Order Summarizing Decisions Made During 810803 Conference Call.Notices of Depositions Must Be Filed by 810810.New Discovery Re 810717 Environ Issuances Deadline Is 810811 & Intervenor Deadline to File Revised Contentions Is 810828
ML20009H208
Person / Time
Site: Bailly
Issue date: 08/04/1981
From: Grossman H
Atomic Safety and Licensing Board Panel
To:
NRC OFFICE OF THE EXECUTIVE LEGAL DIRECTOR (OELD)
References
NUDOCS 8108070027
Download: ML20009H208 (2)


Text

-

E

=

g 9

~:a q

UNITED STATES OF AMERICA a

NUCLEAR REGULATORY COMt11SSION 7

+

AUG '51981 > _id ATOMIC SAFETY AND LICENSING BOARD p := d e e S a c'7 c:Src.;aSmia C

8 k

=h p' Before Administrative Judges:

Ilerbert Grossman, Chairman Dr. Robert L. Holton Dr. J. Venn Leeds SERVED pyg 5 gg 7

)

In the Matter of:

Docket No. 50-367 NORTHERN INDIANA PUBLIC

-)

(Construction Permit SERVICE COMPANY

)

Extension) po a

.gs N

1 fx' A

(Bailly Generating Station, Nuclear-1)

August 4, 1981 g

)

d AUG 0 61981M9 E

(Summarizing

.t ons Taken at

" DE h[^

Conference Call of August 3,1981) b p

'*G At the Board's request, a conference call was held at 11:00 a.m eastern time on August 3,1981 to discuss discovery matters. All Board members were present and all parties except the Grabowskis were present or represented by counsel. The Board set the following schedule and to'ok the following actions:

1.

Set August 10, 1981 as the date by which all notices of deposition must be filed with regard to admitted contentions, except as to new matters raised in the Staff's environmental issuances of July 17, 1981; 2.

Set August 11, 1981 as the deadline.fpr all new discovery arising from the Staff's environmental issuances of July 17, 1981 within the scope of admitted contentions; 3.

Set August 28, 1981, as the deadline for intervenors to file l

revised contentions or rest upon their original contentions not yet acted on by the Board with regard to environmental issues, together with D5o3 sik

~~

i statements containing whatever support they have for the Board's admitting those contentions.

4.

Reaffirmed August 28, 1981, as the date by which discovery responses are to be " updated," which the Board means as requiring a review of all previous responses and a re-answering, providing any information which has developed or been discovered by the date of updating.

5.

Required the filing of notices of deposition containing the information required by 10 CFR 52.740a(a) and a showing of the general relevance of the testimony sought as a prere"quisite to the Board's granting applications for subpoenas.

6.

Set September 30, 1981, as the deadline for the taking of the depositions noticed within the deadlines memorialized in paragraphs 1 and 2, above.

7.

Ordered the Staff to answer the interrogatories propounded by intervenors to which Staff has interposed no objection.

8.

Indicated that the parties could continue specific discovery beyond an estatlished deadline by leave of the Board upon motion showing good cause for the Board's waiving the deadline with regard to the specific discovery sought. Also indicated that the Board would permit discovery to be scheduled beyond a deadline I

if a delay is occasioned by the Board's not acting expeditiously on contested l

discovery.

9.

Indicated that none of the actions taken relate to the short pilings issue not yet officially before the Board pending action by the Commission.

By Order of the Board.

FOR THE ATOMIC SAFETY AND LICENSING BOARD

/

MM-Herbert Grossman, Chairman ADMINISTRATIVE JUDGE Dated at Bethesda, Maryland Rhis 4th day / of August 1981. _