ML20009A990

From kanterella
Jump to navigation Jump to search
Forwards Proposed Revised Response to FSAR Question 211.94(5) Re Demonstration of Capability to Initiate Shutdown Cooling Completely from Control Room.Power Lockout Provision on Safety Injection Tank Valves Maintained
ML20009A990
Person / Time
Site: Waterford 
Issue date: 07/08/1981
From: Maurin L
LOUISIANA POWER & LIGHT CO.
To: Tedesco R
Office of Nuclear Reactor Regulation
References
WP3P81-1639, NUDOCS 8107140595
Download: ML20009A990 (5)


Text

.

LOUISIANA 242 mAnONOe S-POWER & L1GHT P O 00X 6008

  • NEW ORLEANS. LOUISIANA 70174 * (504) 366 2345 EuEsEsN July 8, 1981 W3P81-1639 Q-3-A29 Mr. R. L. Tedesco N-A14 M.02 Assistant Director Option 270 Division of Licensing 0)

Office of Nuclear Reactor Regulation e'

U. S. Nuclear Regulatory Commission

,['rk[J Washington, D. C.

20555 g

SUBJECT:

Waterford SES Unit No. 3 2

JUL 131981 * -

Docket No. 50-382 5;

gangn Reactor Systems Branch (RSB) 50 #

p' SER Open Item No. 61 g,&

/

REFERENCE:

L. V. Maurin to R. L. Tedesco letter dated June 12, 1981 4 /Io r

(W3P81-1467)

ATTACHMENT: Revised Response to FSAR Question 211.94(5)

Dear Mr. Tedesco:

In FSAR Question 211.94 part (5), the RSE has re. quired us to demonstrate our capability of initiating shutdown cooling completely from the control room.

Our initial response submitted u Amendment 17 (4/81), documented our commit-ment to provide motor operators on various valves to achieve this end.

However, we also indicated that the operator would still normall be required to first locally unlock and close the breakers (located at El +21 below the control room at El +46) for the Safety Injection Tank (SIT) discharge valves in order to be able to close these valves from the control room prior to shutdown cooling initiation.

During subsequent discussions with the RSB reviewers, we were informed that the NRC staff felt that this arrangement did not comply with RSB BTF 5-1.

In the referenced letter we expanded upon our response to indicate the SIT discharge valve MCC area and access routes were continuously habitable post-LOCA, and that the power lock-out arrangement on the SIT discharge valves stemmed from ICSB 4 and 18 criteria.

The referenced letter generated another round of discussions among RSB, ICSB, LPL and Ebasco. As a result we hereby submit the attached proposed revision to FSAR Question 211.94(5).

In this response, we commit to maintaining the power lock-out provision on the SIT discharge valves but removing it from the SIT vent valves. We demonstrate that although the norual procedure would be to close the SIT dischs.tge valves, this proposed arrangement would allow the plant to be brought safely to and maintained in a cold shutdown condition, if for some reason the operator were unable to reach the SIT discharge valve breakers.

8107140595 810708 f [(

PDR ADOCK 05000382 r

A pop r $1

}

1

'W3P81-1639 Mr. R. L. Tedesco Page 2

' July 8, 1981 4

We plan to formally incorporate the attached revised response in FSAR Amendment j

20 on 7/17/81.

Very truly yours, j/ N L. V. Maurin Assistant Vice President Nuclear Operations LVM/RWP/sm Attachment cc:

E. L. Blake, W. M. Stevenson i

4

(

i '

I I

. ~...

=

Question No. 211.94 (5)

Discussion with the applicant has indicated that a number of valves in the 4

shutdown cooling system are being modified to include motor operators. Provide details of these modifications. Demonstrate that with these modifications, all actions necessary to initiate shutdown cooling can be taken from the control room, utilizing only safety grade systems, and assuming only onsite power is.

available. Also, indicate whether there are any systems or components needed-for i 2tdown cooling which are de-energized or have power locked out during plant operation.

If so, indicate what actions have to be taken to restore operability to'the components or systems.

Response

.In order to comply, we are equipping the following Shutdown Cooling System (SDCS) valves with motor operators. operable from the control room. These valves are:

i.

VALVE NO.

FUNCTION SI-452 SDCS Heat Exchanger Isolation SI-453 SDCS Heat Exchanger Isolation SI-400 Warm-up Bypass SI-450 Warm-up Bypass SI-456 SDCS Heat' Exchanger Return Line Isolation L

SI-457 SDCS Heat Exchanger Return Line Isolation SI-432 SDCS Cooling Isolation i

SI-444 SDCS Cooling Isolation T

Attached Table'211.94-1 shows all valves in the ECCS'with lockout provisions and operated from the control room. The list is divided into two categories:

a) Valves that have power locked-out from the motor control center during normal operation. From this category, only Safety Injection Tank discharge valves are required for normal shutdown.

i The SIT discharge valves are locked open during normal operation.

This is accomplished by locking open the breakers in the Motor l

Control Center after the motor operated valves have been placed L

in their open position. These breakers are locked open in order

[-

to ensure that.no single failure'such as an electrical fault will

(

cause-these valves to be closed when safety injection is required.

Placing a padlock on~the breaker also diminishes the' probability of the valves being closed due to operator or maintenance error.

Locking open this breaker is in fact required by ICSB BTP's 4 and 18 in order to meet single failure criteria.

I-

~ ~ _,,

J During cooldown, an interlock will prevent these valves from being closed while primary pressure is above 400 psig. At 650 psig primary pressure, the operator vents the SIT's to 377 psig.

At 400 psig, the operator normally closes the SIT discharge valves. However, an SIAS will override and reopen the valves.

This ensures SIT availability during shutdown cooling without the danger of overpressurizing the SDCS.

t In order-to close the valves, an operator must go to El +21 (two flights of stairs directly below the control room at El +46) remove the padlock and locally close the breaker at the MCC.

The valves in the control room may then be closed from a key-lock control switch. Although an operator must move a short distance from the control room, the areas he must pass through i

have been documented in the shielding study (FSAR Appendix 12.3A) as being continuously habitable post-LOCA.

As discussed above, there is no reason why, considering.the proximity and habitability of the MCC area and its accersibility from the control room that the operator should be unablo to close these valves. However,uif we assume that for some non-mechanistic reason, the operator was unable to-close these valves, the plant could still be brought to and maintained in a cold shutdown condition as demonstrated below.

4 THE RCS pressure does not have to be reduced below 377 psig in order to cool down the plant to cold shutdoun conditions (MODE 5).

Procedurally, the SIT discharge valves are normally closed at this time to avoid a reduction in tank inventory and the consequent need for adding water prior to return.ng the plant to operation, but there is no safety requirement for closing these valves. By the same token, the N2 cover gas pressure in the. tanks can be reduced below 377 psig should it be desired.

I The overriding concern which dictates that power be removed from the SIT discharge valves during' operation is the potential for an undefined or non-mechanistic fault which might deve.op a false "CLOSE" signal to the valve operator at the time of a large break LOCA. Such an event would invalidate the safety analysis. There is no equivalent basis for removing the power from the nitrogen vent valves on the SIT's during operation.

In that case, the generation of a non-mechanistic fault which caused a vent valve to open at the-time of-a large break LOCA would have no significant g

impact on system performance or on the safety analyses. For this reason,.and in order to meet the Reactor Systems Branch and ICSB criteria, the SIT ven; valves (2SI-E632, 633, 634, 635, 636, 637,

- 638 and 639) will not have power locked out at the MCC. They will, therefore, be operable from the key-lock control room switch.

In summary, therefore, by maintaining the MCC power lock-out provision on the SIT discharge valves but removing this provision from the SIT vent valves, the plant can be brought to a cold shutdown condition from the control room and still meet ESB 3-1, ICSB ETP4 and 18 criteria.

[

. TABLE 211.94-1 LIST OF LOCKED-0UT REMOTELY OPERATED ECCS VALVES 1.

Locked-out in the control room and in the motor control center.

TAG NO.

DESCRIPTION REQ'D FOR NORMAL SHUTDOWN 2SI-V1557 Hot leg injection No

-V1558 Hot leg injection No ISI-V1505 SI Tank Discharge Yes

-V1506 SI Tank Discharge Yes

-V1507 SI Tank Discharge Yes

-V1508 SI Tank Discharge Yes 2.

Locked-os*. only in the control room.

1SI-V1501B Shutdown Isolation Yes

-V1502B Shutdown Isolation Yes

-V1503A Shutdown Isolation Yes

-V1504A Shutdown. Isolation Yes 2SI-FM317A Shutdown Temp. Control Yes

-FM318A Shutdown Temp. Control Yes

-FM348B Shutdown Temp. Control Yes

-FM349B~

Shutdown Temp. Control Yes

-V326B Shutdown' Containment Isolation Yes

-V327A Shutdown Containment Isolation Yes

-V811B Cold leg injection ho

-V1534 Cold leg injection No

-V1556 Hot leg injection No

-V1559 Hot leg injection No

-E632 SI Tank Vent No

-E633 SI Tank Vent No

-E634 SI Tank Vent No

-E635 SI Tank Vent No

-E636 SI Tank Vent No

-E637 SI Tank Vent No

-E638 SI Tank Vent No

-E639 SI Tank Vent No i

l l

I L

I l

.