?,q, -

-D Il s

g

.J7.+-

ggg 414 Nicollet Mall 1

Minneapolis, Minnesota 554011927 Telephone (612) 3345500 i

T l

' March 21,-1990 Generic Letter 90 'i 1

{

Director of Nuclear Reactor Regulation U S-Nuclear Regulatory Commission Attn: Document Control Desk Washington,-DC 20555 1.

MONTICELLO NUCLEAR GENERATING PIANT Docket No. 50 263 License No. DPR-22 PRAIRIE ISLAND-NUCLEAR GENERATING PLANT Docket Nos. 50 282 License Nos. DPR-42 50 306 DPR-60 Response to Generic Letter 90-01 l

Request for Voluntary Participation in NRC Regulatory Impnet Survey-The attached information is submitted in response to Generic Letter 90 01,

- Request for Voluntary Participation in NRC Regulatory Impact Survey.. The -

information provided is identical for Prairie Island and Monticello.

The total impact on Northern States Power could be obtained by doubling the-numbers on the attached sheets.

The following assumptions.were made to fill out the questionnaire:

1)

Item 5:

The total time is provided in total hours per year for all the people involved.

Example:

120 hr (Number involved) 2 means 2 people would spend a total of 120 hours0.00139 days <br />0.0333 hours <br />1.984127e-4 weeks <br />4.566e-5 months <br /> per year. The average hours per year per person would be 60 hours6.944444e-4 days <br />0.0167 hours <br />9.920635e-5 weeks <br />2.283e-5 months <br />.

2).

Item 5:

Plant Department Heads were assumed to be individuals reporting directly to the Plant Manager.

I x

l um ne

,P-Od

--)

4 j&....

_ ~

Director of Nuclear Reactor Regulation March-21, 1990

'Page'2

.Please, contact us it you wish further information on this issue.

4 I

Thomas M Parker Manager Nuclear: Support-Services c:

' Regional Administrator Region-III, NRC Sr NRC Resident Inspector, Monticello

- NRC Project Manager, Monticello 1Sr NRC Resident Inspector, Prairie Island

NRC Project Manager, Prairie Island C Charnoff i

Attachment:

NRC Regulatory Impact Survey Questionnaire Sheets (8) 1 i

^.

1,

). '

b d

1' NRC Regulatory Impact Survey Sheet 1 of 8 Questionnaire sheet 2 1.

Type of inspection, audit or evaluation:

NRC Team Inspection Based on actual experience over the' past several' years, about how often

~ 2. - - is this activity conducted?

One per year

3. --

Operations / Construction areas covered 7

SSF1. Environment Qualification 4..

Extent of.the activity (how many people, for how long) 5 - 10 inspectors fer 1 to 2 weeks-

'5.-

Approximate percentage of total time (on an annual basis) which-the following managers must spend in direct' involvement before, during, and in response to-the activity described in Item 11.

2 120 hr (numberinvolved)

.a.

Plant Department Heads b.

Plant Manager 30 hr 1

16 hr (numberinvolved)'

c.

Corporate Department Heads d.

' Corp' orate Vice Presidents (numberinvolved) e.

Chief Nuclear Officer 8 hr

7 J

NRC' Regulatory Impact Survey Sheet 2 of 8-i Questionnaire Sheet i

i f

1.-

Type of. inspection, audit.or evaluation:

r

. Other NRC Restdent, Regional and lleadquarters inspectfons/ audits -

lo 2.-

B'ased on actual experience over the past several years, about how often is this activity; conducted?

25 per year

)

3.

Operations / Construction areas coveredt E

All areas of plant operation-t 4.

Extent of the activity (how many people, for how long) 2 - 3 Ir.spectors for a week t

-5.

Approximate percentage of total time (on an annual basis) which the

.following managers must spend in direct involvement before..during, and in response to the activity described in Item fl.

~

4 a..

Plant Department Heads 200 (numberinvolved)

~

b.

Plant Manager.- 50 150 (number. involved) ' 3 I

c.

. Corporate Department Heads 1:

d.

Corp' orate Vice Presidents (numberinvolved)

I e.

Chief Nuclear Of ficer 50 L

L I

NRC' Regulatory Impact Survey sheet 3 of 8 Questionnaire sheet--

1.- -

Type of inspection, audit or evaluation:

INPO Plant Evaluation 2.

Based on actual experience over the past several years, about how often j:

is this activity conducted?

~

Ebery other year' 3.

-Operations / Construction areas covered:

7~

All safety related areas of plant operation 4.

Extent of the activity (how many people, for how long) o 10 - 20 reople for 2 weeke 5.

' Approximate percentage of total time (on an annual basis) which the following managers must spend in directtinvolvement before, during, and -

in response to the activity described in Item fl.

6 a.

Plant Department Heads 480 (numberinvolved) b.

Plant Manager 120-2 80 (numberinvolved) c.

Corporate Department Heads d.

Corp' orate Vice Presidents (numberinvolved) e.

Chief Nuclear Officer 20

____.____a

l-u

~

^,_

NRC Regulatory Impact Survey Sheet'4 of 8

  • ~

n Questionnaire Sheet

1.. - Type of inspection, audit or evaluation:

Insurers (ANI)

D 2.

Based on actual experience over the past several years, about how often is.this activity conducted?

l 5 visits per year (except for Resident. ANI Inspector) 3.

-Operations / Construction areas coveredt 7

i All areas of plant operation 4;

Extent of the activity-(how many people, for how long) 2 people for 2 days (except for Resident ANI Inspector)

100 days per year Resident ANI Inspector f.

- 5.

Approximate' percentage of-total time (on an annual' basis) which the following managers must spend in direct involvement before, during, and i

in response to the activity described in Item 11, y>

2 16 (numberinvolved) a.

Plant Department Heads l -.I o

[

8 L

b.

Plant Manager 1

40 (numberinvolved) c.

Corporate Department Heads d.

Corp' orate Vice Presidents (numberinvolved) e.

Chief Nuclear Officer 4 hr L

1 !

a 1

m.

. m

m NRC Regulctory' Impact Survey-Sheet 5'of 8 Questionn_ aire sheet L1.:. Type of inspection, audit or evaluation:

o a

NRC Required QA Audits 2.

Based on actua1' experience over the past several years, about how often is this activity conducted?

50 per year 3.

Operations / Construction areas covered:

Y All areas of plant operation required by the Technical Specifications 4.

Extent of the activity; (how many. people, for how long) 1 to 2 people for a month 5.

Approximate: percentage of total time (on an annual basis) which the

.following managers must spend in direct involvement before, during, and in response'to the activity described in Item fl.

6 Plant Department Heads 300 (numberinvolved) a.

100 b.

' Plant Manager 3

150

_(numberinvolved) c.

Corporate Department Heads

~d.

Corp' orate Vice Presidents (numberinvolved) e.

. Chief Nuclear Officer 50

NRC Regulatory Impact Survey 0

~ ' '

Questionnaire Sheet i

- 1.-

Type of inspection, audit or evaluation:

[

EPA' State / Local Authorities 2.

Based on actual experience over the past several years, about how often is this activity conducted?

Two Annual Inspections (MPCA. EPA) 9

- 3.

Operations / Construction areas covered:,

Discharge locations, operating changes National Pollution Discharge-Elimination System, Quality Control associated with Chemistry Procedures f

5 4.

. Extent of the activity (how many people, for how long) 1 inspector per inspection L

L 5.

Approximate percentage of total time (on an annual basis) which the following managers must. spend in direct involvement before, during, and

-in response 7 to the activity described in Item #1..

a.

-Plant Department Heads 4

(number involved)

-l b.

Plant Manager 1

L c.

Corporate-Department Heads 2

(number involved) 1 L

g l:

d.

Corp' orate Vice Presidents 0

(number involved) 0 l

e.

Chief Nuclear-Officer 0

h l

i c

w

-NRC Regulatory Impact-Survey Sheet 7 of 8 Questionnaire sheet 1.

Type of inspection, audit or evaluation:

i j

- dot -

_2._-

Based on actual experience over the past several years, about how often is this activity conducted?

O

-3.

Operations / Construction areas covered:-

j

.e-0

-4.

Extent of the activity (how many people, for how long) 0

.5.

Approximate percentage of total time (on an annual. basis) which the-following managers must spend in direct involvement before,'during, and in response to the activity described in Item #1.

0 (numberinvolved) a.

Plant Department Heads b.

Plant Manager o

0 (number involved) c.

Corporate Department Heads 0

(numberinvolved) d.

Corp' orate Vice Presidents e.

Chief Nuclear Officer 0

1

n..'s.

NRC Regulatory Impact Survey She.n 8 d 8-p,-

Questionnaire Sheet 1

f El.

Type of inspection, audit or evaluation:

i 7

\\

OSHA

[

[

2.

. Based on actual experience over the past several years, about how often is.this activity conducted?

o

'l 4

3..

Operations / Construction areas covered:-

0 t

4.

Extentof,theactivity(howmanypeople,forhowlong) 0 5.

Approximate percentage -of total time (on an annual basis) which the following managers must spend in direct involvement before, during, and.

'in response to.the activity described in Item #1.

a.

Plant Department Heads 0

(number involved) 0 b.-

Plant Manager 0-c.

' Corporate Department Heads 0

(numberinvolved) 0 d.

Corp' orate Vice Presidents 0

(numberinvolved) 0 e.

Chief Nuclear Off'cer 0 E

.