Order Granting Applicant Request That Facility CPs Be Withdrawn.Lists Licensee Actions Required to Redress Site
ML20010E073
Person / Time
Site: Davis Besse  
Issue date: 08/28/1981
From: Cotter P
Atomic Safety and Licensing Board Panel
To:
Office of Nuclear Reactor Regulation, TOLEDO EDISON CO.
References
ISSUANCES-CP, NUDOCS 8109030033
Download: ML20010E073 (4)


Text

. _ _ _ _ _

o.

en N

</ \\

UNITED STATES OF AMERICA LY

'0t.\\

NUCLEAR REGULATORY COMMISSION i ]'

'p g

Is fl

'O 3 ATOMIC SAFETY AND LICENSING BOARD S.[ f( y

%1

\\A yL i

j'.

Before Administrative Judges:

\\{' '

[,(w I

b g' #[ '

02 B. Paul Cotter, Jr., Chairman r

'A

,,.qgS$

Dr. Cadet H. Hand, Jr.

C) f Dr. David L. Hetrick SE/Ws S[p nN 4

l l08[

y \\

)

In the Matter of:

)

)

THE TOLED0 EDIS0N COMPANY, Et Al.

)

Docket Nos. 50-500-CP

)

50-501-CP (Davis-Besse Nuclear Power Station,

)

Units 2 rnd 3: Termination of

)

Proceedings)

ORDER Upon consideration of the response by both NRC Staff and counsel for Toledo Edison Company, et al. ("the Applicant") to this Board's order of December 31, 1980 in the captioned proceeding and the entire record in this matter, and pursuant to the authority contained in 10 C.F.R. Part 2, it is this 28th day of August, 1981 ORDERED 1.

That the request of the Applicant that its application for construction permits for the Davis-Besse Nuclear Power Station, Units 2 and 3, be withdrawn is granted.

The applicant shall take the following 810903o033 810828 8

PDR ADOCK 05000500 6A[

PDR

- actions to redress the site, which are prescribed as conditions pursuant to 10 C.F.R. %2.107(a) of the withdrawal of the applications for construction permits:

The temporary construction office facilities (separate and a.

connected trailers) shall be removed from the site. The tempor ary above ground electric service shall also be removed.

(The area between N9,500 and N10,000 around E9,500 on drawing 6670TP-P-C002 of the attachment to Applicant's letter of November 26,1980);

b.

The existing construction material stockpiled throughout the material storage area and the construction equipment shall be removed from the site when dispositioned; The west side of the wave protection dike shall be seeded; c.

d.

Throughout the site, wherever earth r.1ounds or trenches occur, they shall be contoured as necessary and covered with topsoil to enhance the wildlife habitat; The eight ponds created by construction excavaticn shall e.

remain as waterfowl and wildlife habitat. The banks of the ponds shall he graded as required;

. f.

The existing topsoil stockpile shall be utilized throughout the site in strategic areas as ground cover for vegetation restoration purposes; g.

Landscaping and vegetation restoration shall enhance the site's natural environment.

In developing the details of this effort, compatibility with wildlife areas adjacent to the site shall be considered by the Applicant.

h.

The definitive reconditioning plan shall be based on considerations such that the site shall be improved to a condition that shall encourage wildlife to use the area; i.

Approximately 100 grout pipes remaining from the remedial grouting shall be cut off and plugged prior to backfilling the excavation; l

j. The groundwater treatment plant shall be mothballed in place.

l i

(

2.

That the Licensing Board's partial initial decisions, LBP-75-75, l

l 2 N.R.C. 993 (1975) and LBP-78-29, 8 N.R.C. 284 (1978), authorizing issu-1 l

ance of two limited work authorizations for the Davis-Besse Nuclear Power Station, Units 2 and 3, are vacated.

. 3.

That the Director of Nuclear Reactor Regulation is authorized to:

a.

Revoke the outstanding limited work authorizations issued pursuant to 10 C.F.R. %%50.10(e)(1) and 50.10(e)(3);

b.

Cause to be published in the Federal Register in accordance with 10 C.F.R. %2.107(c) a notice of the withdrawal of the applications for construction permits for Davis-Besse Nuclear Power Station, Units 2 and 3.

4.

That the Applicant's Motion for Termination of Proceedings is granted and the construction permit proceedings for Davis-Besse Nuclear Power Station, Units 2 and 3, are terminated.

FOR THE ATOMIC SAFETY AND LICENSING BOARD b*

inl (L

'B.

Pa'ul Cotter, Jr.,

h airman ADMINISTRATIVE JUDG