ML20023B536

From kanterella
Jump to navigation Jump to search
Forwards QA Program Insp Rept 99900795/83-01 on 830314-17 & Notices of Nonconformance & Violation
ML20023B536
Person / Time
Issue date: 04/21/1983
From: Potapovs U
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Lott J
E.L. MANUFACTURING PEEBLES, INC.
Shared Package
ML20023B537 List:
References
REF-QA-99900795 NUDOCS 8305050162
Download: ML20023B536 (3)


Text

-

APR 211983 Docket No. 99900795/83-01 E. L. Manufacturing Peebles, Inc.

ATTN: Mr. J. E. Lott Vice President 69381 Sundury Road Westerville, Ohio 45081 Gentlemen:

This refers to the QA program inspection conducted by Mr. W. M. McNeill of this office on March 14-17, 1983, of your facility at Peebles, Ohio, associated with the fabrication of independent spent fuel storage casks and to the discussions of our findings with you and members of your staff at the conclusion af the inspection.

This inspection was made to confirm that in the areas inspected your QA program is being effectively implemented. The inspection effort is not designed to assure that unique quality requirements imposed by a customer are being achieved; nor to assure that a specific product, component, or service provided by you to your customers is of acceptable quality. As you know, the NRC requires each of its licensees to assume full responsibility for the quality of specific products, components, or services procured from others.

You should, therefore, not conclude that the NRC's inspection exempts you from inspections by an NRC licensee or his agents, nor from taking effective corrective action in response to their findings.

Areas examined and our findings are discussed in the encloscd report. Within these areas, the inspection consisted of an examination of procedures and representative records, interviews with personnel, ari observations by the inspector.

During the inspection, it was found that the implementation of your QA program failed to meet certain NRC requirements. The specific findings and references to the pertinent requirements are identified in the enclosures to this letter.

This Notice of Violation is sent to you pursuant to the provisions of Section 206 of the Energy Reorganization Act of 1974.

You are required to submit to this office within 30 days from the date of this letter, a written statement containing:

(1) a description of steps that have or will be taken to correct these items; (2) a description of steps that have or will be taken to prevent recurrence; and (3) the dates your corrective actions and preventive measures were or will be completed. Consideration may be given to extending your response time for good cause shown.

SCb[ CPS

(

[

RIV BC:V 3 D:DV&

~

)

pI:RECPS IBarnes UPotapovs RLBan pMMcNeill/ mas k/r)o/83 g&/%'83 k/p/83

%//83e/p g'

8305050162 830421 y

PDR GA999 EMVELMP 99900795 PDR

E. L. Manufacturing Peebles, Inc. You are also requested to submit a similar written statement for each item which appears in the enclosed Notice of Nonconformance.

The responses requested by this letter are not subject to the clearance procedures of the Office of Management and Budget as required by the Paperwork Reduction Act of 1980, PL 96-511.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC's Public exempt from disclosure under 10 CFR 9.5(a)y information that you believe to be Document Room.

If this report contains an (4), it is necessary that you (a) notify this office by telephone within 10 days from the date of this letter of your intention to file a request for withholding; and (b) submit within 25 days from the date of this letter a written application to this office to withhold such information.

If your receipt of this letter has been delayed such that less than 7 days are available for your review, please notify this office promptly so that a new due date may be established.

Consistent with Section 2.790(b)(1), any such application must be accompanied by an affidavit executed by the owner of the information which identifies the document or part sought to be withheld, and which contains a full statement of the reasons on the basis which it is claimed that the information should be withheld from public disclosure. This section further requires the statement to address with specificity the considerations listed in 10 CFR 2.790(b)(4). The information sought to be withheld shall be incorporated as far as possible into a separate part of the affidavit.

If we do not hear from you in this regard within the specified periods noted above, the report will be placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely, "Ortsteel signed tm U. PDTAPQV6

Uldis Potapovs, Chief Vendor Program Branch

Enclosures:

1.

Appendix A - Notice of Violation 2.

Appendix B - Notice of Nonconformance 3.

Appendix C - Inspection Report No. 99900795/83-01 4.

Appendix D - Inspection Data Sheets (3 pages)

I E. L. Manufacturing Peebles, Inc. bcc:

-JTCollins, RIV RLBangart, RIV JEGagliardo, RIV-EHJohnson, RIV MIS Section (J. Perry)

VPB Branch Chief VPB Section Chiefs VPB Inspector DMB-IE:09 JPRoberts, NHSS l