. SACRAMENTO MUNICIPAL UTILITY DISTRICT D P. O. Box 15830, Sacramento CA 95852-1830,(916) 452 3211 AN ELECTRIC SYSTEM SERVING THE HEART OF CAL.tFORNIA i
AGM/NUC 90-0'35' L
February -13,.'1990 ^
y U.:S. Nuclear Regulatory Commission F' '
' Attn:
Document Control Desk lHashington,DC-20555 i
- Docket No,'50-312 Rancho Seco Nuclear Generating Station
- License No. OPR-54 SPENT-FilfL POOL INVESTIGATION r
Attention:'. George Knighton lThis letter is to' inform you of a change in the' forecast dates for the Spent ~
Fuel Pool Investigation from those arcsented to the-Commission on January 24,.
1990,-at a meeting held at Rancho SOLO Nuclear Generating Station.
The anticipated changes'are shown on Attachment 1, which is a revised copy of a.
handout from the January 24, 1990 meeting.
This change in forecast dates was
- necessitated by a procurement delay on replacement parts for a traveling hoist which will-beLneeded to move spent fuel. racks, thus-delaying inspection and evaluation of the area under the racks.
Members 1of'your staff with questions requiring additional.information or y
clarification may contact' Rita Bowser at.(209) 333 2935, extension 4522.
Sincerely,
}
. Dan R. Keuter Assistant Genera 1' Manager J
~'
- Nuclear
- Y l
l Attachment 1
- cc.w/atch:
J. B. Martin, 'NRC, Halnut Creek G. Yuhas, NRC Halnut Creek A. D'Angelo, NRC, Rancho Seco 3
i i
):.
sM 9002230531 900213 h9
.j
{DR. ADOCKOS00gi2
/
p
' RANCHO SECO NUCLEAR GENERATING STATION O 1444o Twin Cities Road, Herdd, CA 95638 9799;(209) 333 2935
..j
~
x,;:
y SPENT FUEL POOL INVESTIGATION-PLANNED INVESTIGATION FORECAST
- COMPLETE
- Design / Procure Materials / Construct Rack Handling Fixture 43/90 5/24/90-
- Remove Spent Fuel Racks Adjacent to North Wall 4/10/90 6/8/90
- Evaluate Suspect Embedments 5/M/90
- Apply Sealant-
- Perform Weld Repairs
- Install " Drinking Bird" Flow Meter 3/14/90
- Evaluate Results 6/M/90 7/20/90
- Continue Search or Close Issue j
- Issue Final Report l