GEH-MO: CY2020 Integrated Inspection Plan
ML20015A288
Person / Time
Issue date: 01/14/2020
From: Rhex Edwards
Division of Nuclear Materials Safety III
To: Mcfadden A
General Electric Co
References
Download: ML20015A288 (1)


Text

From: Edwards. Rhex To: "anthony.mdaddeo@ge.com" Cc: Kunowski. Michael; Edwards. Rhex

Subject:

GEH-MO: CY2020 Integrated Inspection Plan Date: Tuesday, January 14, 2020 9:29:47 AM

Dear Mr. McFadden,

In accordance with Inspection Manual Chapter 2690, "Inspection Program for Dry Cask Storage of Spent Reactor Fuel at Independent Spent Fuel Storage Installations and for 10 CFR Part 71 Transportation Packagings," the NRC Region Ill staff developed an Integrated Inspection Plan (IIP) for General Electric-Hitachi Morris Operation for calendar year 2020.

The inspection plan is based on your current performance and your planned activities for the site in January through December 2020. Below is a list of the periodic inspection procedures we expect to use during our inspections. The procedures used during each inspection will depend on the specific activities being conducted at the site. Additional discretionary inspection procedures may be used if ISFSI activities warrant. We will gladly discuss any questions you may have regarding this IIP. If you have questions, please contact me at (630) 829-9722. If you have questions related to security inspections, please contact the Plant Support Branch Chief at 630-829-9500.

Sincerely, Rhex Edwards Inspection Procedure No. Title 60855 Operation of an Independent Spent Fuel Storage Installation Rhex Edwards Senior Health Physicist Division of Nuclear Materials Safety U.S. NRC Region Ill 630-829-9722