Advises That Followup Rept Responding to NRC,801222 Generic Ltr Re Control of Heavy Loads Will Be Delayed Until 811201
ML20010J167
Person / Time
Site: Wolf Creek, Callaway  Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 09/17/1981
From: Petrick N
STANDARDIZED NUCLEAR UNIT POWER PLANT SYSTEM
To: Harold Denton
Office of Nuclear Reactor Regulation
References
TASK-A-36, TASK-OR SLNRC-81-106, NUDOCS 8109290657
Download: ML20010J167 (1)


Text

, _ _ _ _.. _.. _ _ _ _ _ _ _ _ _

SNUPPS Standardized Nuclear Unit Power Plant System 5 Choke Cherry Road Nicholas A. Petrick Rockville, Maryland 20850 Executiv6 Director (301) 8694010 September 17, 1981 SLNRC 81-106 FILE:

0278 SUBJ:

Control of Heavy Loads pg

$\\ '

k Y "h 7,g',$ ("h Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation s' 8g "

',e

c]j C. S. Nuclear Regulatory Commission d

o.,, ; g (9g7, Washington, D. C.

20555 g

Docket Nos.

STN 50-482, STN 50-483 and STN 50-486 k

References:

1.

NRC Generic Letter, dated December 22,198'O

/ /ri M\\'

Same subject 2.

SLNRC 81-48, dated June 22, 1981: Same subject

Dear Mr. Denton:

Reference 1 requested two submittals concerning the control of heavy loads. Reference 2 provided the first of these reports for the SNUPPS plants. The follrwup report, which was expected to be submitted this month, will be delayed. The SNUPPS Utilities will submit the second report about December 1,1981.

Very truly yours, C&<v

~ Nicholas A. Petrick RLS/mtk cc: