Order Requiring Mod of License SNM-23.Licensee Must Develop & Submit Radiological Contingency Plan & Application for License Amend to Incorporate Plan as Condition of License within 180 Days
ML20008E496
Person / Time
Site: 07000033
Issue date: 02/11/1981
From: Cunningham R
NRC OFFICE OF NUCLEAR MATERIAL SAFETY & SAFEGUARDS (NMSS)
To:
TEXAS INSTRUMENTS, INC.
Shared Package
ML20008E491 List:
References
NUDOCS 8103090103
Download: ML20008E496 (6)


Text

.

.O '

UNITED 5%TES OF AMERICA NUCLEAR R GULATORY COMMISSION In the Matter of

)

0ccket No. 70-33

)

Materials License Texas Instruments, Inc.

)

No. SNM-23 Metal Systems Division

)

34 Forest Street

)

Attleboro, Massachusetts 02703 ORDER TO MODIFY LICENSE I

i i'

Texas Instruments, Inc. of Attleboro, Massachusetts ("the licensee") is the holder of Materials License No. SNM-23 issued by the Nuclear Regulatory Commission ("the Commission").

The license authorizes the possession and use 235 of up to 350 kg of U (10% - 93.5% enrichment) and up to 50 kg source material.

The 1icensee is authorized to fabricate test reactor f Jel elements from U 0 38 powder.

The : urrent license was renewed on March 6,1974.

The expiration date was extended to June 30, 1982 due to the licensee's intent to terminate nuclear fuel production operations.

II Before issuance of a license to operate, staff review of th'e application

- determined that the licensee can operate the facility in a safe manner.

Nonetheless, based on the lessons learned from the accident at Three Mile Island and new perspectives on emergency preparedness and planning, the Commission has reevaluated the emergency preparedness requirements for its fuel cycle and materials licensees.

The Commission has decided that significant improvements need to be made promptly to ensure that adequate onsite emergency response

%ve h

/'

. actions will be taken by licensees with major cperations in cases where, even though unlikely, potentially serious radiation accidents could occur.

The operations licensed to be carried out pursuant to Materials License No. SNM-23 appear to fall in this category and require the development of a more comprehensive onsite radiological contingency plan than previously submitted to the Commission for review.

Specifically, considerations are needed to ensure (1) that the plant contains adequate engineered safety features and is otherwise designed to limit releases of radioactive materials and radiation exposures in the j

event of an accident, (2) that a capability exists for measuring and assessing the significance of accidental releases of radioactive materials, (3) that appropriate emergency equipment and planning are provided onsite to protect workers against radiation hazards that might be encountered following an accident, (a) that notifications are made promptly to federal, state, and local government agencies, and (5) that necessary recovery actions are taken in a timely fashion to return the plant to a safe condition following an accident.

The information to be developed and documented is described in the enclosed

" Standard Format and Content for Radiological Contingency 'lans for Fuel Cycle and Materials Facilities" (Enclosure 1).

In summary, the information to be

~ ~

submitted to NRC for review includes a (1) description of plant systems important to safety; (2) characterization of classes of credible emergencies that might occur; (3) description of radiological contingency measures fcr each class of emergency; (4) designation of authorities and responsibilities of key individuals and groups employed by the licensee; and (5) a description of equipment and facilities designated for use during radiation emergencies.

The plan is to be

~

,e a

e e$w a m

. Op e ese

%a.-.

p

=

em v

m w-ww

. directed toward mitigating the consequences of radiological emergencies and r

providing reasonable assurance that appropriate measures will be taken during an emergency to assure protection of the public and minimize adverse environ-mental impacts.

In preparing the plan, consideration should be given to a set of credible accidents ranging from almost everyday occurrences of small conse-quence through highly improbable, but not impossible, accidents such as those resulting from severe natural phenomena, human error, and multiple equipment failures, and sabotage.

6 p-III In addition to onsite radiological contingency planning, as discussed in Section II above, offsite emergency response planning is also highly important.

Offsite planning requirements for fuel cycle and materials facilities are being developed separately and will be considered in a proposed rulemaking to be published in the coming months. Within the framework of that rulemaking, NRC will carry out extensive coordination with state governments and the Federal Emergency Management Agency (FEMA) concerning applicable requirements.

IV The Commission believes that it is prudent and necessary to require the licensee to develop and submit within 180 days of the effective date of this Order, or before, an onsite radiological contingency plan, as discussed in

~

Section II above, applicable to operations licensed pursuant to Materials License No. SNM-23.

Such a plan can be developed and effectively implemented apart from offsite emergency response planning, which necessarily involves state and local government emergency planning actions.

The onsite radiological

_____u e g

.=e.

awww e

en-hhe e-+me s e qu4e*

  • e gee-mwe

~

. contingency plan is a necessary extension of protective actions taken by the licensee during normal operations.

Such planning is essential to ensure that proper plans are made by the licensee to protect the public from accidents i

that could result from the licensed operations.

A lesson learned from the i

Three Mile Island accident is that accidents thought to be highly improbable can and will occur, and that proper emergency preparedness is required to mitigate radiological consequences.

II The reporting and record keeping part of this onsite radiological contin-gency plan is subject to clearance by the General Accounting Office.

GA0 review and clearance will not stay the effective date of this Order as regards the requirement that the licensee develop the plan.

Unless advised to the contrary, GA0 clearance will be effective within 45 days from the date of this Order.

V Accordingly, pursuant to sections 161b and 1610 of the Atomic Energy Act of 1954,~as amended, 640.41(e) of 10 CFR Part 40,$$70.32(a)(8),70.32(b)(2),

and 70.32(b)(5) of 10 CFR Part 70, and $2.204 of 10 CFR Part 2, IT IS HEREBY ORDERED THAT within 180 days of the effective date of this Order, the liceisee shall submit:

1.

A radiological contingency plan in accordance with Enclosure 1 of this Order, " Standard Format and Content for Radiological Contingency.

Plans for Fuel Cycle and Materials Facilities," and an application

.~,.,.-

-A Gem ^46a W& e Mw 4 M M @r&-

  • @4

.m6 e

4 s.se +

a y

ee +e

'M 4 64

=m.

~a.e

.g q

N P& @ m p

g

. for license amendment to incorporate such clan as approved as a condition of the license; or alternatively, 2.

An application for license amendment to reduce the possession limits for radioactive materials below those specified in Enclosure 2 of this Order.

VI The licensee or any person whose interest may be affected by this Order may, within 20 days of the date of the Order, request a hearing with respect to all or part of the Order.

A request for a hearing shall be addressed to the Secretary of the Ccemission, U.S.N.R.C., Washington, D.C.

20555.

A copy of the hearing request shall also be sent to the Executive Legal Director, U.S.N.R.C., Washington, D.C.

20555. If a person other than the licensee requests a hearing, that person shall set forth with particularity the nature of his or her interest and the manner in which his or her interest may be affected by this Order in accordance with 10 CFR S2.714(a)(2) of the Commission's Rules of Practice.

If a hearing is requested by the licensee or a person who has an interest affected.by this Order, the Commission will ' issue an order designating the time and place of the hearing.

If no hearing is requested, this Order will become effective 20 days from the cate'of the Order.

If a hearing is requested, this Order.will become effective on the date specified in an order made following the hearing.

___.._-_T___._.._.

M4+

MWe

+m a

i

! VII If a hearing is held, the issue to be considered at the hearing shall be whether the licensee (1) shall submit a radiological contingency plan which complies with Enclosure 1 of this Order, " Standard Format and Content for 4

Radiological Contingency Plans for Fuel Cycle and Materials Facilities," or i

(2) if a plan is not submitted as required in Section V (1) of the Order, should an application for a license amendment to reduce its possession limits for radioactive materials below those specified in Enclosure 2 of this Order j

be submitted.

FOR THE NUCLEAR REGULATORY COMMISSION hey d' W

Richard E. Cunningham, Director Division of Fuel Cycle and Material Safety Dated at Silver Spring, Maryland this 1 kh day of February,1981 4