Updated Interim Deficiency Rept Re Hfa Relay Bobbin Assembly Cracking,Initially Reported on 810325.Availability of Replacement Matls Primary Source of Delay in Initiating Work Required.Work Will Begin 810803
ML20010A268
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 07/31/1981
From: Delgeorge L
COMMONWEALTH EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, NUDOCS 8108110251
Download: ML20010A268 (2)


Text

g

[' :: N Commonwealth Edison

) One First N tiorni PLua, Chicago, Illinois

( C j Address Reply to: Post Offica Box 767 Chicago, Illinois 60690 j

July 31, 1981

<ipYI])

k( p

(

e J

Mr. James G. Keppler, Director g'

AUG 101981 >

g{l Directorate of Inspection and Enforcement - Region III UA ggmat.

U.S. Nuclear Regulatory Commission 9,

799 Roosevelt Road J

/y7

-Qi '

\\

Glen Ellyn, IL 60137

Subject:

LaSalle County Station Units 1 and 2 HFA Relay Bobbin Assembly Cracking Inte.im Report Under la CFR 50.55(e)

No. 50-373/81-02 and 50-374/81-02 NRC Docket Nos.-50-373/374 Reference (1):

L. O. DelGeorge letter to J. G. Keppler dated March 25, 1981

Dear Mr. Keppler:

The purpose of this letter is to update information provided in Reference (1) relative to the replacement program for HFA Relay Bobbin Assemblies.

As has been indicated in our previous correspondence, this program will conform to the guidance provided in SE Service Information Letter (SIL) No. 44, Supplement 2, dated February 13, 1981.

Availability of replacement materials has been the primary source of delay in initiating the work required.

In order to e.ompress the time to completion both the inspection and replacement if required of Lexan. Bobbins will be made at a single equipment

(

outage to reduce the impact on the plant testing program.

Sufficient materials are now available to allow for the initiation of work on the effected nuclear steam Jupply system relays.

That work will begin on August 3, 1981 and is expected to be completed within two weeks.

The work in the balance of plant relays will also begin in August, 1981 and is expected to be completed prior to fuel loading.

This schedular information will be updated on September 15, 1981 at which time we expect to be able to issue a final report on this subject.

76N s

/ /

S!!!8168M'o!!8yh Aus s isat s

IWe-

' If you have any further questions in this regard, please direct them to this office.

Very truly your L. O. DelGeorge / O Director of Nuclear Licensing cc:

Director of Inspection and Enforcement, Washington, DC NRC Resident Inspecton - LSCS 2361N l