Staff Requirements Memo Re 900118 Immediate Effectiveness Review Briefing in Rockville,Md by Representatives of New Hampshire Yankee,Commonwealth of Ma & Other Parties Re Readiness to Operate Facility at Full Power
ML20006C281
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 01/31/1990
From: Chilk S
NRC OFFICE OF THE SECRETARY (SECY)
To: Taylor J
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
References
REF-10CFR9.7 M900118, NUDOCS 9002070267
Download: ML20006C281 (2)


Text

m J

l a

y:

q.

D

/

'og UNITED STATES IN RESPONSE, PLEASE

' F ',,.

Q NUCLEAR REGULATORY COMMISSION REFER TO:

M900ll8-i

,j W ASHIN GTON, D.C. 206S5 7

January 31, 1990 OFFEE OF THE SECRETARY I

3 MEMORANDUM-FOR:

James M. Taylor Stions Executive Director for Op 9

FROM:

Samuel J.

Chilk, Secreta

SUBJECT:

STAFF REQUIREMENTS - IMMIpI TE EFFECTIVE-NESS REVIEW BRIEFING - SEAE OOK, 9:00 A.M.,

THURSDAY, JANUARY 18, 1990, COMMISSIONERS' CONFERENCE ROOM, ONE WHITE FLINT NORTH, ROCKVILLE, MARYLAND (OPEN TO PUBLIC ATTENDANCE) i

.The commission

  • was briefed by the representatives of the New

- Hampshire Yankee (NHY) Division of Public Service of New Hampshire (PSNH) (Seabrook), the Commonwealth of Massachusetts, the Seacoast Anti-Pollution League, the New England Coalition I,

on Nuclear Pollution,'and the NRC staff on the readiness of tne 1

Seabrook Nuclear Power Plant, Unit 1 to operate at full power.

Representing PSNH were:

e l

- Edward A. Brown, President and CEO, NHY

- Ted Feigenbaum, Senior Vice President and H

Chief Operating Officer, NHY 1

c

- Bruce Drawbridge Executive Director for Nuclear Production, NHY

- George Gram, Executive Director of Emergency Preparedness and Community Relations, NHY~

Representing the Commonwealth of Massachusetts was:

- John Traficonte, Chief Nuclear Safety Unit Department of the Attorney General 9002070267 900131 PDR 10CFR PT9.7 PDC ot-

  • Commissioners Curtiss and Remick were not present.

en-:

y Representing Seacoast Anti-Pollution League was:

- Robert A. Backus Representing _ New England Coalition on Nuclear Pollution was:

- Diane Curran Chairman carr requested that PSNH provide the Commission with the age of the oldest maintenance item in the corrective i

maintenance' backlog and that the staff advise the Commission on when"they plan to do a maintenance team inspection at Seabrook.

l t

(Subsequently on January 23, 1990, the staff forwarded responses t

to Chairman Carr's questions.)

Chairman Carr thanked the participants and indicated that he expected that the Commission would conclude its immediate effectiveness review and reach a decision on the pending adjudicatory matters within two to three weeks.

cc:

Chairman Carr Commissioner Roberts

' Commissioner Rogers Commissioner Curtiss Commissioner Remick i

OGC GPA ACRS PDR - Advance f

DC - P1-24

-