ML20024C279
| ML20024C279 | |
| Person / Time | |
|---|---|
| Site: | Callaway |
| Issue date: | 06/30/1983 |
| From: | Dougherty C UNION ELECTRIC CO. |
| To: | Harold Denton Office of Nuclear Reactor Regulation |
| References | |
| ULNRC-644, NUDOCS 8307120477 | |
| Download: ML20024C279 (1) | |
Text
_ _ _ _ _ _ _ _ _ _ _ _ _.
UNION E LECTRIC C O M PANY 1901 GR ATIOT S T R E ET - ST. Louis cMARLs. J. DovowaRTY M AIUNG AD DR E..e C M A8-M A N P. O..OM 149
.a4
.v.
t o vi.. u o.....
. lune 30, 1983 c...... c u r.v. o
..c..
Mr. liarold R.
Denton, Director
~
Office of Nuclear Reactor Regulation Nuclear Regulatory Commission Washington, D.C.
20555 ULNRC-644
Dear Mr. Denton:
l DOCKET NUMBER 50-483 CALLAWAY PLANT, UNIT 1 QUARTERLY PROGRESS UPDATE l
Reference:
ULNRC - 615 Dated March 31, 1983 1
This is a quarterly follow-up response to your letter of May 27, 1981, regarding progress of our Callaway Plant.
Our schedule remains unchanged since our last report, which was transmitted by the referenced letter.
Fuel load is scheduled for April, 1984 with commercial operation scheduled for late 1984 or early 1985.
Sincere'.v, s
c c
)
-F M
N
._m
\\
8307120477 830630 DRADOCK05000g8 i
.a.
i r
.