Confirms Aug 1985 Const Completion.Schedule May Be Advanced as Much as 8 Months.Confirmation Will Be Submitted Quarterly
ML20010E461
Person / Time
Site: Washington Public Power Supply System
Issue date: 08/27/1981
From: Bouchey G
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
GO1-81-281, NUDOCS 8109040149
Download: ML20010E461 (1)


Text

Washington Public Power Supply System P.O. Box 968 3000 GeorgeWashingtonWay Richland, Washington 99352 (509)372-5000 August 27, 1981 m

G01-81-281 go.

Docket Nos. 50-460 & 50-513 8

Office of Nuclear Reactor Regulation SEP 0 3 ;ggg u.a, %

y U.S. Nuclear Regulatory Commission Washington, D.C. 20555 V

%

  • a=

~

Attn: Mr. Darrell G. Eisenhut, Director r, /

Division of Licensing

Dear Mr. Eisenhut:

Subject:

' Supply System Nuclear Projects Nos. 1 & 4 WNP-1 Construction Completion Schedule

Reference:

Ltr, Darrell G. Eisenhut, NRC to R.L. Ferguson, Supply System, "WNP-1 Construction Completion Schedule", dated August 3, 1981.

The reference requested that we confim, or change the indicated construction completion date of December,1984 for WNP-1.

The Project's projected construction completion date for WNP-1 is August, 1985. However, a number of actions are being taken to advance that date by as much as eight months. Therefore, we request that NRC allocation of resources consider this potential schedule edi=ce.

As requested, we will provide the Staff quarterly confirmation of this schedule.

Very truly yours, G. D. Bouchey N ector Nuclear Safety GDB:pp cc: NS Reynolds, Debevoise & Liberman FDCC - 899 V Mani, UE&C - 897 HC Grau, UE&C-PA - 08US b