Interim Deficiency Rept Re Incorrect Structural Calculations Used for Holdup & Boric Acid Makeup Tanks.Const Completion Date Delayed So Final Rept Will Not Be Submitted Until 830221
ML20023B256
Person / Time
Site: Waterford Entergy icon.png
Issue date: 12/15/1982
From: Maurin L
LOUISIANA POWER & LIGHT CO.
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
10CFR-050.55E, 10CFR-50.55E, W3I82-0132, W3I82-132, NUDOCS 8212270166
Download: ML20023B256 (1)


Text

.

/

LOUISIANA P O W E R & L 1 G H T! P O BOX 6008 *

,42 octanoNot s1nar NEW ORLEANS LOUGIANA 70174 = (5041366 2345 sus $ SVSSE December 15, 1982 L v uAunin Voce Pre $Kient Nuckar Operatens W3182-0132 Q-3-A35.07.55 Mr. John T. Cc111ns, Regional Administrator Region IV U. S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76012

SUBJECT:

'Jaterford SES Unit No. 3 Docket No. 50-382 Significant Construction Deficiency Report No. 55

" Hold Up and Boric Acid Make Up Tanks Incorrect Structural Calculations"

~

Third Interim Report

REFERENCE:

LP&L letter W3K82-0480 dated August 5, 1982

Dear Mr. Collins:

At the present time, due to the delay in obtaining the required material to complete the construction modification to the boric acid tank supports, the construction completion date has been delayed.

l. final report will, therefore, be delayed until February 21, 1983.

Very truly yours,

[f

{ g 47 7 fill {l t-L L. V. Maurin LVM/ MAL:keh cc:

1) Director 3)

E. Blake Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.

20555

(

2) Director 4)

W. Stevenson j

Office of Management l

Information and Program Control U. S. Nuclear Pegulatory Commission l

Washington, D. C.

20555 l

(-'82f2270166 821215

~

1 PDR ADOCK 05000382 S

PDR I

.