ML20009G852

From kanterella
Jump to navigation Jump to search
Forwards LER 81-009/01T-0
Date released: 01/23/2020 Download: ML20009G852


LER 81-009/01T-0:on 810714,per IE Bulletin 80-11 Analyses, Contractor Reported That Four Control Room & Two Battery Room Walls Did Not Meet Revised Criteria for Seismic Event. Caused by Reanalysis Per Revisions.Supports Installed
ML20009G853
Person / Time
Site: Point Beach NextEra Energy icon.png
Issue date: 07/28/1981
From: Fay C
WISCONSIN ELECTRIC POWER CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
Download: ML20009G853 (3)
Forwards LER 81-009/01T-0
ML20009G851
Person / Time
Site: Point Beach NextEra Energy icon.png
Issue date: 07/28/1981
From: Fay C
WISCONSIN ELECTRIC POWER CO.
To: KEPPLER J G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
Download: ML20009G851 (1)