Responds to NRC Requesting Review of NRC Identified Deficiencies Re Environ Qualification of Electrical Equipment.Conclusions Reached in Util Remain Valid.Continued Safe Operation of Facility Assured
ML20008E682
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 03/02/1981
From: Linder F
DAIRYLAND POWER COOPERATIVE
To: Lainas G
Office of Nuclear Reactor Regulation
References
LAC-7393, NUDOCS 8103090432
Download: ML20008E682 (2)


Text

k

,a D DA/RYLAND COOPERAT/VE

  • Po BOX 817
  • 2615 EAST AV south. LA CROSSE. W1SCO*JSIN 54601 (6Ces 188 4000 March 2, 1981 In reply, please refer to LAC-7393 DOCKET NO. 50-409 U.

S. Nuclear Regulatory Commission ATTN:

Mr. Gus C.

Lainas, Assistant Director Aq l' N g

for Safety Assessmert

/

Division of Licensing Washington, D.

C.

20555

'r

~

o k o ~$o l

SUBJECT:

DAIRYLAND POWER COOPERATIVE 1-

'O O

LA CROSSE BOILING WATER REACTOR (LACBWR Q

/

7 PROVISIONAL OPERATING LICENSE NO. DPR-4

/

s ENVIRONMENTAL OUALIFICATION OF ELECTRICA

\\g EOUIPMENT 4

to 1

e

References:

(1)

NRC Letter, Lainas to Linder, dated February 17, 1981.

(2)

DPC Letter, Linder to Eisenhut, LAC-7196, dated October 31, 1980.

r Gentlemen:

Your letter (Reference 1) transmitted the preliminary results of your review of environmental qualifications of safety related electrical equipment at the La Crosse Boiling Water Reactor.

We were requested to review NRC identified deficiencies and their ramifications and to provide you our overall finding regarding continued safe operation of l

LACBWR.

Our letter (Reference 2) responded to your order dated September 18, 1980.

We find that the conclusions reached in this response remain valid.

Many of the corrective actions identified in Reference 2 have been initiated.

Therefore having considered the NRC staff's prelimin-ary list of deficiencies which generally constitute the need for infor-mation to be developed and submitted, we conclude that continued safe operation of the LACBWR facility is assured.

Very truly yours, DAIRYLAND POWER COOPERATIVE N

h~

y Frank Linder, General Manager FL:RES:af I

cc:

J.

G.

Keppler, Reg. Dir., NPC-DRO III NRC Resident Inspectors 8103090432 --

,b i

l Mr. Gus C. Lainas, Assistant Director LAC-7393 l

for Safety Assessment March 2, 1981 Division of Licensing

{

. STATE.OF WISCONSIN )

)

COUNTY OF LA CROSSE)

Personally came before me this eh'?'"

day of March, 1981, the above named Frank Linder, to me known to be the person who executed the foregoing instrument and acknowledged the same.

)Yl NotaryDblic, La Crosse County, Wisconsin.

My Commission Expires February 26,- 1984.

2-I