Interim Deficiency Rept Re Safe Shutdown Boration Capability.Fsar Amend Will Be Issued in Oct 1981 Covering Details of Emergency Boration Sys.Interim or Final Rept Will Be Submitted by 811231
ML20009D746
Person / Time
Site: Midland
Issue date: 07/17/1981
From: Jackie Cook
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, 12050, 79-11-#6, NUDOCS 8107240315
Download: ML20009D746 (2)


Text

/)m6l57)55Td

?

e.

CODSumBIS Power James W Cook COMPBRY Vice President - Projects, Engineering and Construction General offices: 1945 West Parnali Road, Jackson, MI 49201 * (517) 788-0453 79-11 kb July 17,1981 h I 'I'k[ljp /

Mr J G Keppler, Regional Director Office of Inspection

'e Enforcement US Nuclear Regulatory Commission Region III 8

[;

\\[

799 Roosevelt Road y

JUL 2 31981 * *~ g

~

Glen Ellyn, IL 60137 y,g,e m s uS**

  • 2 MIDLAND PROJECT -

{8 DOCKET NOS 50-329 aND 50-330 0) d SAFE SHUTDOWN BORATION CAPABILITY s.'

FILE:

0.h.9.36 SERIAL: 12050 Ih

References:

CPCo letters to J G Keppler; Same

Subject:

1.

Serial Hove-283-79 dated October 21, 1979 2.

Serial Hove-308-79; dated December 6,1979 3

Serial Hove-78-80; dated April 11, 1980 h.

Serial 8807; dated July 31, 1980 5

Serial 9786; dated October 31, 1980 This letter, as were the referenced letters, is an interim 50.55(e) report regarding safe shutdown boration capability assuming a most restrictive core condition and the control rod of highest worth stuck out of the core.

1 Consumers, Bechtel and B&W are discussing the detailed design of the system including the procedures required for system operability. Any requirements for system operability will be factored into the detailed design.

The equipment required for this modification is on order and in various l

stagese of fabrication.

It is expected that shipment of the major components vill occur during the latter part of 1981 and construction will extend through the spring of 1982.

TEN It is expected that an FSAR Amendment vill be issued in October of 1981 3

/[j covering the details of the Emergency Boration System.

Another report, either interim or final, will be transmitted on or bercre December 31, 1981.

m

d. 6vl s

DTP/1r 8107240315 810717 gQ N l

PDR ADOCK 05000329 g

l S

PDR i

i

0 Serial 12050 2

79-11 #6 o

CC: Director, Office of Inspection & Enforcement Att Mr Victor Stello, USNRC (15)

Director, Office of Management Information & Program Control, USNRC (1)

RJCook, USNRC Resident Inspector Midland Nuclear Plant (1)

CBechhoefer, ASLB Panel RSDecker, ASLB Panel FPCowan, ASLB Panel AS&L Appeal Panel MMCherry, Esq MSinclair BStamiris CRStephens, USNRC WDPaton, Esq, USNRC FJKelly, Esq, Attorney General SHFreeman, Esq, Asst Att General WHMarshall GJMerritt, Esq, ' INK &J

,