
References
NUDOCS 8308050033
Download: ML20024D447 (6)


Text

-

n.

JUL 2 81983 i

. Docket Nos.: STN 50-456 and STN 50-457 MEMORANDUM FOR:

B. J. Youngblood, Chief, Licensing Brancn No.1, DL FROM:

J. A.-Stevens,. Project Manager, Licensing Bsanch No. 1. DL

SUBJECT:

FORTHCOMING NRC CASELOAD FORECAST PANEL VISIT TO THE BRAIDWOOD SITE DATE AND TIME:

August 24-26, 1983 9:00 a.m. - 4:00 p.m.

LOCATION:

Braidwood Plant Site Joliet, Illinois PURPOSE:

Assess status of construction and completion schedules for Braidwood Units 1 and 2 (Meeting Agenda enclosed).

PARTICIPANTS:

NP.C Staff W. Lovelace D. Hayes, L. McGregor, J. Stevens, J. Youngblood CECC Staff D. Swartz, et al.

Other Meeting between CECO and the NRC staff on the first day is open for interested members of the public, petitioners, intervenors, or other parties to attend as observers pur-suant to "Open Meeting and Statement of NRC Staff Policy,"

43 FR 28058, June 28, 1978 Of M M;::'dBV u.:A.L::tvens 830805o033 030728

~

gDRADOCK 05000456 J. A. Stevens, Project Manager PDR Licensing Branch No.1 Division of Licensing.

Enclosure:

Meeting Agenda.

cc w/ encl.: See next page ph

~

4[,l,IM e,nc.,.D.L,: Lg,(

D

- -. - ~ ~ -

- - - - - - - ~ ~ ~ ~

  • 3 13, 4

JStev

auR,

.1./.:4Z/.03........Z.

.a.3...........

m.,

NaC FORM 313 (10-40) NRCM 0240 -

OFFICIAL RECORD COPY use--asum -

e Mr. Dennis L. Farrar Director of Nuclear Licensing Commonwealth Edison Company Post Office Box 767 Chicago, Illinois 60690 cc:

Mr. William Kortier Atomic Power Distribution Westinghouse Electric Corporation Post Office Box 355 Pittsburgh, Pennsylvania 15230 Paul M. Murphy, Esq.

Isham, Lincoln & Beale One First National Plaza 42nd Floor Chicago, Illinois 60603 C. Allen Bock, Esq.

Post Office Box 342 Urbana, Illinois 61801 Thomas J. Gorden, Esq.

Waaler, Evans & Gordon 2503 S. Neil Champaign, Illinois 61820 Ms. Bridget Little Rorem Appleseed Coordinator 117 North Linden Street Essex, Illinois 60935 Mr. Edward R. Crass Nuclear Safeguards and Licensing Division Sargent & Lundy Engineers 55 East Monroe-Street

~

Chicago, Illinois 60603 i

U. S. Nuclear Regulatory Commission Resident Inspectors Office RRfi, Box 79 c

Braceville, Illinois 60407 i

Mr. James G. Keppler U. S. NRC Region III 799 Roosevelt Road Gle'n Ellyn, Illinois 6,0137 l

l

~

1 CASELOAD FORECAST PANEL SITE VISIT Braidwood Station,< Units 1 and 2 MEETING AGENDA Presentation for each unit-

1. -Overview of project construction and preoperational testing schedule, inc'.uding progress and major milestones completed, current problems and any anticipated problem areas that may impact the current pro-jected fuel' load date.

2.

Detailed review and current status of design and engineering effort

~

(by major discipline), including any potential problems that may arise from necessary rework.

~

3.

Detailed review and current status-of procurement activities, including valves, pipe, instruments, cable, major components, spare parts, etc.

4.

Actual and proposed craft work force (by major craft), craft avail-ability, productivity, potential labor negotiations and problems.

5.

Detailed review and current status of all large and small bore pipe hangers, restraints, snubbers, etc., including design, rework, pro-curement, fabrication, delivery and installation.

6.

Detailed review of project schedule identifying critical path items, near critical items, amount of float for various activities, the current critical path to fuel loading, methods of implementation of corrective action for any activities with negative float, and provisions for contingencies. The estimated project percent complete as of July 31, 1983.

7.

Detailed review and current status of bulk quantities, including current estimated quantities, quantities installed to date,;"qua6tTties scheduled to date, current percent complete for each, actual versus forecast installation rates, in cubic yards /mo., linear feet /mo~., or number /mo., and basis for figures.

(a) Concrete (CY)

(b) Process Pipe (LF)

Large Bore Pipe (21/2" and larger)

Small Bore Pipe (.2" and smaller)

(c) Yard Pipe (LF)

(d) Large Bore Pipe Hangers, Restraints, Snubbers (ea)

(e) Small Bore Pipe Hangers, Restraints (ea)

(f) Cable Tray (LF) 1r m-b T

"'w

'W 4

7-'~m

- ' - ' * --~ --

+'-<-t-4

~~-t--<-'-4~--

-- ~ - - -

r

= - ' -

"e*'

' - ' =

f'-

    • ~ -

(g)

Total Ccnduit (LF)

(h)- Total Exposed Metal Conduit (LF)

(i)

Cable (LF)

Power

- Control

- Securi ty

- Instrumentation Plant Lighting

'(j). Terminations (ea)

- Power

- Control

- Securi ty

- Instrumentation

- Plant Lighting (k)

Electrical Circuits (ea)

- power

- Control

- Security (1)

Instrumentation (ea)

Detailed review and current status of preparation of preop and acceptance 8.

procedures, integration of preop and acceptance test activities with tes construction schedule, system turnover schedule identifying each system and status, prhop and acceptance tests schedule identifying each test and status, current and proposed preop and acceptance testa y.v3 ram manpower.

Total number of procedures required for' fuel load.

(a) l (b)

Number of draft procedures not started.

I (c)

Number of draft procedures being written.

(d)

Number of procedures approved.

(e)

Number of procedures in review

( f) Total number of preop and acceptance tests required for fuel t

load identifying each.

l (g)

Number of preop and acceptance tests completed identifying each.

(h)

Number of preop and acceptance tests currently in progress identifying each and status.

(i)

Number ~of sys'tems and/or subsystems turned over to start-up identi fying each.

l l

l

. ~ -. -, _,_ _

e.

. g

9. - ;e ailed discussion and status of chances attricuted to twREG-0737 and otner recent licensing requirer.ents.

Discussion of schedular impact, if any, regarding poten"tial deficien--

10.

cies reported in accordance with 10 CFR 50.55(e).

Overview of current construction and startup management organization 11.. showing interfaces between the two.

12. Site tour and observation of construction actiyities.

i 0

0 e

e s

a f

O k

5 F

e B

L v-TF**'

P--

D-*h?v Y'

ti&=-

+TMFT='TT T*-

MEETING NOTICE JUL 2 81983

[ RC PDR-h I

kI NRC PARTICIPANTS:

N L PDR W. Lovelace PRC System D. Hayes NSIC L. McGregor J. Stevens LBf1 Rdg.

'J. Youngblood M. Rushbrook J. A. Stevens Project Manager H. Denton/E. Case D. Eisenhut/R. Purple T. Novak/S, Black A. Schwencer G. Knighton E. Adensam

' G. Lainas F. Miraglia F. Schroeder F. Rowsome J. Knight W. Johnston D. Muller T. Speis L. Rubenstein W. Houston E. Jordan, OIE J. Taylor, OIE Attorney, OELD ACRS (10)

F. Ingram, PA J

b