Requests Extension of Amend Beyond 7-day Period Originally Requested for Emergency Basis Change to Tech Specs to Permit Removal from Svc & Repair of Sys Auxiliary Transformer (TR 242)
ML20011A125
Person / Time
Site: Zion File:ZionSolutions icon.png
Issue date: 10/01/1981
From: Lentine F
COMMONWEALTH EDISON CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
NUDOCS 8110070337
Download: ML20011A125 (1)


Text

Commonwealth Edison C

one First National Plaza, Chicago, Illinois C4 Address Reply to: Post Office Box 767 Chicago, Illinois 60690

/(o I : W

  • iq October 1, 1981

}

OCT g 198k a ;

c-u,s s

Mr. Harold R. Denton, Director 3

ads

  • Office of Nuclear Reactor Regulation U.S.

Nuclear Regulatory Commission N

$\\ <

Washington, DC 20555 M'

Subject:

Zion Station Unit 1 Temporary Change to Facility Operating License No. OPR-39 NRC Docket No. 50-295 Reference (a): F.

G.

Lentine letter to H.

R.

Denton, dated September 25, 1981

Dear Mr. Denton:

Reference (a) requested on an emergency basis a change to the Zion Unit 1 Technical Specifications to permit removal from service and repair of the Unit 2 system auxiliary tranformer (TR 242).

This letter is submitted to request an extention of the provisions of that amendment beyond the seven day period originally requested to October 14, 1981.

This extention is necessary to complete the work required on the transformer.

While no major internal damage was discovered, a number of minor repairs are required to internal transformer connections.

In addition, it is desirable to perform several preventive maintenance items at this time, including a thorough internal cleaning.

Finally, an extensive testing program is planned for the transformer following reassembly, in order to ensure that all problems have been corrected and reassembly has been properly accomplished.

Bocause of the importance of this transformer to plant safety and reliability, sufficient time should be made available to perform the work thoroughly and carefully.

Please address any questions you may have concerning this matter to this of fice.

Very truly yours, Yk F. G. Lentine Nuclear Licensing Administrator cc:

Zion Resident Inspector 2624N I

A 8110070337 811oo3 I

DR ADOCK 05000295 I@