Comments on NRC 791009 Safety Assessment for SEP Topic IV-1.A Re Facility Operation W/Less than All Loops in Svc. Contingencies Noted in Subj Rept Incorporated Into Appropriate Procedures
ML20010F569
Person / Time
Site: Big Rock Point File:Consumers Energy icon.png
Issue date: 09/03/1981
From: Bordine T
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: Crutchfield D
Office of Nuclear Reactor Regulation
References
TASK-04-01.A, TASK-4-1.A, TASK-RR NUDOCS 8109100360
Download: ML20010F569 (2)


Text

e Consumers Power Company Genere4 offices: 212 West Michigen Avenue, Jackson, MI 492ot * (617) 788-o650 September 3, 1981 W

t tR[x(([b F2;'

Director, Nuclear Reactor Regulation

,SEP 09 g Att Mr Dennis M Crutchfield, Chief k m.a.DD h]

Operating Reactors Branch No 5 1

/

(jh.

US Nuclear Regulatory Commission Washington, DC 20555 ggf

'v @g's DOCKET 50-155 - LICENSE DPR BIG ROCK POINT PLANT - SEP TOPIC IV-1.A - OPERATION WITH LESS THAN ALL LOOPS IN SERVICE NRC letter dated October 9, 1979 completed the safety assessment of SEP Topic IV-1.A for single loop operation. The assessment noted that a::ceptability of the topic is contingent upon the licensee's agreement to:

1.

Include in a procedure for N-1 loop operation a statement that the bypass and isolation valves in the inactive loop be closed during N-1 operation.

2.

Physically lock-out power to the inactive pump.

3.

Incorporate the MAPLHGR limits for N-1 loop operation in the Technical Specifications.

Consumers Power Company has incorporated these coatingencies in appropriate plant procedures.

Items (1) and (2) are addressed in the Big Rock Point Operating Procedures Manual - System Operative Procedures (SOP 29). The procedure specifies in part the following:

Two reactor recirculating loops shall be in service unless otherwise specified by the plant superintendent or reactor engineer, or an emergency procedure. Extended power operation (greater than one hour) with only one reactor recirculating loop in operation, requires that the suction, discharge and discharge bypass valves of the inactive loop be closed and the controls caution tagged, that the inactive pump oe opened and caution l

tagged, and ---.

l l

Consumers Power Company letter of February 25, 1980 included the proposed technical specification for Item (3) and NRC letter dated June 9, 1981 provided Amendment No 44 to Facility Operating License j

j No DPR-6 lelaying tue N-1 loop operation in the Technical j st')

l Specifications upon completion of the NRC staff evaluation.

It is fy b i

oc0981-0002bl42 i

l 8109100360 810903 PDR ADOCK 05000155 l

P PDR

p.'

t Dennis M Crutchfield, Chief 2

Big Rock Point Plant September 3, 1981 I

requested ths: 1 mediate attention be placed upon NRC staff concerns of single loop operation so that the Technical Specification chan<,es can be fully implemented.

f -

7, 7

l/,,sJ. _. > v '/

s

~<

v Thomas C Bordine Staff Licensing Engineer' CC JGKeppler, USNRC NRC Resident Inspector i