MONTHYEARML18152A2161999-02-23023 February 1999 Summary of 990119 Meeting with Util to Discuss Issues Re GL 97-04, Assurance of Net Positive Suction Head for Emergency Core Cooling & Containment Heat Removal Pumps ML18153B1971994-12-27027 December 1994 Notification of 950110 Meeting W/Util in Rockville,Md to Discuss Vision 2000 Program Update,Current & Future Licensing Activities & Cost Beneficial Licensing Actions ML18151A3451994-06-0303 June 1994 Summary of 940216 Meeting W/Vepco Re VEPCO Proposal for Five Year Term License Renewal,For Surry Npgs,Units 1 & 2 & North Anna Npgs,Units 1 & 2.List of Attendees,Agenda & Other Handouts Encl ML20059H8251993-10-29029 October 1993 Summary of 931028 Meeting W/Util Re Current Licensing Actions Ongoing at Plant.Licensing Actions Discussed Listed ML18152A4531993-09-0808 September 1993 Summary of 930825 Meeting W/Util in Rockville,Md Re Discussions on Integrated Trending Program,Ts Line Item Improvement,Regulatory Requirements Marginal to Safety & Surrey Fire Protection Tss.List of Attendees Encl ML18153D0121992-05-12012 May 1992 Summary of 920330 Meeting W/Util in Rockville,Md Re Significant Licensing Issues for Surry Units 1 & 2 & North Anna Units 1 & 2 ML18153C6941991-08-0808 August 1991 Summary of 910801 Meeting W/Util in Rockville,Md to Provide Opportunity to Describe Efforts Underway to Enhance Inservice Testing Program for Pumps & Valves at Both Surry & North Anna Stations ML18153C5891991-03-29029 March 1991 Summary of 910227 Meeting W/Util in Rockville,Md Re General Overall Status & Direction of Plants & Programs,Including Nuclear & Industrial Safety,Human Resources,Regulatory Compliance & Performance & Cost Mgt ML18153C2451990-06-0505 June 1990 Summary of 900523 Meeting W/Util in Rockville,Md Re Recent Changes in Matls Procurement Program.List of Attendees & Viewgraphs Encl ML20248D8821989-09-26026 September 1989 Summary of 890907 Meeting W/Util in Rockville,Md to Discuss Safety Sys Outage Mods Insp Finding IC-3,alleging That non-Class 1E Pressure Transmitters Powered from Class 1E Buses W/O Proper Isolation.Viewgraphs & Attendees List Encl ML20247E3641989-09-0606 September 1989 Summary of 890717 Meeting W/Numarc,B&W Owners Group & Representatives of Lead Plants Re Status of STS Amends & Outstanding Issues Associated W/Lead Plant STS Submittals ML18153B7971989-07-0606 July 1989 Summary of 890612 Meeting W/Util in Rockville,Md Re Plant Configuration Mgt Program.Informs That Goal of Program Is to Confirm That as-built Plants in Conformance W/Licensing Design Basis as Described in FSAR ML20246B8971989-07-0505 July 1989 Summary of 890615 Meeting W/Util & Westinghouse Re Lead Plant Implementation for Westinghouse Merits Tech Specs. List of Attendees,Agenda & Merits Program Description Encl ML20247K0901989-05-23023 May 1989 Summary of 890517 Meeting W/Inpo Re Similarities & Differences Between Performance Indicator Programs.Detailed Discussion Encl ML20247K1011989-05-16016 May 1989 Summary of 890517 Meeting W/Inpo in Bethesda,Md Re Similarities & Differences Between INPO & NRC Performance Indicators ML18153B7071989-05-0404 May 1989 Summary of 890419 Meeting W/Util in Rockville,Md Re Followup on NRC Bulletin 80-11, Masonry Wall Design. NRC Requested Documentation of as-built Boundary Conditions, Available Conservatisms & Field Verifications ML18153B6791989-04-11011 April 1989 Summary of 890330 Meeting W/Util in Rockville,Md Re Util Overall long-term Improvement Plan to Enhance Plant Operations ML20247F1991989-03-24024 March 1989 Summary of Operating Reactors Events Meeting 89-12 on 890322.List of Attendees,Events Discussed & Significant Elements,Summary of Reactor Scrams & Comparison of Weekly Statistics W/Industry Averages for Wk Ending 890319 Encl ML20247A8971989-03-16016 March 1989 Summary of Operating Reactors Events Meeting 89-11 on 890315.List of Attendees,Events Discussed & Significant Elements of Events & Four Events Identified for Input to NRC Performance Indicator Program & Summary of Scrams Encl ML20154P4171988-05-13013 May 1988 Summary of 880408 Meeting W/Util & Arrowhead Industrial Water,Inc in Rockville,Md Re Very Low Level Radioactive Concentrations Observed in Reverse Osmosis Sys Used to Generate Makeup Water at Plant.Attendance List Encl ML20151L0681988-04-0404 April 1988 Summary of 880127 CRGR Meeting 128 Re Listed Items,Including Review of Proposed Generic Ltr to Inform Licensees of New NRC Position on Guidelines for Determining Whether Operating Basis Earthquake Limits Exceeded ML20148K0921988-01-22022 January 1988 Summary of ACRS Subcommittee on Metal Components & Thermal Hydraulic Phenomena 871215 Meeting W/Vepco & Westinghouse in Washington,Dc Re Steam Generator Tube Rupture Failure & Dl Johnson Comments on Criteria for ECCS Rule ML20148H6621988-01-15015 January 1988 Summary of Operating Reactors Events Meeting 88-02 on 880112 Re Events Which Occurred Since Last Meeting on 880105.List of Attendees,Significant Elements of Events & Tabulation of long-term Followup Assignments to Be Completed Encl ML20236P2841987-11-0505 November 1987 Summary of Operating Reactors Events Meeting 87-38 on 871103.List of Attendees,Viewgraphs & Summary of Reactor Scrams Encl ML20238A5321987-08-26026 August 1987 Summary of 870729 Meeting W/Util & Westinghouse at Plant Re 870715 Steam Generator Tube Rupture.List of Attendees, Meeting Viewgraphs & North Anna Unit 1 870715 Steam Generator Tube Rupture Event Rept Encl ML20237G3791987-08-11011 August 1987 Summary of Operating Reactors Events Meeting 87-23 on 870721.List of Attendees,Viewgraphs & Summary of Reactor Scrams & Significant Events Encl ML18149A3681986-10-0909 October 1986 Summary of 860902 Meeting W/Util in Bethesda,Md Re Security Plans.Interpretation of Detection as Used in Regulations Addressed.Viewgraphs Encl ML20149C1001986-06-20020 June 1986 Discusses Attendance at 860528 & 29 INPO Accreditation Board Meetings.Board Attendees Listed & Major facility-specific Issues & Util Responses Discussed.Evaluation Method Appears Effective Overall.Nrc Involvement Should Be Maintained ML20141F4091986-04-10010 April 1986 Summary of Operating Reactors Events Meeting 86-10 W/Ofc Director,Div Directors & Representatives Re Events Since 860324.Viewgraphs & Supporting Documentation Encl ML20154N8751986-03-12012 March 1986 Summary of Operating Reactor Events 860310 Meeting 86-07 W/Ornl Re Events Occurring Since 860303 Meeting.Followup Review Assignments,Status of Previous Assignments,List of Attendees & Viewgraphs Encl ML20154P0071986-03-12012 March 1986 Summary of Operating Reactor Events 860303 Meeting 86-06 W/Ornl Re Events Occurring Since 860224 Meeting.Followup Review Assignments,Status of Previous Assignments,List of Attendees & Viewgraphs Encl ML20151N3021985-12-19019 December 1985 Summary of 851216 Operating Reactor Events Meeting 85-27. Attendance List,Viewgraphs of Events Discussed,Significant Event Elements,Assignment of Followup Review Responsibility & Status of Previous Assignments Encl ML20141E9501985-11-18018 November 1985 Summary of ACRS Subcommittee on Reactor Operations 851104 Meeting in Washington,Dc to Discuss Recent Plant Operating Experience.Fr Notice,Schedule of Discussion & Agenda Encl ML20136C5141985-11-11011 November 1985 Summary of Operating Reactors Event Meeting 85-21 on 851028.List of Attendees,Events Discussed & Completion Dates Assigned Encl ML20149B8651985-11-0404 November 1985 Summary of INPO Accreditation Board 851023-24 Meetings in Atlanta,Ga Re Training Programs for Listed Facilities, Performance Indicators,Nrc Exam Failure Rate & Instructor Qualifications ML20133E4631985-10-0101 October 1985 Summary of Operating Reactors Events Meeting 85-17 on 850923.List of Attendees & Viewgraphs Encl ML20138A1201985-09-23023 September 1985 Trip Rept of 850617-20 Site Visits Re Reduction of Wrong Unit/Wrong Train Events at Facilities ML20133Q4171985-09-0505 September 1985 Summary of 850823 Meeting W/Util in Atlanta,Ga Re Development of Scaling Factors for 10CFR61.55 Compliance. Attendance List Encl ML20128C9601985-06-25025 June 1985 Summary of 850607 Meeting W/Util in Bethesda,Md Re Svc Water Sys Piping Corrosion & Preservation Program.Nrr Approval Given to Portion of Util Mechanical Cleaning Program ML20127A7001985-06-0505 June 1985 Summary of 850506 Meeting W/Utils & Bechtel Corp in Bethesda,Md Re Respiratory Protection for Subatmospheric Containments.Agenda & List of Attendees Encl ML20024D4061983-07-25025 July 1983 Trip Rept of 830714 Site Visit for NRC & Lll to Obtain Addl Info Re Recurring Main Transformer Failures ML18139B9671982-07-13013 July 1982 Trip Rept of 820512-14 Visit to Facilities Re Radiological Effluent Tech Specs ML18139B6491981-12-0202 December 1981 Summary of 811113 Meeting W/Util in Richmond,Va Re Emergency Operations Facility & Technical Support Ctr.Agenda,Attendee List & Viewgraphs Encl ML20032C9041981-10-21021 October 1981 Trip Rept of 811008 Site Visit & Concurrent IE Plant Insp to Discuss Technical Assignment Control Sys for Facilities. Areas Inspected:Const of Machine Shop Bldg,Auxiliary Feedwater Pumps & Mods Underway on Powdex Demineralizers ML20031F1401981-10-0101 October 1981 Summary of 810918 Meeting W/Westinghouse Owners Group Re Pressurized Thermal Shock to Reactor Pressure Vessels. Attendance List & Handouts Encl ML20065H6621981-08-10010 August 1981 Summary of 810806 Operating Reactor Events Meeting.Related Info Encl.Next Meeting Scheduled for 820812 ML20030A9071981-07-22022 July 1981 Trip Rept of 810709 Site Visit to Observe Effects of Main Phase B Transformer Fire Which Occurred on 810703 ML20010D6101981-06-24024 June 1981 Minutes of ACRS Ad Hoc Subcommittee on Decay Heat Removal Sys 810505 Meeting Re Response to Commissioner Gilinsky Questions on RHS & Low Power Injection Sys Improvements & Re NRC Sponsored Work at Sandia Alternate Heat Removal Sys ML20126L2331981-05-0101 May 1981 Summary of 810429 Meeting W/Pwr Owners Group Re Thermal Shock to Reactor Pressure Vessels.All Parties Agree That Thermal Shock W/Subsequent Repressurization Is Safety Concern Needing Prompt Evaluation ML20126H6141981-04-0909 April 1981 Summary of 810320 Meeting W/Utils,Westinghouse & EPRI in Bethesda,Md Re Testing of Block Valves.Attendance List, Handouts & Vendor Ltrs Encl 1999-02-23
[Table view] Category:TRIP REPORTS
MONTHYEARML20138A1201985-09-23023 September 1985 Trip Rept of 850617-20 Site Visits Re Reduction of Wrong Unit/Wrong Train Events at Facilities ML20024D4061983-07-25025 July 1983 Trip Rept of 830714 Site Visit for NRC & Lll to Obtain Addl Info Re Recurring Main Transformer Failures ML18139B9671982-07-13013 July 1982 Trip Rept of 820512-14 Visit to Facilities Re Radiological Effluent Tech Specs ML20032C9041981-10-21021 October 1981 Trip Rept of 811008 Site Visit & Concurrent IE Plant Insp to Discuss Technical Assignment Control Sys for Facilities. Areas Inspected:Const of Machine Shop Bldg,Auxiliary Feedwater Pumps & Mods Underway on Powdex Demineralizers ML20030A9071981-07-22022 July 1981 Trip Rept of 810709 Site Visit to Observe Effects of Main Phase B Transformer Fire Which Occurred on 810703 ML20008F0621981-02-26026 February 1981 Summary of 810219 Site Visit Conducted by Aslab Re Replacement of Low Pressure Turbine Rotor 2 w/TMI-2 Low Pressure Turbine Rotor 2 ML19345C4501980-11-19019 November 1980 Trip Rept of 801113 Visit to Site to Inspect Lpdr,Discuss, Update & Provide Continuity on Active Ongoing Actions & Tour Plant ML19345G3641973-10-0101 October 1973 Trip Rept of 730929 Site to Observe Exposed Geologic Structures.Attendance List Encl 1985-09-23
[Table view] |
Text
.
kM41.dyg.
i
};
N51N3 e,
JUL 2 51983
$ /) p. O /lo MEMORANDUM FOR:
Robert A. Clark, Chief Operating Reactor Branch #3 Division of Licensing FROM:
Leon B. Engle, Project Manager Operating Reactors Branch #3 Division, of Licensing
SUBJECT:
TRIP REPORT - SITE VISIT TO OBTAIN ADDITIONAL INFORMATION REGARDING RECURRING MAIN TRANSFORMER FAILURES (MTFs) AT THE NORTH ANNA POWER STATION (NAPS) ;
On July 14, 1983, the NRC and its consultant (Lawrence Livemore National Laboratory - LLNL) met at' NAPS regarding the subject noted.
above. A list of attendees is provided in the Attachment.
_(1) to hold a The purpose of the site visit was two-fold: discussion with the VEPC0 staff regard a p.lant tour was made to acquaint LLNL with the physical plant layout with respect to MTFs.
General Meeting Highlights' '
O LLNL pmsented a status' update on the various tasks identified in the NRC statement of, work.
O LLNL presented a short summary on the present conclusions of its Probabilistic Risk Assessment (PRA) evaluation of the generator;and transformer protection system.
For the PRA analysis, it has been detemined that the increase in frequency of MTFs and plant nactor trip does not degrade.the plant protection system. Also, no modi-fications are warranted for the NAPS MTF protection system.
O VEPCO reported that the' investigation of the seventh failure (December 5,1982) is. complete (report to follow).
O A question / answer period was held where NRC_ requested additional information from VEPC0 regarding the MTFs.
O VEPC0 will contact GE and McGraw Edison representatives to help assist in obtaining operating and maintenance instructions for MTs.
Site Visit t
0 Pictures were taken to provide LLNL orientation of the plant physical layout to assist in the Failure Mode and Effects Analysis (FMEA) for MT fires, missiles and oil-spills.
O L,ar:1 tilf:ri::tici =: Obt: h:d by te r%g the tr r fe m ?
hay,,1 ocat.1,on,,and.,aMacent, struct,ure,s.,,,,,
p p pog g g gg; %
~~*
PDR our>
g
...,...................l....................
' "ac roa* 3'e na scinacu o24o
- OFFICIAL RECORD COPY
-.m. _- - m
l\\
. r. x a~
n ~.=m s
m-
?%iy D E C n s;g a 1 G 9 C r s; g ;~ M b
g-W-
- 2'd?
.42p o
.2-0 A tour of the turbine building and control room location was conducted with respect to potential MT missiles.
O A tour was made of the general area where reserve station service overhead lines have been relocated since the July 3,1981 MT fires.
0 A Status update was made by VEPC0 on any possible transformer bay modifications.
==
Conclusions:==
A formal NRC request for information to VEPC0 will be prepared based on the site visit and meet.ing discussions. A preliminary assessment following the tour determined that MTF missiles could have only insigni-ficant effects on LLNL's PRA and FEMA reports.. Oil spills and fins
~
will be included and expanded on in the LLNL mports.
Criginal signed by 4
Leon B. Engle, Project Manager Operating Reactors Branch #3 ~
Division of Licensing
Attachment:
Attendance List
^
cc: See next page A
\\O_s
? ll
/
o"'c5 > 0,R,B,f3:h~,,,,0,R,h(,,,,.,0RBj3p{Ct[,
cuoucur>.PMKr,s,d, tzer.........../..p n RAClaP LEngle 1
.r...............
..-..~.- -
.. -...y/ 8 3 Ocer) 7/6/83 7/2983 7/;15
.. ~............. -
, _ f3 oo "83-*o7247 -
NOC FORM 318 410,80l NRCM O240 OFFICIAL RECORD COPY
e MEETING
SUMMARY
DISTRIBUTION Licensee: Virginia Electric and Power Company
- Copies also sent to those people on service (cc) list for subject plant (s).
vDocket File NRC PDR L PDR NSIC ORB #3 Rdg ORB #3 Summary File JHcitemes BGrimes RAClark Project Manager PMKreutzer 0FJ.D ELJordan JMTaylor ACRS-10 NRC Participants JDonohue SNewberry MChiramal JKnight VBenaraya G
6
~ ~~
^ '
~
.u...
s s.
~
Virginia Electric and Power Company cc:
Richard M. Foster, Esq.
Musick, Williamson, Schwartz, leavenworth & Cope, P.C.
P. O. Box 4579 Boulder, Colorado 80306 Mrs. Margaret Dietrich Route 2, Box 568 Michael W. Maupin, Esq.
Gordonsville, Virginia 22042 i
Hunton, Williams, Gay and Gibson P. O. Box 1535 Mr. W. T. Lough Richmond, Virginia 23212 Virginia Corporation Commission Division of Energy Regulation Mr. Paul W. Purdom P. O. Box 1197 Environmental Studies Institute Richmond, Virginia 23209 Drexel University 32nd and Chestnut Streets Mrs. June Allen Philadelphia, Pennsylvania 19104 North Anna Environmental Coalition 8720 Lockmoor Circle Atomic Safety and Licensin9 Wichita, Kansas 67207 Appeal Board Panel U.S. Nuclear Regulatory Commission U.S. Environmental Protection Agency Washington, D. C.
20555 Region III Office ATTN:
Regional Radiation Representative Ellyn R. Weiss, Esq.
Curtis Building Sheldon, Harman, Roisman and Weiss 6th and Walnut Streets 1725 I Street, N.W. Suite 506 Philadelphia, Pennsylvania 19106 Washington, D. C.
20006 Regional Administrator Mr. E. W. Harrell Nuclear Regulatory Commission, Region II P. O. Box 402 Cffice of Executive Director for Operations Mineral, Virginia 23117 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303 Mr. Anthony Gambardella Office of the Attorney General 11 South 12th Street - Room 308 Richmond, Virginia 23219 l
l Resident Inspector / North Anna c/o U.S.N.R.C.
Route 2, Box 78A Mineral, Virginia 23117 Mr'. J. H. Ferguson Executive Vice President - Power Virginia Electric and Power Company Post Office Box 26666 Richmond, Virginia 23261 l
4 v-9g y+
~r*w-
ATTACHMENT North Anna Power Station Site Visit July 14,1983 Attendance List NRC VEPC0 L. B. Engle J. Leberstien R. E. Nicholls LLNL R. W. Broocks N. G. Vidonic J. W. Savage E. W. Harrel J. C. Selan W. R. Cartwright K. J. Dalton (EG&G)
- 0. Compton W. Bugg H. Suttan K. S. Berger C. G. Chewing J. M. Mosticane D. E. Thomas J. R. Harper I