I gc L Aw OFFICCs BISHOP, COOK, PURCELL & REYNOLDSRhlllD
- 140o L. STREET, N.W.
WASHINGTON, D.C. 20005 3502 (202)3715700 (IIlCE Of SLC0f7IObkoSM *TLa*U'
, wairca s osarcT DIAL uGCK[llNG \\ h6tif&ica woaisusoso SRANCH April 2, 1990 Peter B.
Bloch, Esquire Dr. Jerry Harbour
- Chairman, Atomic Safety and Atomic Safety and Licensing Licensing Board Board U.S.' Nuclear Regulatory U.S.
Nuclear Regulatory Commission Commission Washington, D.C.
20555 Washington, D.C.
20555 Mr. Glenn O.
Bright' Atomic Safety and Licensing Board U.S.
Nuclear Regulatory Commission Washington, D.C.
20555 Subj:
Washington Public Power Supply System (WPPSS Nuclear. Project l
No. 1) Docket No. 50-460-OL Gentlemen:
In accordance with the October 14, 1983, Memorandum and Order in the-captioned proceeding, the Washington Public Power l
Supply System hereby submits its twenty-sixth quarterly status l -
report regarding construction activities at WNP-1.
L
'During-the first quarter of 1990, no significant safety-l related construction activities were performed at WNP-1, although'a limited engineering effort was continuing.
We do not anticipate any change in this level of activity during the next several months.
f Since y,
6
[
9004060307 900402 PDR ADOCK 05000460-O PDR Nichola e nolds Counsel' fpr )p licant b
cc:
Service List 1
.